INSP - Grading Inspection | 7/7/1998 | | 7/7/1998 | | PASS |
Rita DeYoung
|
|
|
Revegetation and final grading have been completed. $500.00 bond can be released.
|
INSP - Final | 2/20/1998 | 2/23/1998 | 2/23/1998 | A | NR |
Wes Worcester
|
|
|
02/22/98 342 - ryan cont ###-#### tile roof not complete
|
INSP - Final | 2/23/1998 | 2/23/1998 | 2/23/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 - ryan called and roofer arrived on site to finish valley's
|
INSP - Energy code compliance | 12/2/1997 | 12/3/1997 | 12/3/1997 | P | PASS |
Wes Worcester
|
|
|
12/02/97 342 -
|
INSP - Framing/Rough-in | 12/1/1997 | 12/2/1997 | 12/2/1997 | A | PART |
Wes Worcester
|
|
|
12/01/97 342 -
|
INSP - Framing/Rough-in | 12/1/1997 | 12/1/1997 | 12/1/1997 | P | PASS |
Wes Worcester
|
|
|
12/01/97 342 -
|
INSP - Foundation | 10/21/1997 | 10/21/1997 | 10/21/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - per site plan
|
INSP - Footings | 10/20/1997 | 10/21/1997 | 10/21/1997 | A | PASS |
Wes Worcester
|
|
|
10/21/97 342 -
|
INSP - Conference | 10/21/1997 | 10/21/1997 | 10/21/1997 | | PASS |
Wes Worcester
|
|
|
/ / 342 - met w/Steve on site and went over setbacks....per site plan
|
INSP - Foundation | 10/21/1997 | 10/21/1997 | 10/21/1997 | | NR |
Wes Worcester
|
|
|
/ / 342 - noted difference between site plan and grading plan...13 vs
|
INSP - Site Preparation | 10/20/1997 | 10/20/1997 | 10/20/1997 | | NR |
Wes Worcester
|
|
|
/ / 342 - NW corner of garage not string lined as property pin was kno
|
INSP - Footings | 10/17/1997 | 10/20/1997 | 10/20/1997 | A | PART |
Wes Worcester
|
|
|
10/20/97 342 - ck nw corner of garage as property pin on No side (sunnyr
|
Issue PAID IN FULL permit | | | 10/16/1997 | | |
|
|
|
|
(F) Reprint permit | | | 10/16/1997 | | |
|
|
|
|
Telephone call | | | 10/15/1997 | | |
|
|
|
called and left message on answering machine 9 a.m.10/15/97
|
Inspection Record Card- Bld | | | 10/15/1997 | | |
|
|
|
|
Print Occupancy Form | | | 10/15/1997 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/1997 | | PASS |
|
|
|
ISSUE
|
Print Pending Permit.LaserJet4 | | | 10/15/1997 | | PASS |
|
|
|
FILES
|
Plan Reviewer's activity | | | 10/15/1997 | | PASS |
|
|
|
REVIEW PLANS AND ASSEMBLE, MARK-UP, INPUT CONDITIONS, INPUT TO TIDEMARK, ISSUE
|
Plan assigned to (PRP) | 10/3/1997 | | 10/15/1997 | | PASS |
|
|
|
10/15/97 08:53:22 PRP - this action updated by action script from <<>> in Case No. BLD97-2961
|
Routing - PLANNING | 10/9/1997 | | 10/13/1997 | | PASS |
|
|
|
APPROVED BY MH.
|
Routing - PUBLIC WORKS GRADING | 10/8/1997 | | 10/8/1997 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3
|
Routing - PUBLIC WORKS | 10/3/1997 | | 10/8/1997 | | PASS |
|
|
|
|
Application received | | | 10/3/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 10/13/1997 | | | | PEND |
|
|
|
|