Letter of compliance | | | 7/7/1998 | | PASS |
|
|
|
Letter of Compliance #15770 issued 7-7-98.
|
INSP - Final | 7/1/1998 | 7/2/1998 | 7/2/1998 | A | FAIL |
Tom Arcoraci
|
|
|
07/02/98 408 - after 9am Mike ###-#### OK AFTER PUBLIC WORKS SIGNS
|
INSP-Final Inspection | 6/29/1998 | 6/29/1998 | 6/29/1998 | P | PASS |
Joe Tawney
|
|
|
06/29/98 406 - mike ###-#### REINSP OK FOR CERT OF COMPLETION ì
|
INSP-Final Inspection | 12/30/1997 | 12/31/1997 | 12/31/1997 | A | FAIL |
Joe Tawney
|
|
|
12/31/97 406 - HARD CARD ON THE WALL IN THE ADDITION OF POST OFFICE FINAL FAIL SPKLR PROTECTION REQUIRED
|
INSP - Final | 12/30/1997 | 12/31/1997 | 12/31/1997 | A | NR |
Jim Sly
|
|
|
12/30/97 316 - Need all required signatures on occ req card ...left note
|
INSP - Conference | 12/30/1997 | 12/30/1997 | 12/30/1997 | | PASS |
Jim Sly
|
|
|
/ / 316 - Met with superintendent to discuss requirements for final...
|
INSP - Final | 12/29/1997 | 12/30/1997 | 12/30/1997 | A | NR |
Jim Sly
|
|
|
12/30/97 316 - C/N...Need all required signatures....
|
Code Occupancy Approval | | | 12/30/1997 | | PASS |
|
|
|
Final Occupancy by: Carol A. Montgomery 12/30/97 Everything in order as far as we are concerned.
|
INSP - Framing/Rough-in | 11/20/1997 | 11/19/1997 | 11/19/1997 | P | PASS |
Tom Arcoraci
|
|
|
|
INSP - Framing/Rough-in | 11/19/1997 | 11/19/1997 | 11/19/1997 | P | CANC |
|
|
|
sent to 408
|
INSP - Framing/Rough-in | 11/6/1997 | 11/7/1997 | 11/7/1997 | A | CANC |
Tom Arcoraci
|
|
|
WALLS SHOULD BE FOUNDATION INSP
|
INSP - Foundation | 11/7/1997 | 11/7/1997 | 11/7/1997 | A | PASS |
Tom Arcoraci
|
|
|
|
INSP - Footings | 11/4/1997 | 11/4/1997 | 11/4/1997 | P | PASS |
|
|
|
11/04/97 333 - after 1:45 FTG -OK FOOTING
|
Issue PAID IN FULL permit | | | 10/28/1997 | | |
|
|
|
|
Telephone call | | | 10/27/1997 | | |
|
|
|
AS PER MIKE HE WILL CALL AND LET THEM KNOW.
|
Inspection Record Card- Bld | | | 10/27/1997 | | |
|
|
|
|
Print Occupancy Form | | | 10/27/1997 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/27/1997 | | PASS |
|
|
|
|
Application received | | | 10/24/1997 | | |
|
|
|
|
Plan Reviewer's activity | | | 10/24/1997 | | PASS |
|
|
|
THIS PROJECT WAS APPROVED IN AUGUST OF 1996 AND WAS NOT PICKED UP. ORIGINAL PERMIT WAS VOIDED. APPROVAL BY PUBLIC WORKS, PLANNING DEPARTMENT, FIRE DEPARTMENT AND MYSELF WAS COMPLETE BY 08/22/96. ADDITIONAL COMMENTS ARE NOTED IN PERMIT BLD96-1971. PLAN REVIEW FEES WERE PAID REFER TO BLD96-1971 FOR INFORMATION.
|
Routing for occupancy | 12/30/1997 | 12/30/1997 | | | PEND |
|
|
|
Requested Final Occupancy Inspection:
|