Permanent Occupancy | | 3/5/1998 | 3/5/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/5/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7160 issued 3-5-98 to McRae's Cleaners.
|
INSP - Final | 3/3/1998 | 3/4/1998 | 3/4/1998 | P | PASS |
Jim Sly
|
|
|
03/04/98 316 - Final Occ OK phone is [3841888].
|
INSP-Final Inspection | 3/4/1998 | 3/4/1998 | 3/4/1998 | P | PASS |
Rick Jackson
|
|
|
all items corrected, occ approved
|
INSP - Final | 2/20/1998 | 2/20/1998 | 2/20/1998 | | PART |
|
|
|
Structural ok need other signoffs for final.Ok for temp. occ.
|
INSP - Final | 2/20/1998 | 2/20/1998 | 2/20/1998 | P | CANC |
Carl Dependahl
|
|
|
temp occ. mcrae's cleaners ###-#### paul GAVE TO BOB A
|
INSP-Final Inspection | 2/17/1998 | 2/18/1998 | 2/18/1998 | P | PART |
Rick Jackson
|
|
|
life safety ###-#### mobile mike no smoking sign and hazard placard.
|
INSP - Framing/Rough-in | 1/8/1998 | 1/8/1998 | 1/8/1998 | P | PASS |
Jim Sly
|
|
|
01/08/98 316 - reinspection OK
|
INSP - Framing/Rough-in | 1/6/1998 | 1/7/1998 | 1/7/1998 | A | FAIL |
Jim Sly
|
|
|
01/06/98 316 - C/N...Need firestops at 1hr walls/ceiling....
|
INSP - Misc. complaint | 12/31/1997 | 12/31/1997 | 12/31/1997 | | PART |
|
|
|
Released hold on inspections, Architect promised to submit as-built plumbing plan for project. Plumbing plan to be submitted and approved proir to occupancy approval.
|
INSP - Misc. complaint | 12/31/1997 | 12/30/1997 | 12/30/1997 | | FAIL |
|
|
|
placed hold on all inspections for non-compliance with plumbing correction notice requiring plumbing resubmittal on 12/10/97. Follow up verbal and written requests also not complied with.
|
90 day tracking............. | | 9/29/1997 | 12/28/1997 | | PEND |
|
|
|
|
Issue PAID IN FULL permit | | | 12/1/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/26/1997 | | PASS |
|
|
|
ISSUE
|
Inspection Record Card- Bld | | | 11/26/1997 | | |
|
|
|
|
Print Occupancy Form | | | 11/26/1997 | | |
|
|
|
|
Telephone call | | | 11/26/1997 | | |
|
|
|
left message for mike gorringe that permit was ready on recorder
|
Plan assigned to (PRP) | 10/2/1997 | | 11/26/1997 | | PASS |
|
|
|
waiting resub for Ventalation 11/24/97 08:52:56 PRP - this action updated by action script from <<>> in Case No. BLD97-2881 11/26/97 08:14:48 PRP - this action updated by action script from <<>> in Case No. BLD97-2881
|
Routing - FIRE | 11/24/1997 | | 11/25/1997 | | PASS |
|
|
|
|
Routing - FIRE | 10/27/1997 | | 10/28/1997 | | FAIL |
|
|
|
|
Routing - FIRE | 10/22/1997 | | 10/23/1997 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 10/21/1997 | | PEND |
|
|
|
REVIEWED PLANS, CALLED ARCH FOR CLEANING FLUID MATERIAL CONFIRMATION, SUITE #, DID PLAN REVIEW AND INPUT TO TIDEMARK, FORWARD TO FIRE. NO CORRECTIONS
|
Print Pending Permit.LaserJet4 | | | 10/21/1997 | | PASS |
|
|
|
FILES
|
Routing - PUBLIC WORKS | 10/3/1997 | | 10/13/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 9/29/1997 | | 10/2/1997 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 10/2/1997 | | |
|
|
|
Route to PUBLIC WORKS then to PLAN CHECK. After Plan Check route to FIRE DEPARTMENT.
|
Application received | | | 9/29/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 9/29/1997 | | |
|
|
|
|