Permit Information
Permit NumberBLD97-02549
StatusFinaled
Name AMERISUITES HOTEL
Site Address 925 MILWAUKEE ST
Project NameAMERISUITES HOTEL
Customer Number 
ePlanReviewNo
Description
AMERISUITES HOTEL * TO CONSTRUCT A FOUR STORY 70,754 SQ.FT. 128 ROOM HOTEL WITH EXERCISE ROOM, MEETING ROOMS, IN HOUSE LAUNDRY, AND ATTACHED 2478 SQ. FT. SWIMMING POOL ENCLOSURE. DR#8-97 CU-93-96 PC#561-97 FIRE SPRINKLERS USED FOR AREA.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  6/29/2004  
Case Summary (BLD)  6/14/2000 DONE
Permanent occupancy  10/15/1999 DONE
Perm. Occ. Cert. #7942 issued 10-15-99 to the Amerisuites Hotel.
BLD-Final10/8/199910/11/199910/9/1999APASS
Details
Final reinspect for the Amerisuites Hotel
Permanent Occupancy 10/8/199910/8/1999 DONE
Details
FIRE-Final Inspection10/7/199910/5/199910/5/1999PPASS
DetailsJoe Tawney
reinsp ok for permanent occupancy
INSP-Final Inspection5/12/19995/12/19995/12/1999PNR
DetailsJoe Tawney
05/12/99 406 - not ready allC/N items not completed
Code Occupancy Approval  4/28/1999 PASS
Inspected for Final. They did not put 2' berm at front of proj. - o.k.'d by TKW 4/28/99 - no parking in this area and no negative impact - nothing along here that a 2' berm could buffer. Meets compliance with DR-8-97. PASS
INSP-Conference1/22/19991/22/19991/22/1999 PART
DetailsJoe Tawney
/ / 406 - CHECKED LOCATION OF HYDRANTS AT SITE TO VERIFY ADEQUATE WATE OK
INSP - Final1/11/19991/11/19991/11/1999 PART
DetailsJoe Tawney
/ / 406 - REINSP OK FOR FULL TEMP OCC
INSP - Final1/11/19991/11/19991/11/1999 PART
Details
/ / 338 - MADE OK FOR TEMP SIGNED THE TEMP COLSTILL NEED HARD COPY OF
SUPER- Supervisor's review1/7/19991/7/19991/7/1999
temp issued some question on low level exit signs. problem resoved.
INSP - Final1/7/19991/7/19991/7/1999 PART
DetailsJoe Tawney
/ / 406 - FINAL OK FOR LIMITED TEMP OCC NO PUBLIC ACCESS AT THIS TIME.
SUPER- Supervisor's review1/7/19991/6/19991/6/1999
revied final process with inspectors. still not open will do finals and test dampers.
INSP - Final1/6/19991/6/19991/6/1999 PART
Details
/ / 338 - made ok for conditionaql temporary occ cert for hotel person
INSP-Final Inspection1/4/19991/5/19991/5/1999ANR
DetailsJoe Tawney
01/05/99 406 - Preston ###-#### FINAL NOT READY
Code Occupancy Approval  1/4/1999 FAIL
Bond posted for stripping & landscaping - $15,950.00
INSP - Final12/30/199812/31/199812/31/1998AFAIL
DetailsTom Arcoraci
12/31/98 408 - preston- ###-#### temp occ insp NOT READY WITH FIRE INSPECTOR
INSP-Final Inspection12/30/199812/31/199812/31/1998AFAIL
DetailsRick Jackson
preston- ###-#### fn fire insp tested sprinkler alarms only. corridors and stairtowers not complete.
INSP-Final Inspection12/31/199812/31/199812/31/1998 FAIL
DetailsRick Jackson
12/31/98 409 - preston- ###-#### fn fire insp tested sprinkler alarm portion only. stair towers and corridors, alarms
Temporary occupancy  12/31/1998 PASS
Temp. Occ. Cert. #3767 issued 12-31-98 to the Amerisuites Hotel (note special conditions on this t.o.)
INSP-Final Inspection12/14/199812/17/199812/17/1998APART
DetailsJoe Tawney
12/17/98 406 - ERIC PAGER ###-#### PER JOE 9:00 FN INSP
SUPER- Supervisor's review12/16/199812/16/199812/16/1998
profit in progress. perry keeper of record for all trades smooth so far.perry managing site
Fee Review-notes7/15/1998 12/15/1998
INSP-Conference12/14/199812/14/199812/14/1998 PART
DetailsJoe Tawney
/ / 406 - PROFIT MEETING WITH ALL INSPECTORS, CONTRACTOR AND SUB CONTR
SUPER- Supervisor's review12/14/199812/14/199812/14/1998
PROFIT MEETING. P. PAINE IN CHARGE. MIKE OTTO ATTENDING AS WELL AS ASSIGNED INSPECTORS. RULES SET. SHOULD GO WELL
INSP - Framing/Rough-in12/10/199812/11/199812/11/1998APART
Details
12/11/98 338 - made ok to drop in he tile in east hall 1st floor
INSP - Final12/10/199812/10/199812/10/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON HYDRO TEST OF 1ST & 2ND FLRS, OK ON BOOSTER PUMP TEST
INSP - Wall cover11/13/199811/16/199811/16/1998APART
Details
11/14/98 338 - PRESTON ###-#### WALL COVER INSP madeok to cover restroom
INSP - Framing/Rough-in11/9/199811/10/199811/10/1998AFAIL
Details
11/10/98 338 - PRESTON BAKER- ###-####-2ND FLOOR BATHROOMS fail penetrat
INSP - Framing/Rough-in11/6/199811/9/199811/9/1998APART
Details
11/09/98 338 - made ok to cover the 2nd floor and the rest of the 3rd fl
INSP - Framing/Rough-in11/4/199811/4/199811/5/1998PPART
DetailsTom Arcoraci
11/04/98 408 - 3RD FLOOR BATHROOM--PRESTON ###-#### ok to cover 3rd floor
INSP - Framing/Rough-in11/2/199811/2/199811/2/1998PPART
Details
11/03/98 338 - ok to cover east end of 4 th floor
INSP-Sprinkler Rough-in/Hydro10/27/199810/27/199810/27/1998 PART
DetailsJoe Tawney
/ / 406 - ok on hydro test of 3rd & 4th flrs, underground,FDC,DPV,& st
INSP - Framing/Rough-in10/22/199810/23/199810/23/1998APART
Details
10/23/98 338 - COVER INSPECTION PRESTON ###-#### ok to cover parts of th
INSP - Wall cover10/19/199810/20/199810/20/1998AFAIL
Details
10/20/98 338 - fire caulk putty pads not complet no cover
INSP - Wall cover10/15/199810/15/199810/15/1998PPART
Details
MADE K TO COVER 4TH FLOOR WALLS BETWEEN SUITES
INSP - Wall cover10/13/199810/13/199810/13/1998 PART
Details
/ / 338 - MADD OK RECIEVED ENG FIX FOR RE ROUT OF STORM DRAINS
INSP - Framing/Rough-in9/29/199810/13/199810/13/1998AFAIL
Details
10/13/98 338 - need eng for the holes cut in bearing/ demising walls
INSP - Wall cover10/9/199810/13/199810/13/1998APART
DetailsTom Arcoraci
10/13/98 408 - preston ###-#### done by 338
INSP - Framing/Rough-in9/29/199810/12/199810/12/1998ANR
Details
10/12/98 338 - will call for insp for 10-13-98
INSP - Framing/Rough-in9/29/199810/9/199810/9/1998APART
Details
10/09/98 338 - conference on the plans review and approved plans and the
INSP - Framing/Rough-in9/29/199810/8/199810/8/1998APART
Details
10/08/98 338 - made ok to cover the 1st floor all penetrations made ok.
INSP - Framing/Rough-in9/29/199810/7/199810/7/1998AFAIL
Details
10/07/98 338 - PROPER ASSYS NOT ON SITE NO INSP MADE
INSP - Framing/Rough-in9/29/199810/6/199810/6/1998ANR
Details
10/06/98 338 - not ready assys were not on site inspection will not be d
INSP-Supply line flush10/6/199810/6/199810/6/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON SUPPLY LINE FLUSH OK ON 4TH FLR ROUGH IN
INSP - Framing/Rough-in9/29/199810/5/199810/5/1998ANR
Details
10/05/98 338 - need fire stop info prior to inspection
INSP - Framing/Rough-in9/29/199810/2/199810/2/1998AFAIL
Details
subs do not have proper info not ready no insp completed
INSP - Framing/Rough-in10/2/199810/2/199810/2/1998 PART
Details
10/02/98 338 - MADE OK TO COVER PART OF THE 3RD FLOOR EAST END
INSP - Framing/Rough-in9/29/199810/1/199810/1/1998ACANC
DetailsTom Arcoraci
bob called early and said insp could wait til tomorroe as subs were all not ready
INSP - Framing/Rough-in9/29/19989/30/19989/30/1998AFAIL
Details
09/30/98 338 - not ready fire assys are not complete next not complete i
INSP - Framing/Rough-in9/30/19989/30/19989/30/1998PPART
Details
09/30/98 338 - made ok to cover the suite walls in the west of the 3rd a
INSP - Framing/Rough-in9/28/19989/29/19989/29/1998AFAIL
Details
09/29/98 338 - sheer wall bob ###-#### NOT REWADY FOR INSP OTHER AGENCIE
INSP - Wall cover9/24/19989/25/19989/25/1998APART
Details
09/25/98 338 - made ok for to cover the 2nd floor rooms only not hall
INSP-Sprinkler Rough-in/Hydro9/16/19989/16/19989/16/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON ROUGH IN OF 2ND FLOOR OK TO COVER
INSP - Framing/Rough-in9/4/19989/8/19989/8/1998AFAIL
Details
09/08/98 338 - NOT READY TO COVER C/N ISSUED FIRE ASSYS AND FIRE BLOCK A
INSP - Framing/Rough-in8/31/19988/31/19988/31/1998 NR
Details
08/28/98 338 - with m otto , P BAKER. B LEONARD. PLMER SUPER AND MYSELF
INSP - Framing/Rough-in8/28/19988/28/19988/28/1998PNR
Details
fireproofing/bob ###-#### this is a conf had m otto on site to answer questions on the fire proofing requirements and the rated wall assys
INSP - Conference8/14/19988/14/19988/14/1998 FAIL
DetailsAlan Hauser
/ / 350 - wanted underground pipe looked at, they don't have permit, c
INSP - Framing/Rough-in8/13/19988/13/19988/13/1998PPART
Details
08/13/98 338 - ok to start rocking as inspected
INSP - Framing/Rough-in8/11/19988/12/19988/12/1998APART
Details
08/12/98 338 - ok to cover bob ###-####
INSP - Wall cover8/11/19988/11/19988/11/1998PPART
Details
08/11/98 338 - conf with bob leonard and p baker on the use of approved
INSP - Wall cover8/7/19988/7/19988/7/1998PCANC
Details
this is for a conf only no framing is to be covered
INSP - Wall cover8/7/19988/7/19988/7/1998 PART
Details
08/07/98 338 - bob ###-#### struc. and wall need to supply ner 200 for t
INSP - Framing/Rough-in8/4/19988/5/19988/5/1998PNR
Details
08/05/98 338 - this is a conference to speak to the rated walls and fram attending Dave McKlenna, Bob Leonard, Prestom Baker and P Paine.Must rev
INSP - Framing/Rough-in8/3/19988/4/19988/4/1998ANR
Details
08/04/98 338 - NR NO ONE ON JOBSITE
CHANGE STATUS TO (I)  6/10/1998
INSP - Foundation6/8/19986/8/19986/8/1998PPART
Details
06/08/98 338 - Preston ###-#### FOOTINGS out of time will inspect 06-09-
INSP - Foundation6/3/19986/3/19986/3/1998PPART
Details
06/03/98 338 - MADE OK WITH SP INSP APPROVAL R-BAR IS PLACED
INSP - Foundation6/1/19986/2/19986/2/1998APART
Details
06/02/98 338 - made ok with sp insp for the west end only sp insp for th
Receive PAYMENT IN FULL PRINT  6/1/1998
PLANS/APPL TAKEN TO FRONT DESK  6/1/1998 PASS
FEES RECEIVED FOR RESUBMITTALS PLANS TAKEN TO FRONT DESK. MLO
INSP - Foundation5/27/19985/28/19985/28/1998APART
Details
AROUND 12:00-PRESTON ###-#### ok to pour only south and north walls
Plan assigned to (MLO)5/4/1998 5/28/1998 PASS
DetailsMike Otto
resubmittals for changes to approved permit submitted 05\04\98.
Plan Reviewer's activity  5/28/1998 PASS
FAX SENT TO ARCHITECT WITH COPY OF INVOICE OF FEES DUE. ARCHITECT INFORMED THAT FEES TO BE PAID PRIOR TO APPROVED MODFICATIONS BEING RELEASED.
Routing - PLAN CHECK5/27/1998 5/28/1998 PASS
REVIEW OF RESUBMITTALS COMPLETED. MLO
Telephone call  5/28/1998 PASS
CONTACTED PRESTON BAKER ABOUT RESUBMITTED PLANS AND FEES DUE. AMOUNT DUE IS 1332.50 WHICH WAS RELAYED TO BAKER. ALSO INFORMED BAKER THAT MODIFICATION FORM NEEDS TO BE FILLED OUT AND SIGNED AND THAT PLANS COULD NOT BE RELEASED UNTIL FEES DUE ARE PAID IN FULL. MLO
Telephone call  5/27/1998 PEND
PUT IN PHONE CALL TO KEITH JONES TO FIND OUT FEE DUE FOR ADDITIONAL REVIEW. HE SAID IT WOULD GET BACK TO ME IN A DAY OR SO. PLANS ON HOLD PENDING OUTSIDE ENGINEERING FEE AMOUNT. MLO
Routing Off Site - STRUCTURAL5/18/1998 5/27/1998 PASS
CORRECTIONS BY ATTWOOD-HINZMAN-JONES VERIFIED BY MLO.
INSP - Concrete5/18/19985/19/19985/19/1998PPART
Details
made ok with sp insp approval
Plan resubmittals received  5/18/1998 PEND
recieved resubmittals from Wieser Architects forwarded same to Mike O
Routing Off Site - STRUCTURAL5/7/1998 5/13/1998 FAIL
SENT RESUB TO KEITH JONES AT MIKE OTTO'S REQUEST.
Plan Reviewer's activity  5/13/1998 PEND
CHECKED WITH TEMPRA WILSON, PLANNING AND NO REVIEW REQUIRED FOR EXTERIOR CHANGES AT POOL HOUSE BREEEZEWAY AND SPANDREL GLASS IN FRONT AND REAR OF HOTEL AS SHOWN ON RESUBMITTALS DATED 5-4-98. MLO
Plan resubmittals requested  5/13/1998 FAIL
CORRECTIONS FORM THE CONSULTING ENGINEER HAVE BEEN RECEIVED AND FORWARDED ON TO THE ARCHITECT. MLO
INSP - Conference5/12/19985/12/19985/12/1998 PART
Details
/ / 338 - WITH OWNERS REP PROJECT SUPER AND SP INSP
Routing - PLAN CHECK5/4/1998 5/8/1998 PEND
INSP - Foundation5/7/19985/7/19985/7/1998PPART
Details
05/07/98 338 - made ok to pour south wall 100 ft. +-
Plan resubmittals received  5/4/1998
RECEIVED RESUBMITTALS AND GIVEN TO MIKE O.
(F) Reprint permit  4/2/1998
Issue PAID IN FULL permit  4/1/1998
Inspection Record Card- Bld  3/30/1998
Print Occupancy Form  3/30/1998
Telephone call  3/30/1998
called lafe feller gave him $ amount
PLANS/APPL TAKEN TO FRONT DESK  3/30/1998 PASS
Plan assigned to (M_O)9/23/1997 3/27/1998 PASS
Routing - PUBLIC WORKS3/23/1998 3/24/1998 PASS
Routing Off Site - A.C.H.D9/2/1997 3/24/1998 PASS
PACKAGE #4 CONTACTED CLINTON YAKA AT ###-#### TO TAKE PLANS OUT TO ACHD. ACHD FEES PAID RECEIPT # 98-0973 DAR 3/24/98 DAR
Routing - PUBLIC WORKS2/18/1998 2/20/1998 FAIL
PACKAGE #2 REQUIRES STREET LIGHT PLAN
Plan resubmittals received  2/12/1998
RECEIVED 3 COPIES OF STAMPED DRAWINGS. ROUTED TO MIKE O.
Plan resubmittals received  2/11/1998 FAIL
RECEIVED 2 COPIES OF BLUELINE SET - CHANGES TO AMERISUITES HOTEL 1 COPY LETTER CONTACTED LAFE FELLER TO LET HIM KNOW THAT THE PLANS NEED TO BE STAMPED AND SIGNED.
Routing - PLAN CHECK1/29/1998 2/3/1998 FAIL
CORRECTIONS ON REUSBMITTAL NOT COMPLETED. COMMENTS FAXED AND MAILED TO ARCHITECT. MO
Routing Off Site - STRUCTURAL12/5/1997 2/3/1998 PASS
RESUBS KEITH JONES HAD ONE ADDITIONAL COMMENT WHICH HAS BEEN MAILED TO THE ARCHITECT. MO
Routing - PLUMBING1/30/1998 1/30/1998 PASS
Plan resubmittals received  1/30/1998 PEND
PLUMBING RESUBS RECEIVED.
Plan resubmittals received  1/29/1998
RECEIVED 2 COPIES OF PARTIAL SET (BUILDING REVIEW SET) 2 COPIES OF PARTIAL SET (PLUMBING REVIEW SET) RECEIVED 1 COPY OF LETTER TO MIKE O. 1 CC OF LETTER MR. VARNER CONCERNING PLUMBING PLAN REVIEW OF 1-2-98. ROUTED ALL TO MIKE O. KMM
Plan resubmittals received  1/26/1998 PASS
SEE ACTION A103: RECEIVED THE ADDITIONAL REVISED SHEETS G2.3,A4.3,A5.3, AND COVER SHEET. ROUTED TO MIKE OTTO
Plan resubmittals received  1/23/1998 HOLD
RECEIVED ONE COPY OF UPDATED PLANS AND 2 COPIES OF RESPONSE LETTER. CONTACTED KEVIN OF WIESER ARCH. AND TOLD HIM I NEED 2 COPIES OF THE PLANS. HE WILL HAVE THEM TO US BY 1-26-98. KMM
SUPER- Supervisor's review1/5/19991/5/19981/5/1998
request for temp. w/o pool being completed. i told mec contractor to write letter with time frames, no use of that area.
Routing - FIRE12/15/1997 12/30/1997 PASS
PLANS BACK TO BLDG. PLAN REVIEW.
Plan resubmittals requested  12/12/1997 FAIL
CORRECTIONS ON RESUBMITTALS SENT TO ARCHITECT. MO
Routing - PLAN CHECK12/5/1997 12/12/1997 FAIL
CORRECTIONS ON RESUBMITTAL MAILED TO ARCHITECT 12-12-97.MO
Plan resubmittals received  12/5/1997 FAIL
90 day tracking............. 8/28/199711/26/1997
Plan Reviewer's activity  11/17/1997 FAIL
LETTER SENT TO LAFE FELLER CONCERING USE OF FIRE RATED WOOD IN EXTERIOR WALLS OF TYPE III-1HR IN COMBINATION WITH E.I.F.S. SYSTEMS. MO
Routing - FIRE10/14/1997 10/29/1997 FAIL
PACKAGE #1
Plan resubmittals requested  10/13/1997 FAIL
CORRECTIONS MAIELD TO ARCHITECT. MO
Routing - PLAN CHECK9/23/1997 10/13/1997 FAIL
CORRECTIONS MAILED TO ARCHITECT. MO
Routing Off Site - STRUCTURAL9/9/1997 10/3/1997 FAIL
PACKAGE #3 ON HOLD UNTIL I RECEIVE A THIRD SET OF PLANS FROM CLINTON. I NOTIFIED HIM OF THIS NEED. KMM 9-9-97 RECEIVED THIRD SET. CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD, HINZMAN, AND JONES. CORRECITIONS MAILED WITH BUILDING CORRECTIONS 10-13-97. MO
Routing - PLANNING9/24/1997 9/26/1997 PASS
PACKAGE #2 CU-93-96 & DRH97-0008. APPROVED BY TKW & RC.
Routing - PUBLIC WORKS9/10/1997 9/24/1997 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN REVISIONS. BM RREQUIRES STREET LIGHT PLAN. BILL COLSEN
Plan assigned to (RGG)9/2/1997 9/23/1997 PASS
Routing - PLUMBING9/15/1997 9/16/1997 FAIL
PACKAGE #1 PROVIDE SITE DRAWINGS INDICATING MAIN WATER AND SANITARY SEWER SOURCE -LOCATION - SIZE.
Routing - ELECTRICAL9/2/1997 9/15/1997 PASS
PACKAGE #1 NO REVIEW FIELD VERIFY
Routing Off Site - C.D.H9/2/1997 9/9/1997 PASS
PACKAGE #2 CONTACTED CLINTON YAKA AT ###-#### TO TAKE PLANS OUT TO CDH.
Received Certificate of Value  9/2/1997 PASS
Plan routing begun/NEW & ADDTN  9/2/1997 PASS
Routing - MECHANICAL9/2/1997 9/2/1997 PASS
PACKAGE #1 NO REVIEW FIELD VERIFY.
Plan assigned to (MYS)8/28/1997 9/2/1997
DetailsMarlene Southard
Plans ACCEPTED BY PLAN CHECK  9/2/1997 PASS
AM HOLDING PACKAGE #3 (WHICH REQUIRES AN ADDITIONAL SET), UNTIL I RECEIVE A THIRD SET. CONTACTED CLINTON YAKA OF THIS NEED. KMM
Application received  8/28/1997
Recd Pcfee & Taken To Pln CK  8/28/1997
Routing - PLUMBING12/31/1997 1/5/1997 FAIL
Routing - PLAN CHECK2/20/1998 2/23/1938 PASS
SUPER- Supervisor's review6/18/1998   D
pre constuction meeting. perry ran show plan review notes reviewed subs their, inspectors their. well done, 75% of plan review notes were ada requirments and should be on the approved plan not just notes. policy is inspectors are to do exactly what the plan has for ada. The architect is responsible and plan review is in sole charge of checking against the ada documents. Questions on ada were to be refered to plan review and not answored by inspectors in the field.