Permanent Occupancy | | 6/16/1998 | 6/16/1998 | | DONE |
|
|
|
|
INSP - Final | 6/16/1998 | 6/16/1998 | 6/16/1998 | P | PART |
Wes Worcester
|
|
|
06/16/98 342 - ###-#### digital pager Shane
|
Permanent occupancy | | | 6/16/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7281 issued 6-16-98 to Mountain Cove School for a couple of portable classroom bldgs.
|
INSP-Final Inspection | 5/6/1998 | 5/7/1998 | 5/7/1998 | A | FAIL |
Rick Jackson
|
|
|
shane ###-#### strobes, test alarms, bldg number, door hardware, fire extinguisher
|
Code Occupancy Approval | | | 5/7/1998 | | PASS |
|
|
|
Checked site and landscape in with sprinklers.
|
Issue PAID IN FULL permit | | | 3/16/1998 | | |
|
|
|
|
Additional plans submitted | | | 3/6/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/6/1998 | | PASS |
|
|
|
|
Telephone call | | | 3/6/1998 | | PEND |
|
|
|
CALLED LEFT MESSAGE FOR JEFF FOSTER GAVE $ AMOUNT
|
Inspection Record Card- Bld | | | 3/6/1998 | | |
|
|
|
|
Print Occupancy Form | | | 3/6/1998 | | |
|
|
|
|
Plan assigned to (M_O) | 11/14/1997 | | 3/6/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 3/4/1998 | | PEND |
|
|
|
MISSING ONE SET OF REVISED PLANS. ARCHITECT CONTACTED TO PROVIDE ADDITIONAL SET. MO
|
Routing - PUBLIC WORKS | 3/3/1998 | | 3/4/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/24/1998 | | 2/26/1998 | | FAIL |
|
|
|
FLOOD PLAIN ISSUES.
|
Routing - PLAN CHECK | 2/13/1998 | | 2/23/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 2/13/1998 | | |
|
|
|
RECEIVED 2 REVISED BLUELINES INCLUDING SHEETS A0,C1,A1,A2,A3,A4 2 COPIES FOUNDATION DESIGN STRUCTURAL CALCS. 1 COPY OF CORRECTIVE ACTION LETTER ROUTED TO MIKE O.
|
Plan resubmittals received | | | 2/13/1998 | | |
|
|
|
RRECEIVED 2 COPIES OF SPECS. ROUTED TO MIKE O.
|
90 day tracking............. | | 10/29/1997 | 1/27/1998 | | PEND |
|
|
|
|
Plan resubmittals requested | | | 12/3/1997 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 12/2/1997 | | 12/3/1997 | | FAIL |
|
|
|
CORRECTIONS MAIELD AND FAXED TO ARCHITECT ON 12-03-98.MO
|
Routing - FIRE | 11/26/1997 | | 12/1/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 11/20/1997 | | 11/26/1997 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MO
|
Routing - PLANNING | 11/10/1997 | | 11/19/1997 | | PASS |
|
|
|
X-REF: CZC97-0122. APPROVED BY RLB.
|
Plan assigned to (RGG) | 10/30/1997 | | 11/14/1997 | | |
|
|
|
|
Routing - PLUMBING | 11/5/1997 | | 11/10/1997 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 10/31/1997 | | 11/4/1997 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN. FLOOD PLAIN ISSUES.
|
Routing Off Site - A.C.H.D | 10/30/1997 | | 10/31/1997 | | PASS |
|
|
|
CONTACTED JEFF FOSTER AT ###-#### TO TAKE PLANS OUT TO ACHD
|
Plan routing begun/NEW & ADDTN | | | 10/30/1997 | | PASS |
|
|
|
|
Routing - ELECTRICAL | 10/30/1997 | | 10/30/1997 | | PASS |
|
|
|
NO REVIEW FIELD VERIFY
|
Plans ACCEPTED BY PLAN CHECK | | | 10/30/1997 | | PASS |
|
|
|
JEFF FOSTER WILL FAX OVER BLDG. TAG NUMBERS TAG #6880CC
|
Plan assigned to (MYS) | 10/29/1997 | | 10/30/1997 | | |
Marlene Southard
|
|
|
|
Received Certificate of Value | | | 10/30/1997 | | PASS |
|
|
|
|
Application received | | | 10/29/1997 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 10/29/1997 | | PEND |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|