Fee Review-notes | 7/14/1998 | | 10/16/1998 | | OK |
|
|
|
|
Letter of compliance | | | 5/7/1998 | | PASS |
|
|
|
Letter of Compliance #15037 issued 5-7-98.
|
INSP - Final | 5/4/1998 | 5/5/1998 | 5/5/1998 | P | FAIL |
Carl Dependahl
|
|
|
has fire and other ok's...meet at 5 at school. Bill ###-####...727312 radio phone...c/n, smoke seals, penetrations, temp. glass w/i 24" of doors. ok for t/o, card to contractor.
|
Code Occupancy Approval | | | 5/4/1998 | | PASS |
|
|
|
Contractor told that Code Enforcement had to sign off. There is not a CU or DR assigned to this location or Bld permit. Signed the card so he could turn it in.
|
INSP-Final Inspection | 5/1/1998 | 5/1/1998 | 5/1/1998 | P | PASS |
Joe Tawney
|
|
|
05/01/98 406 - bill ###-####-727312 OK FOR CERT OF COMPLETION
|
INSP - Final | 5/4/1998 | 5/1/1998 | 5/1/1998 | P | PART |
Carl Dependahl
|
|
|
need other insps...signatures, etc; will recall.
|
INSP - Final | 4/29/1998 | 4/30/1998 | 4/30/1998 | P | FAIL |
Carl Dependahl
|
|
|
bill/###-#### 727312 radio phone. AFTER 3:30 NEED OTHER SIGNATURES ON CARD
|
INSP - Framing/Rough-in | 4/24/1998 | 4/24/1998 | 4/24/1998 | P | PART |
Carl Dependahl
|
|
|
'HALL" AREA, PRINCIPAL'S OFFICE...OK TO COVER.
|
INSP - Framing/Rough-in | 4/3/1998 | 4/3/1998 | 4/3/1998 | P | PART |
Carl Dependahl
|
|
|
new doors at corridor ok, 20 min. s.c.
|
INSP - Framing/Rough-in | 4/3/1998 | 4/2/1998 | 4/2/1998 | P | PART |
Carl Dependahl
|
|
|
ok to cover lower restroom...need clarification of hall/corridor...spoke w/ Mike O.
|
INSP - Framing/Rough-in | 4/1/1998 | 3/31/1998 | 3/31/1998 | P | PASS |
Carl Dependahl
|
|
|
no insp, conf w/ Bill, proj. supt.
|
INSP - Framing/Rough-in | 3/27/1998 | 3/27/1998 | 3/27/1998 | P | PART |
Carl Dependahl
|
|
|
carpentry; restroom area below "teachers" room, new framed openings.
|
INSP - Framing/Rough-in | 3/27/1998 | 3/26/1998 | 3/26/1998 | P | PART |
Carl Dependahl
|
|
|
not insp, conf....need clarify "halls" vs. corridors for rated openings; discussed w/ Mike O.
|
INSP - Framing/Rough-in | 3/26/1998 | 3/25/1998 | 3/25/1998 | P | PART |
Carl Dependahl
|
|
|
after 5:00; conc sub base at restroom ok for slab, principals & sec's offices ok to cover
|
INSP - Concrete | 3/24/1998 | 3/23/1998 | 3/23/1998 | P | PART |
Carl Dependahl
|
|
|
restroom, lower area...not insp, conf only. ok
|
INSP - Framing/Rough-in | 3/16/1998 | 3/17/1998 | 3/17/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [8871401]. ok to cover teachers area as ok'd by elec...need struct fill for slab at restroom at lower area,should chk w/ plbg for reqs.
|
INSP - Framing/Rough-in | 3/12/1998 | 3/12/1998 | 3/12/1998 | A | PART |
Carl Dependahl
|
|
|
carpentry, attachment of ledger at floor
|
INSP - Framing/Rough-in | 3/9/1998 | 3/6/1998 | 3/6/1998 | P | PART |
Carl Dependahl
|
|
|
RESTROOMS
|
INSP - Framing/Rough-in | 3/4/1998 | 3/5/1998 | 3/5/1998 | A | CANC |
Wes Worcester
|
|
|
03/05/98 342 - ###-#### ext 114 \\kiwi given to Carl
|
INSP - Framing/Rough-in | 3/5/1998 | 3/5/1998 | 3/5/1998 | A | PART |
Carl Dependahl
|
|
|
TOOK FOR WES; GIRLS RESTROOM, OK TO COVER, NEED FIX EXISTING CUT JOIST AT FLOOR
|
INSP - Framing/Rough-in | 3/4/1998 | 3/4/1998 | 3/4/1998 | P | PART |
Carl Dependahl
|
|
|
"HALL" AREA, NEW HEADERS, ETC OK TO FILL IN TO MATCH EXISTING WALL. 1/2" TYPE X OK
|
INSP - Framing/Rough-in | 2/28/1998 | 3/2/1998 | 3/2/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [8871401]. RMS. 116,117 & 118(RESTROOMS, CUSTODIANS CLOSET, CORRIDOR/HALL(?)
|
INSP - Framing/Rough-in | 2/20/1998 | 2/19/1998 | 2/19/1998 | P | FAIL |
Carl Dependahl
|
|
|
C/N RE NONCONFORMING SPEC INSP REPORT....NEED ENG'S OK FOR GROUT, ETC
|
INSP - Framing/Rough-in | 2/6/1998 | 2/6/1998 | 2/6/1998 | P | FAIL |
Carl Dependahl
|
|
|
late; restroom area...COMPLETE FIREBLOCKS, REMOVE INSUL FACE PAPER,ETC...NEED SP[EC. INSP. REPORTS IN TIMELY MANNER. OK TO COVER FURRED WALLS AT RESTROOMS ONLY
|
INSP - Carpentry | 1/30/1998 | 1/30/1998 | 1/30/1998 | P | PART |
Carl Dependahl
|
|
|
NURSE (COUNSELORS ?) AREA WALLS OK TO COVER, MAY NEED RESUB FOR WINDOW. NEED SPEC INSP REPORTS (MTI)
|
INSP - Framing/Rough-in | 1/27/1998 | 1/28/1998 | 1/28/1998 | P | NR |
Carl Dependahl
|
|
|
bill ###-#### dial 0 for receptionist...NR , NEED ELEC R/I AT WORK AREA
|
INSP - Conference | 1/29/1998 | 1/28/1998 | 1/28/1998 | P | PASS |
Carl Dependahl
|
|
|
MET W/ BILL, FOREMAN; DISCUSSED INSP PROCEDURE, PLAN REQ'S, ETC. SAYS MTI IS SPEC INSP, BUT I'VE RECEIVED NO REPORTS. REMODEL AT PIERCE PARK SCHOOL
|
90 day tracking............. | | 9/29/1997 | 12/28/1997 | | |
|
|
|
|
FEE REVIEW-NOTES | | | 12/5/1997 | | FEES |
|
|
|
refund full plancheck fee. overpayment. right amount collected lh
|
(F) Reprint permit | | | 12/4/1997 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 12/4/1997 | | |
|
|
|
|
Plan assigned to (M_O) | 10/23/1997 | | 11/17/1997 | | PASS |
|
|
|
|
Telephone call | | | 11/17/1997 | | |
|
|
|
CALLED AND LEFT MESSAGE WITH SECRETARY PERMIT WAS READY AND AMOUNT DUE
|
Inspection Record Card- Bld | | | 11/17/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/17/1997 | | PASS |
|
|
|
|
Print Occupancy Form | | | 11/17/1997 | | |
|
|
|
|
Telephone call | | | 11/13/1997 | | PASS |
|
|
|
Notified architect that only one set of revised plans were submitted and another set is required to complete processing. MO
|
Routing - FIRE | 11/3/1997 | | 11/12/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/12/1997 | | 11/12/1997 | | PASS |
|
|
|
|
Plan resubmittals received | | | 11/6/1997 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 10/23/1997 | | 11/3/1997 | | FAIL |
|
|
|
CORRECTIONS SENT AND FAXED TO ARCHITECT. MO
|
Plan resubmittals requested | | | 11/3/1997 | | FAIL |
|
|
|
corrections mailed and faxed to architect. MO
|
Plan assigned to (RGG) | 10/6/1997 | | 10/23/1997 | | PASS |
|
|
|
|
Routing - PLUMBING | 10/14/1997 | | 10/15/1997 | | PASS |
|
|
|
|
Routing - PLANNING | 10/10/1997 | | 10/10/1997 | | PASS |
|
|
|
APPROVED BY SRS.
|
Routing - PUBLIC WORKS | 10/6/1997 | | 10/9/1997 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 10/6/1997 | | 10/6/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Plan routing begun/TENANTS | | | 10/6/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 9/29/1997 | | 10/6/1997 | | |
Marlene Southard
|
|
|
|
Application received | | | 10/6/1997 | | PASS |
|
|
|
|
Received Certificate of Value | | | 9/29/1997 | | PASS |
|
|
|
|
Application received | | | 9/29/1997 | | |
|
|
|
|