Permit Information
Permit NumberBLD97-03332
StatusFinaled
Name BOB ERLAND
Site Address 4980 W CAMAS ST
Project NameEVENING SHADE APT.
Customer Number 
ePlanReviewNo
Description
EVENING SHADE APARTMENTS * TO CONSTRUCT A NEW 15 UNIT TWO STORY APARTMENT BUILDING ON ORCHARD AND CAMAS ST. Construction to be Type V-1Hr with two separate corridor stairways. The building is composed of one 173sf laundry room, 8-509sf one bedroom units with 116sf patio each; 4-572sf one bedroom units with 104sf patios, one 435sf one bedroom unit, and two 304sf studio units with no patios all under one roof. DR97-0144 CU45-97. ACHD # 98-0235; PRP PC#716-97
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval  1/28/1999 DONE
Terry Records inspected hillside and pond, drainage project complete 01/28/99. R.Rokovitz
Permanent occupancy  10/15/1998 PASS
Perm. Occ. Cert. #7459 issused 10-13-98 to the Evening Shade Apts.
INSP - Final10/13/199810/13/199810/13/1998 PASS
DetailsJoe Tawney
/ / 406 - REINSP OK FOR PERM OCC SIGNED OF BY P PAINE
INSP - Final10/12/199810/12/199810/12/1998PFAIL
DetailsJoe Tawney
10/12/98 406 - BOB WILL CALL TO SCHEDULE..###-#### FINAL FAIL SMOKE DETECTORS IN UNIT # 16
Permanent Occupancy 10/12/199810/12/1998 DONE
Details
INSP - Final10/8/199810/9/199810/12/1998PPART
Details
10/09/98 338 - made eok occ req card signed 406 c/n made ok
Code Occupancy Approval  10/12/1998 PASS
ALL CONDITIONS OF THE DRH97-0144 HAS BEEN MET, FINAL SIGNED OFF.
INSP - Energy code compliance5/22/19985/22/19985/22/1998APASS
Details
MADE OK TO COVER
INSP - Framing/Rough-in5/21/19985/22/19985/22/1998APASS
Details
MADE OK C/N REMOVED
INSP - Framing/Rough-in5/18/19985/19/19985/19/1998AFAIL
Details
bob ###-#### c/n issued fans and the recessed lights penetrations too big for 1-hour seperations.
INSP - Framing/Rough-in4/13/19984/14/19984/14/1998APART
Details
04/13/98 338 - PART MADE OK CONF ONLY VERBAL ONLYBOB ###-####-PRE FRAMIN
INSP - Framing/Rough-in3/26/19983/27/19983/27/1998APART
Details
03/27/98 338 - steel straps bob ###-#### made ok missing two straps
INSP - Concrete2/12/19982/12/19982/12/1998PPASS
Details
02/12/98 338 - FRMS-OK FORMS-REBAR
INSP - Concrete2/9/19982/9/19982/9/1998PPASS
Details
02/09/98 338 - footings ryan ###-#### ok to pour when the r-bar is place waiting for the r-bar to arrive
90 day tracking............. 11/6/19972/4/1998 PEND
Issue PAID IN FULL permit  1/29/1998
Telephone call  1/7/1998
called bob erland, gave $ amount, he is coming by to check the break down.
Inspection Record Card- Bld  1/7/1998
Print Occupancy Form  1/7/1998
PLANS/APPL TAKEN TO FRONT DESK  1/6/1998 PASS
ISSUE
Plan assigned to (PRP)12/1/1997 1/6/1998 PASS
Details
routing to ACHD since 11/06--Waiting return review finished, Arch to redo plans. sent for corr 12/29/97 01/06/98 15:11:01 PRP - this action updated by action script from <<>> in Case No. BLD97-3332
Routing - PLAN CHECK1/5/1998 1/6/1998 PASS
ISSUE AS RED-LINED
Routing - PLUMBING1/2/1998 1/5/1998 PASS
Plan resubmittals received  1/2/1998 PASS
RECEIVED PLUMBING AND RESUB PLANS REQUESTED. ROUTE BACK TO PLUMBING, RECEIVED BACK AND REVIEWED, INSERT, UPDATE INPUT, ISSUE--1/6/98
Routing - FIRE12/29/1997 1/2/1998 PASS
Routing - PUBLIC WORKS12/29/1997 12/29/1997 PASS
Routing - PLUMBING12/26/1997 12/29/1997 FAIL
Print Pending Permit.LaserJet4  12/26/1997 PEND
FILE
Plan resubmittals requested12/26/1997 12/26/1997
Plan Reviewer's activity  12/26/1997 FAIL
REVIEW PLANS, RED-LINE SOMEWHAT, PREPARE CORRECTIONS, DISCUSS WITH OWNER, CALL ARCH, WAIT FOR RETURN CALL FROM ARCH TO FAX, FORWARD TO PLUMBING, AND FIRE.
Routing - PUBLIC WORKS12/19/1997 12/19/1997 PASS
Routing - PLUMBING12/16/1997 12/18/1997 FAIL
Routing - PLANNING12/12/1997 12/15/1997 PASS
X-REF: CUP97-0045. APPROVED BY RLB.
Routing - PUBLIC WORKS12/9/1997 12/12/1997 FAIL
REQUIRES DRAINAGE PLAN 3 MORE COPIES
Routing Off Site - A.C.H.D11/7/1997 12/9/1997 PEND
CONTACTED MIKE FAIRCHILD TO TAKE PLANS OUT TO ACHD ACHD FEES NOT PAID 12/09/97
Plan assigned to (RGG)11/6/1997 12/1/1997 PASS
Plan routing begun/NEW & ADDTN11/6/1997 11/7/1997 PASS
Plans ACCEPTED BY PLAN CHECK  11/7/1997 PASS
MIKE CAME IN AND STAMPED AND SIGNED SHEETS A-7, A-8, AND A-9B. I AM READY TO ROUTE
Plans ACCEPTED BY PLAN CHECK  11/6/1997 HOLD
ARCH. SHEETS A-7 A-8 AND A-9B WERE NOT STAMPED OR SIGNED. CONTACTED MIKE FAIRCHILD AT ###-#### (TRIED NO ONE HOME) WILL TRY AGAIN IN AM. OF THIS NEED.
Received Certificate of Value  11/6/1997 PASS
Recd Pcfee & Taken To Pln CK  11/6/1997 PEND
Application received  11/6/1997