Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD97-02908
StatusFinaled
Name MCGRATHS PUBLICK FISH HOUSE #9
Site Address 1749 S COLE RD
Project NameMCGRATH'S FISH HOUSE
Customer Number 
ePlanReviewNo
Description
McGrath's fish house * new construction of an 8038 sq. ft. restaraunt facility including adjoining on-site facilities and services. Fully fire sprinkled because of the drinking facility involved. The building is aV-N single story with the allowable area gained by yards. It is an A-3 occupancy with an accessory kitchen ( B occupancy ). Construction to be as per the attached comment, the 1994 UBC and CABO/ANSIA117.1-1992. grading permit bld 97-3295 DRH97-0153 DR-22-97 MOD PC#710-97 jml
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  8/18/1998 PASS
Perm. Occ. Cert. #7355 issued 8-18-98 to McGrath's Publick Fish House #99.
Permanent Occupancy 8/17/19988/17/1998 DONE
Details
INSP-Final Inspection8/5/19988/5/19988/5/1998PPASS
DetailsJoe Tawney
08/05/98 406 - ###-#### please call he will need to meet you out there REINSP OK FOR PERM OCC
Code Occupancy Approval  6/22/1998 PASS
Bonded for temporary - $1,600 for remaining landscaping. Inspected for Final 6/22/98 - Meets compliance with DRH97-0153-PASS
Temporary occupancy  6/19/1998 PASS
Temp. Occ. Cert. #3636 issued 6-19-98 to McGrath's Fish House.
INSP-Final Inspection6/18/19986/18/19986/18/1998PPART
DetailsJoe Tawney
06/18/98 406 - final jim ###-#### REINSP OK FOR TEMP OCC ADDRESS RISER ROOM AIR BALANCE REPORT
INSP - Final6/18/19986/18/19986/18/1998PPART
Details
06/18/98 338 - made ok for temp occ, life safety and plmg ele are temp.
INSP-Final Inspection6/16/19986/16/19986/16/1998PFAIL
DetailsJoe Tawney
06/16/98 406 - Jim ###-#### REINSP FAIL FEW ITEMS LEFT FOR TEMP AND FINAL
INSP-Final Inspection6/11/19986/12/19986/12/1998AFAIL
DetailsJoe Tawney
06/12/98 406 - temp occ. arround 11 a.m. ###-####/ FINAL FAIL ANSUL SYSTEM TESTS EMERG AND EXIT LIGHTS
INSP-Sprinkler Rough-in/Hydro6/11/19986/11/19986/11/1998PFAIL
DetailsJoe Tawney
06/11/98 406 - sprinkler ###-#### jim FINAL FAIL ALARM SYSTEM EXIT AND EMERG LIGHTS
INSP - Framing/Rough-in6/4/19986/5/19986/5/1998APART
Details
06/05/98 338 - final on ceiling/ ###-#### jim ceiling grid ok to drop in the tiles willcheck slack wires again at the
INSP-Sprinkler Rough-in/Hydro6/3/19986/3/19986/3/1998 PART
DetailsJoe Tawney
/ / 406 - OK ON ABOVE GROUND HYDRO TEST
INSP-Conference6/1/19986/1/19986/1/1998 PART
DetailsJoe Tawney
/ / 406 - CONF ON TAMPER SWITCHES FOR ANTI FREEZE LOOP VLVS
INSP-Conference5/27/19985/27/19985/27/1998 PART
DetailsJoe Tawney
/ / 406 - PROFIT CONFERENCE WANT OCC BY 6/19/98
INSP - Final5/20/19985/21/19985/21/1998APASS
Details
OK TO COVER THE SHAFTS
INSP - Framing/Rough-in5/19/19985/20/19985/20/1998APART
Details
grease duct chase ###-#### they are to recall whith verbal correction repairs
Plan resubmittals received  5/20/1998 PEND
RECEIVED RESUBS FROM DAVE BECK. FORWARDED TO PW AND PLUMBING.DAR
INSP - Framing/Rough-in5/13/19985/14/19985/15/1998APASS
Details
05/15/98 338 - grease chase ###-#### FAIL BAD CLEARANCES AND POOR WORKM
INSP - Framing/Rough-in4/20/19984/21/19984/21/1998APART
Details
04/21/98 338 - approved and posted resubmittals for the duct shaft attac
INSP - Framing/Rough-in3/30/19983/31/19983/31/1998APART
Details
made ok to insulate ext walls only
INSP-Supply line flush3/25/19983/26/19983/26/1998APASS
DetailsJoe Tawney
03/26/98 406 - 8:30 AS PER 406-GREGG ###-#### DIGITIAL OK ON UNDERGROUND FLUSH
INSP - Framing/Rough-in3/17/19983/18/19983/18/1998PPART
Details
03/18/98 338 - sheer wall roof sheathing nailing harold ###-####
(F) Reprint permit  1/12/1998
(F) Reprint permit  1/12/1998
Issue PAID IN FULL permit  1/9/1998
Inspection Record Card- Bld  1/9/1998
Print Occupancy Form  1/9/1998
(F) Reprint permit  1/9/1998
PLANS/APPL TAKEN TO FRONT DESK  1/9/1998 PASS
Plan assigned to (JML)11/14/1997 1/9/1998 PASS
Details
Print Pending Permit.LaserJet4  1/8/1998 PASS
Plan Reviewer's activity  1/8/1998 PEND
I faxed to Scott Beck a cover sheet informing him that all departments had approved the project for issuing a permit except for ACHD. We need verification of fees paid and approval from ACHD.
Plan Reviewer's activity  1/8/1998 PASS
Routing Off Site - A.C.H.D1/8/1998 1/8/1998 PASS
received ACHD receipt # 98-0542
Routing Off Site - STRUCTURAL12/19/1997 12/31/1997 PASS
RESUBMITTALS RECEIVED AND SENT OUT TO ATWOOD HINZMAN AND JONES VIA PDQ SENT THREE SETS OUT. RESUBMITTALS APPROVED 12-31-97 BY AHJ
90 day tracking............. 9/29/199712/28/1997 PEND
Plan resubmittals received  12/22/1997 PEND
RESPONSE TO STRUCTURAL NON-STRUCTURAL AND MECH PLAN REVIEWS RECIEVED (PLANS CALC'S 3-EACH & LETTER)
Routing - FIRE12/4/1997 12/12/1997 FAIL
PACKAGE #1 APPROVED FOR GRADING ONLY. BLD97-3295
Routing - PLUMBING12/3/1997 12/4/1997 PASS
Plan Reviewer's activity  12/2/1997 PEND
The review is completed, a response and corrections are required from the architect. I will send to fire for review.
Meeting  12/1/1997 PEND
Meet with Scott Beck in our office and gave him a copy of my plan review comments minus the respose from the structural consultant. I told him I would contact the consultant to see where thier response was. I did so and found out they had responded earlier but we had no record of it so they faxed me a copy. I will transmit a copy of the fax to Scott Bec , the architect.
Routing - ELECTRICAL11/14/1997 11/21/1997 PASS
PACKAGE #1
Routing - PUBLIC WORKS11/18/1997 11/18/1997 PASS
Plan assigned to (RGG)10/6/1997 11/14/1997 PASS
Routing - PUBLIC WORKS11/13/1997 11/13/1997 FAIL
Routing - PLANNING11/7/1997 11/12/1997 PASS
PACKAGE #1 X-REF: DRH97-0022,DRH97-0153. APPROVED BY MGS.
Routing - PLUMBING11/4/1997 11/7/1997 FAIL
PACKAGE #1
Routing Off Site - STRUCTURAL10/6/1997 11/6/1997 FAIL
PACKAGE #3 CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN JONES RECEIVED CORRECTIONS AND REQUESTING KNEW PLANS TO BE SUBMITTED FOR FUTHER REVEIW ABY ATWOOD HINZMAN AND JONES.
Plan resubmittals received  11/3/1997
SHEETS; AO.O, A4.3, A5.1, A5.2, A7.1, A8.2, A8.3, P2.1, E3.2, E5.1, AND REVISED PROJECT MANUELS. (3 SETS OF SHEETS AND 2 MANUELS.)
Routing - PUBLIC WORKS10/28/1997 10/31/1997 FAIL
PACKAGE #1 REQUIRES DRAINAGE PLAN (MORE COPIES) BM INCOMPLETE FIXTURE INFORMATION FOR BAR AREA,ARDEN BAUMAN
Routing Off Site - A.C.H.D10/6/1997 10/10/1997 PASS
PACKAGE #2 CONTACTED BRIAN HUFFAKER ###-#### TO TAKE PLANS OUT TO ACHD FEES DUE FEES PAID 1-8-98
Plans ACCEPTED BY PLAN CHECK  10/6/1997 PASS
REQUIRES SITE PLAN SHEETS. CONTACTED SCOTT BECK OF THIS NEED. I AM GOING TO STILL ROUTE TO CDH FIRST,PW, PLUMB. THEN P.& Z.
Plan routing begun/NEW & ADDTN  10/6/1997 PASS
Routing - MECHANICAL10/6/1997 10/6/1997 PASS
NO REVEIW FIELD VERIFY PACKAGE #1
Routing - PLAN CHECK9/29/1997 9/29/1997 PEND
Received Certificate of Value  9/29/1997 PASS
Application received  9/29/1997
Plan assigned to (MYS)9/29/1997 9/29/1997
DetailsMarlene Southard
Routing - FIRE1/5/1998 1/6/1997 PASS
Routing Off Site - C.D.H10/6/1997 10/28/1907 PASS
PACKAGE #1 CONTACTED BRIAN HUFFAKER AT ###-#### TO TAKE PLANS OUT TO CDH