Information based on query as of Saturday, July 20, 2024.
Permit Information
Permit NumberBLD97-02761
StatusFinaled
Name MIKE MARRS
Site Address 6169 S SETTLEMENT WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
TO BUILD A 2597 SF TWO STORY SFD( 1265 SF 1ST FL; 1332 SF 2ND FL.) WITH AN ATTACHED 730 SF GARAGE, A 105 SF COVERED DECK OVER THE BACK OF THE GARAGE, AND A 110 SF CONCRETE PORCH PER APPROVED PLANS AND SPECIFICATIONS. ACHD#97-1968 PC#714. 340CD.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Letter of compliance1/28/19981/28/19981/28/1998 PASS
DetailsRuss Owen
/ / 407 - LC#14367
INSP - Letter of compliance1/28/19981/28/19981/28/1998 PASS
DetailsRuss Owen
/ / 407 - LC#14367
INSP - Letter of compliance1/27/19981/27/19981/27/1998 PASS
DetailsRuss Owen
/ / 407 - LC#14367
INSP - Letter of compliance1/27/19981/27/19981/27/1998 PASS
DetailsRuss Owen
/ / 407 - LC#14367
INSP - Energy code compliance11/14/199711/17/199711/17/1997APASS
DetailsJim Storey
11/17/97 301 - INSL-OK INSULATION-ENERGY CODE
INSP - Framing/Rough-in11/14/199711/17/199711/17/1997APASS
DetailsJim Storey
11/17/97 301 - FRAM-OK FRAMING
INSP - Framing/Rough-in11/12/199711/13/199711/13/1997PFAIL
DetailsWes Worcester
11/13/97 342 - TRUSS ENG, BLOCKING, SHEAR TRMMR NOT FULL HEIGHTH, OK TO
INSP - Wall cover11/3/199711/4/199711/4/1997APASS
DetailsTom Arcoraci
SHEER AND HOLD DOWN
Routing - PLAN CHECK9/22/1997 10/8/1997 PASS
(F) Reprint permit  10/8/1997
Inspection Record Card- Bld  10/8/1997
Routing - PLAN CHECK10/2/1997 10/8/1997 PASS
Issue PAID IN FULL permit  10/8/1997
Plan assigned to (DJO)9/18/1997 10/3/1997 PASS
DetailsDan Overy
10/03/97 16:13:48 340 - this action updated by action script from <<>> in Case No. BLD97-2761
testing condition printout  10/3/1997 PASS
Plan Reviewer's activity  10/3/1997 PASS
REC'D ENG'G
Plan resubmittals requested  10/3/1997 PASS
REQUESTED REDLINE PLAN TO ATTACH TO PLANS
Print permit w/o conditions  10/3/1997 PASS
PLANS/APPL TAKEN TO FRONT DESK  10/3/1997 PASS
ASAP
Routing - PUBLIC WORKS9/19/1997 10/2/1997 PASS
re-sent to public work
INSP - Footings9/22/19979/22/19979/23/1997PPART
DetailsRuss Owen
09/22/97 407 - no approved plot plan,construction,talked with Bob the jo there was an easment.I told him to provide something which showed easeme the 5 foot set back he said he would. poured at there own risk.
Print Pending Permit.LaserJet4  9/19/1997
Application received  9/18/1997
Routing - PLANNING9/18/1997 9/18/1997 PASS
APPROVED BY RW.