Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD97-02891
StatusFinaled
Name DIAMOND CONSTRUCTION
Site Address 2404 S ORCHARD ST
Project NameDAVIS COMM/RETAIL
Customer Number 
ePlanReviewNo
Description
COMMERCIAL/RETAIL SPACE FOR BRENT DAVIS * TO CONSTRUCT A 23,500 SQ. FT. MASONRY BLOCK BUILDING SHELL & CORE. TO CONSTRUCT A FOUR HOUR AREA SEPARATION WALL TO CREATE TWO SEPARATE BUILDING AREAS DO TO WATER FIRE FLOW AT BUILDING PROJECT LOCATION. TO BE LOCATED AND CONSTRUCTED AS SHOWN ON PLANS. NOTE: SEPARATE MISCELLANEOUS TENANT IMPROVEMENT PERMITS FOR SCUBA SALES/TRAINING POOL TENANT; ACTIVE WEAR RETAIL TENANT AND SULLIVAN DENTAL SUPPLY TENANT, ARE BEING ISSUED WITH THIS PLAN FOR PURPOSE OF CERTIFICATE OF OCCUPANCY ISSUANCE. PLANS, PLAN REVIEW COMMENTS AND FEE'S FOR SHELL AND CORE AND TENANT IMPROVEMENTS ARE A PART OF THIS PERMIT. THE BUILDING IS NOT SPRINKLED. UNFINISHED SHELL & CORE AREAS AS SHOWN ON PLANS WILL REQUIRE SEPARATE SUBMITTAL OF APPLICATIONS; PLANS FOR REVIEW, APPROVAL & ISSUANCE OF PERMITS FOR EACH PROPOSED FUTURE TENANT. SOME CODE ISSUES REMAIN TO BE ADDRESSED PRIOR TO CERTAIN STAGES OF THE CONSTRUCTION. SEE PLAN REVIEW COMMENTS ATTACHED TO THE APPROVED PLANS. A LETTER OF COMPLIANCE IS REQUIRED FOR SHELL & CORE CONSTRUCTION PRIOR TO ISSUANCE OF A CERTIFICATE OF OCCUPANY FOR ANY OF THE INDIVIDUAL TENANTS. DR-61-97 PC#622-97/JML
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  9/18/2014 DONE
BLD-Final12/18/201312/18/201312/18/2013PDONE
DetailsAdele J Schaffeld-Griffin
I am finalling out this permit as the only outstanding item was planning and zonning. Sara has made a site visit and is signing off on the project. I did not make a site visit but reviewed and closed out all existing permits. With that done this part, core and shell is completed. 12/18/13 ajs
Zoning Approval12/18/201312/18/201312/18/2013 PASS
DetailsSarah Schafer
to final out core and shell permit
Override - Parcel Holds  12/18/2013  
CHANGE STATUS TO (FNL)  12/18/2013 DONE
DetailsAdele J Schaffeld-Griffin
Override - Parcel Holds  12/18/2013  
Case Summary (BLD)  2/18/2004  
Case Summary (BLD)  9/22/2003  
Code Occupancy Approval  2/9/1999 PASS
MISSING TRASH DUMPSTER LOCATION WITH BRICK WALL, TWO TREES ARE MISSING BUT THEY RECEIVED AN OK TO DO SO. MADE SITE INSPECTION 2-8-99, DUMPSTER SCREENING IN AS REQUIRED, ALL OTHER CONDITIONS OF APPROVAL COMPLETED, NOTIFED CARL OF COMPLETION AS I AM UNABLE TO FIND CARD TO SIGN OFF.
INSP-Final Inspection7/7/19987/8/19987/8/1998APART
DetailsJoe Tawney
07/08/98 406 - kEVIN 8705915 REINSP OK FOR TEMP OCC
INSP - Final7/7/19987/8/19987/8/1998APART
Details
07/08/98 338 - SIGNED THE OCC REQ CARD IN THE TEMP COL
INSP-Final Inspection7/7/19987/7/19987/7/1998PFAIL
DetailsJoe Tawney
07/07/98 406 - Kevin ###-#### FINAL FAIL DAMPERS & SMOKE SEALS IN RATED CORRIDOR
INSP - Final7/7/19987/7/19987/7/1998PNR
Details
07/07/98 338 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Final6/30/19987/1/19987/1/1998ANR
Details
07/01/98 338 - kevin ###-#### coorections not complete over allowed glaz
INSP-Final Inspection6/30/19986/30/19986/30/1998PNR
DetailsJoe Tawney
06/30/98 406 - Kevin ###-#### NOT READY FOR INSP
SUPER- Supervisor's review6/9/19986/9/19986/9/1998 PEND
SWO by Perry. Conference w/contractor.
INSP - Framing/Rough-in6/9/19986/9/19986/9/1998PFAIL
Details
ceiling inspection ###-#### NOT READY FOR INSP COVERED W/O FRAME INSP 1-HOUR CEILING NOT COMPLETE ETC
INSP - Framing/Rough-in2/17/19982/18/19982/18/1998ANR
DetailsWes Worcester
02/18/98 342 - ###-#### ROOFING NO ONE THERE, NO LADDER, ROOF ONLY PARTI
INSP - Roof2/18/19982/18/19982/18/1998 NH
DetailsWes Worcester
/ / 342 - NO ANSWER AT JOB SITE, ANSWERING MACHINE ONLY, I WILL GO BYE
(F) Reprint permit  1/13/1998
INSP - Conference1/7/19981/7/19981/7/1998 PASS
Details
/ / 333 -
INSP-Conference1/7/19981/7/19981/7/1998 PASS
DetailsJoe Tawney
/ / 406 - ATTENDED PRE CONSTR CONFERENCE NO QUESTIONS WERE ASKED
INSP - Miscellaneous1/5/19981/5/19981/5/1998PPART
Details
01/05/98 338 - masonary block made ok with sp insp approval
INSP - Foundation12/31/19971/2/19981/2/1998PPART
Details
01/02/98 333 - ok pending special insp report he will call you.
CHANGE STATUS TO (I)  12/31/1997
Issue PAID IN FULL permit  12/31/1997
Issue PAID IN FULL permit  12/31/1997
Print Occupancy Form  12/31/1997
Inspection Record Card- Bld  12/31/1997
Inspection Record Card- Bld  12/31/1997
Routing - PLAN CHECK12/11/1997 12/31/1997 PASS
PACKAGE #2
Routing Off Site - A.C.H.D10/2/1997 12/31/1997 PASS
PACKAGE #4 CONTACTED BRENT DAVIS AT ###-#### TO TAKE PLANS OUT TO ACHD ACHD FEES PAID. RECEIVED COPY OF RECEIPT AT 1:30PM 12/26/97 ADVISED THE BRENTS THAT THE PLANS FROM ACHD MUST BE SIGNED AND RETURNED PRIOR TO A PERMIT BEING ISSUED. 12/31/97 - Larry Sales talked to Tim Hogland and released the plans verbally, then the contractor went to ACHD and picked up plans.
Routing - PLAN CHECK11/26/1997 12/31/1997 PASS
PACKAGE #1
Plan assigned to (JML)11/14/1997 12/31/1997 PASS
Details
Print Pending Permit.LaserJet4  12/29/1997 PASS
Print Pending Permit.LaserJet4  12/29/1997 PASS
90 day tracking............. 9/29/199712/28/1997
Print Pending Permit.LaserJet4  12/26/1997 PASS
Print Pending Permit.LaserJet4  12/26/1997 PASS
Routing - FIRE12/24/1997 12/26/1997 PASS
Print Pending Permit.LaserJet4  12/24/1997 PASS
PERMIT BEING PROCESSED UNDER THE DIRECTION OF MARLENE SOUTHARD AND TIM HOGLAND WITH OUTSTANDING ITEMS TO BE SATISFIED PRIOR TO OCCUPANCY
Plan Reviewer's activity  12/24/1997 PASS
DIRECTED BY IMMEDIATE SUPERVISOR MARLENE SOUTHARD AND THE BUILDING OFFICIAL TIM HOGLAND TO DO WHAT IS NECESSARY TO ISSUE THIS PERMIT TODAY. ANY OUTSTANDING ITEMS WILL BE NOTED ON THE PLANS AND IN THE PLAN REVIEW COMMENTS ATTACHED. THE FINAL RESUBMITTAL BY THE ARCHITECH WERE RECEIVED ATFER 2:30 ON THIS DAY. ACHD FEES HAD NOT BEEN PAID AND THE FIRE DEPARTMENT HAD NOT SIGNED OFF. JML
Telephone call  12/15/1997 PEND
OSCAR OF LARRY KNOPP ARCH. CALLED ON 12-12-97 RE: MY REVIEW OF HIS RESUBMITTAL. I TOLD HIM MY NEW FINDINGS AND THAT THEY HAD NOT BEEN TYPED UP YET.
Plan resubmittals received  12/15/1997 PEND
recieved 12-10-97
Plan Reviewer's activity  12/15/1997 FAIL
FAXED AND MAILED A RESPONSE TO RESUBMITTED PLANS WHICH WERE CHANGED FROM A SPRINKLED V-N TO A NON-SPRINKLED V-N WITH TWO AREA SEPARATION WALLS. THIS ELIMINAATES THE NEED FOR SPRINKLERS FOR BOTH ALLOWABLE AREA AND > 12000 SF M OCC.
Routing - PLANNING12/11/1997 12/11/1997 PASS
X-REF: DRH97-0061. APPROVED BY MGS.
Plan resubmittals received  12/10/1997
RECEIVED 2 REVISED SETS ONE LETTER FROM LARRY KNOPP REGUARDING PLAN CHENCK ITEMS REQUIRING A REPONSE. TWO SETS OF REVISED STRUCTURAL CALCULATIONS.
Routing - FIRE11/24/1997 11/26/1997 FAIL
Plan resubmittals requested  11/21/1997 PEND
SENT PLAN REVIEW NOTES TO ARCHITECT ON 11-20-97 BY LETTER - SENT TO FIRE 11-21-97 - NEEDS RESUBMITTAL
Routing - PUBLIC WORKS11/19/1997 11/19/1997 PASS
Package #2.
Plan assigned to (RGG)10/2/1997 11/14/1997 PASS
Routing - PLANNING11/14/1997 11/14/1997 PEND
X-REF: DRH97-0061. APPROVED FOR GRADING ONLY! APPROVED BY MGS.
Routing - PUBLIC WORKS11/12/1997 11/13/1997 FAIL
PACKAGE #2 REQUIRES 3 MORE COPIES OF DRAINAGE PLANS. REQUIRES STREET LIGHT PLAN BILL COLSON.
Routing - PUBLIC WORKS11/3/1997 11/10/1997 FAIL
PACKAGE #2 REQUIRES DRAINAGE PLAN (3 MORE COPIES) PER BRIAN MURPHY REQUIRES STREET LIGHT PLAN PER BILL COLSON
Routing - FIRE11/3/1997 11/6/1997 PEND
PACKAGE #1 GRADING ONLY GRADING PERMIT PASSED BY FV ON 11/06/97
Routing - PLANNING10/23/1997 10/31/1997 FAIL
PACKAGE #2 Denied by: MGS Plans do not comply with DR conditions of approval. Applicant needs to provide revised plans.
Routing Off Site - C.D.H10/2/1997 10/22/1997 PASS
PACKAGE #2 CONTACTED BRENT DAVIS AT ###-#### TO TAKE PLANS OUT TO CDH REVIEW NOT REQUIRED PER SUSIE SIMMONS. LETTER ATTACHED TO PLANS AND A COPY IS IN THE FILES FOR 2404 SOUTH ORCHARD.
Routing Off Site - STRUCTURAL10/1/1997 10/17/1997 PEND
WE ARE DOING ENGINEERING PER JOHN M.
Routing - PLUMBING10/7/1997 10/7/1997 PASS
PACKAGE #1
Routing - ELECTRICAL10/2/1997 10/7/1997 PASS
PACKAGE #1
Plan routing begun/NEW & ADDTN  10/2/1997 PASS
WE ARE DOING ENGINEERING PER JOHN MENARD.10-1-97
Received Certificate of Value  10/2/1997 PASS
Plans ACCEPTED BY PLAN CHECK  10/2/1997 PASS
Plan assigned to (MYS)9/29/1997 10/2/1997
DetailsMarlene Southard
Routing - MECHANICAL10/2/1997 10/1/1997 PASS
PACKAGE #2 NO REVIEW FIELD VERIFY.
Application received  9/29/1997