Permit Information
Permit NumberBLD97-03390
StatusExpired
Name SCOTT EDENS
Site Address 10700 W USTICK RD
Project NameALBERTSONS #161
Customer Number97-722
ePlanReviewNo
Description
ALBERTSON'S INC. STORE #161 * TO REMODEL EXISTING ALBERTSON'S AND ADD A 12,452 S.F., SINGLE STORY BUILDING ADDITION AND MODIFY STORE FRONT ENTRY. CONSTRUCTION IS TYPE III-N AND FIRE SPRINKLERS ARE USED FOR AREA. DR59-97 CUP-97-0054 PC#722-97. THE EXIT ALTERNATE PLAN IS TO BE USED ON THIS PROJECT UNLESS A RECORDED RECORD OF SURVEY IS PROVIDED THAT MOVES THE NORTH PROPERTY LINE SIX FEET AWAY FROM THE NORTH WALL AS SHOWN ON THE APPROVED PLANS. THE RECORDED RECORD OF SURVEY IS TO BE PROVIDED PRIOR TO FINAL INSPECTION IF NOT USING THE ALTERNATE EXIT PLAN.
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  4/9/2015 DONE
SUPER- Supervisor's review2/2/19992/2/19992/2/1999
work still inprogress slow and slow at calling for inspection
INSP - Final12/30/199812/30/199812/30/1998 FAIL
DetailsJoe Tawney
/ / 406 - REINSP FAIL DUCT DETECTORS, REFRIGERATION ISSUES
INSP-Final Inspection12/29/199812/29/199812/29/1998PCANC
DetailsJoe Tawney
12/29/98 406 - BLAKE ###-#### CANCEL RESCHED FOR 1:00 PM 12/30/98
Fee Review-notes7/23/1998 12/15/1998 PASS
Code Occupancy Approval  12/9/1998 PASS
Meets approval w/DRH97-0059/CUP97-0054. Card N/A. Jason Starner will take to City Hall tomorrow. Final.
INSP - Final12/2/199812/2/199812/2/1998 PART
DetailsJoe Tawney
/ / 406 - REINSP ON SPKLR SYSTEM SPKLR SYSTEM SIGNED OFF OK
INSP - Final11/10/199811/10/199811/10/1998 PART
DetailsJoe Tawney
/ / 406 - FINAL OK FOR TEMP OCC SPKLR ITEMS, DUCT DET, EMERG GEN TIME
INSP-Final Inspection11/5/199811/5/199811/5/1998PPART
DetailsJoe Tawney
11/05/98 406 - BLAKE ###-#### PRE FINAL CONF AND WALK THRU WITH GEN CONTR
INSP-Sprinkler Rough-in/Hydro10/30/199810/30/199810/30/1998P
DetailsJim Sly
INSP-Final Inspection10/30/199810/30/199810/30/1998PFAIL
Details
store found to be occupying addition without any final approval from fire or structural. request for fire sprinkler contractor to produce plans to do rough-in had been ignored. informed store manager of illegal occupancy - he contacted general contractor
INSP-Sprinkler Rough-in/Hydro10/30/199810/30/199810/30/1998PFAIL
DetailsMike Kinnear
Inspection of fire sprinkler roughin for occupancy with Grinnell's engineer. Found many difficiencies and left copy with store manager.
Plan assigned to (MLO)4/17/1998 10/30/1998
DetailsMike Otto
revisions to approved plans. PLANS NEVER RETURNED FORM CENTRAL DISTRICT HEALTH. THIS PROJECT HAS BEEN APPROVED BY FIELD STAFF WITHOUT BENEFIT OF PLAN REVIEW FOR THE REVISIONS RECEIVED 4-17-98. PLAN REVIEW IS CANCELLED. MLO
INSP - Final10/27/199810/27/199810/27/1998PFAIL
DetailsJim Sly
10/27/98 316 - C/N...Complete prev corr and add address #'s....
INSP - Final10/23/199810/26/199810/26/1998AFAIL
DetailsJim Sly
10/26/98 316 - C/N..All signatures,draftstops,letterEngineer&specinsp,P/
Print Occupancy Form  10/26/1998
INSP-Sprinkler Rough-in/Hydro10/23/199810/23/199810/23/1998 FAIL
DetailsJoe Tawney
/ / 406 - ROUGH IN OF NEW SPKLR SYSTEM FAIL NEED CONF WITH SPKLR CONTR
INSP-Sprinkler Rough-in/Hydro10/21/199810/22/199810/22/1998APART
DetailsJoe Tawney
10/22/98 406 - KERRY TURNER- PAGER ####-#### SPR INSP OK ON HYDRO TEST OF NEW SYSTEM EXC FDC PIPING
INSP - Framing/ Rough-in10/22/199810/22/199810/22/1998 FAIL
DetailsJim Sly
/ / 316 - C/N...No inspection of (completed) 1hr hood shafts..Not appr
INSP - Framing/Rough-in10/20/199810/20/199810/20/1998PPART
DetailsJim Sly
10/20/98 316 - Ceiling grid at front and South end center section...OK
INSP - Framing/Rough-in10/5/199810/6/199810/6/1998APART
DetailsJim Sly
10/06/98 316 - Ceiling grid OK at cart storage area....
INSP - Framing/Rough-in9/17/19989/18/19989/18/1998APART
DetailsJim Sly
09/18/98 316 - Insp of new store front framing..eng to specify straps..c
INSP - Framing/Rough-in9/16/19989/17/19989/17/1998ANR
DetailsJim Sly
09/17/98 316 - Cancelled by Contractor...... phone is [3717146].
INSP - Framing/Rough-in9/9/19989/10/19989/10/1998ACANC
DetailsJim Sly
09/10/98 316 - Done by Tom A.
INSP - Framing/Rough-in9/10/19989/10/19989/10/1998 PART
DetailsTom Arcoraci
/ / 408 - GRID PART OK
INSP - Letter of compliance8/31/19988/31/19988/31/1998 PASS
DetailsJim Sly
/ / 316 - C/C # 015699
INSP - Framing/Rough-in8/28/19988/31/19988/31/1998APART
DetailsJim Sly
08/31/98 316 - Insp of Ceiling grid S. sect, and Bakery...All int. soffi
INSP - Letter of compliance8/31/19988/31/19988/31/1998 PASS
DetailsJim Sly
/ / 316 - C/C # 015699
INSP-Conference8/27/19988/27/19988/27/1998PPART
DetailsStan Johnson
08/27/98 352 - mitch ###-#### test on vents instock area
INSP-Sprinkler Rough-in/Hydro8/27/19988/27/19988/27/1998PPART
DetailsJoe Tawney
08/27/98 406 - Scheduled by Hello!. Contact phone is [3717149]. OK TO COVER IN STORE AREA NORTH SIDE
INSP - Framing/Rough-in8/24/19988/25/19988/25/1998APART
DetailsJim Sly
08/25/98 316 - CEILING GRID OK at center drop...approx 3000 sq ft (exis
INSP - Framing/Rough-in8/8/19988/10/19988/10/1998APART
DetailsJim Sly
08/10/98 316 - Insp of West common wall (new sect)..between public area
INSP - Framing/Rough-in7/29/19987/29/19987/29/1998PPART
DetailsJim Sly
07/29/98 316 - Ceiling grid above beer cooler OK
Routing - PUBLIC WORKS7/27/1998 7/28/1998 PASS
INSP - Framing/Rough-in7/24/19987/27/19987/27/1998AFAIL
DetailsJim Sly
07/27/98 316 - Ceiling grid NR
Telephone call  7/27/1998
CALLED DORY PERMIT READY
INSP - Framing/Rough-in7/22/19987/24/19987/24/1998APART
DetailsJim Sly
07/24/98 316 - Grid ceiling OK over New camera bar.
Plan resubmittals received  7/24/1998
Received plan modification - Three copies of revised drawings, plan modification application, and application fee of $500.00. Routed to Mike Otto. KMM
INSP - Framing/Rough-in7/21/19987/21/19987/21/1998PPART
DetailsJim Sly
07/21/98 316 - OK'd soffit and fascia framing above new meat dept.
Plan Reviewer's activity  7/21/1998 PEND
ARCHITECT BROUGHT IN ANOTHER SET OF PLANS WITH VARIOUS CHANGES INCLUDING STRUCTRUAL. ARCHITECT MUST FILL OUT PLAN MODIFICATION FORM AND PAY FEES. MLO
INSP - Framing/Rough-in7/17/19987/17/19987/17/1998 FAIL
DetailsWes Worcester
/ / 342 - called cell number, left msg at office number....not screwed
INSP - Framing/Rough-in7/16/19987/17/19987/17/1998ANH
DetailsWes Worcester
/ / 342 - Scheduled by Hello!. Contact phone is [3214953]. could no
Routing Off Site - C.D.H  7/9/1998
Routing Off Site - C.D.H5/28/1998 7/9/1998 PASS
PUT IN CALL TO CDH ON 7-3-98 REGARDING STATUS OF PLAN REVIEW. MLO RECEIVED PHONE CALL FROM STEVE ELMER OF CDH ON ALBERTSONS PLANS. ELMER SAID HE HAD REVIEWED THE PLANS ON MAY 29, 1998 AND GAVE PLANS TO STORE MANAGER RUSS WEDDEL. 7-7-98. MLO. PLANS RETURNED TO BLDG. DEPT. 7-09-98. MLO
Telephone call  7/9/1998 PEND
CALL PUT IN TO MANAGER RUSS WEDDEL WHO WAS ON VACATION. SPOKE WITH MANAGER BY FIRST NAME OF JIM WHO WAS UNAWARE OF SUCH PLANS AND LOCATION WAS UNKNOWN. EXPLANATION OF PROCESS FOR APPLAICANT CARRYING PLANS TO HEALTH DEPT. AND RETURNING GIVEN. SEE MEMO AT HEALTH DEPT. ROUTING 5/28/98. MLO
INSP - Framing/Rough-in6/30/19987/1/19987/1/1998APART
DetailsJim Sly
07/01/98 316 - Grid ceiling OK at West of Pharmacy...
INSP-Final Inspection5/29/19986/1/19986/1/1998AFAIL
DetailsJoe Tawney
05/31/98 406 - ###-#### partial final on phase I FINAL PHASE 1 FAIL SPKLR PROTECTION IN FLORAL COOLER AND SOFFIT PROTECTO
INSP - Framing/Rough-in5/28/19985/29/19985/29/1998APART
DetailsTom Arcoraci
/ / 408 - ###-#### ready to move into the new pharmacy PHARMANCY FRAMING ONLY IS OK
INSP - Framing/Rough-in5/22/19985/26/19985/26/1998APASS
DetailsJim Sly
05/26/98 316 - CEILING INSPECTION/ Pharmacy......OK
Routing - PLANNING5/20/1998 5/22/1998 PASS
These plans were a resubmitttal and not site plan or landscaping plan was submitted. There were not plans submitted with this resubmittal which I would need to review. The associated files are CUP97-0054 and DRH97-0059.
Routing - PLUMBING5/18/1998 5/20/1998 FAIL
Routing - PUBLIC WORKS5/13/1998 5/18/1998 PASS
Routing - PLAN CHECK5/12/1998 5/13/1998 PASS
REVISED PLANS OK. MLO
Routing - PLAN CHECK4/17/1998 5/12/1998 HOLD
plan review on hold until response form architect on letter sent by Building Official concerning additional plan review fees due. 4-22-98. MLO.
INSP - Framing/Rough-in5/1/19985/4/19985/4/1998APART
DetailsJim Sly
05/04/98 316 - ###-#### conference With all trades and job superintenden
INSP - Framing/Rough-in4/30/19984/30/19985/1/1998PPART
DetailsTom Arcoraci
04/30/98 408 - jason ###-#### NORTH INSIDE PHARMACY WALLS OK TO COVER AF
INSP - Foundation4/29/19984/29/19984/29/1998PPART
DetailsJim Sly
04/29/98 316 - REBAR INSP Pending spec insp approval...
INSP - Foundation4/27/19984/27/19984/27/1998PPART
DetailsJim Sly
04/27/98 316 - Footing pending special inspection approval....
Plan resubmittals received  4/17/1998
plan changes made to approved plans. Will require review by C.D.H, plumbing , plan check, public works.
Issue PAID IN FULL permit  4/15/1998
Additional plans submitted  4/9/1998 PASS
PROVIDED ADDITIONAL SHEETS THAT HAD MISSING STAMPS.
Print Occupancy Form  4/9/1998
Telephone call  4/9/1998
left message on voice mail for jake jones at wright bros.
Inspection Record Card- Bld  4/9/1998
PLANS/APPL TAKEN TO FRONT DESK  4/9/1998 PASS
Plan assigned to (MLO)11/14/1997 4/9/1998 PASS
DetailsMike Otto
Routing - PLAN CHECK4/3/1998 4/8/1998 PASS
Plan resubmittals received  4/8/1998 PEND
RECEIVED RESUBMITTALS FROM PETERSON STAGGS. DAR
Plan resubmittals received  4/3/1998 PEND
EXIT ALTERNATE PLANS RECEIVED. PROPERTY LINE STILL NOT RESOLVED. EXIT ALTERNATE ALLOWS EXIT TO BE MOVED AND BRING BUILDING INTO COMPLIANCE WITH EXISTING PROPERTY LINE. MLO
Routing Off Site - A.C.H.D11/14/1997 3/25/1998 PASS
CONTACTED TIM STAGGS AT ###-#### TO TAKE PLANS OUT TO ACHD PACKAGE #2 DAVE CARNAHAN IS THE CONTACT PERSON FOR DELIVERIES AT ###-#### ACHD FEES DUE. 3-25-98 FEES PAID IMPACT FEE CERTIFICATE #98-1113
Routing - PLAN CHECK2/27/1998 3/6/1998 PEND
PROPERTY LINE BEING WORKED ON. MLO
Plan resubmittals received  2/27/1998 PEND
NEW PLANS SUBMITTED.
90 day tracking............. 11/12/19972/10/1998
Routing - FIRE12/30/1997 1/6/1998 PASS
Plan resubmittals requested  12/10/1997 FAIL
Routing - PLAN CHECK12/8/1997 12/10/1997 FAIL
SPOKE WITH ARCHITECT ON PHONE 12-09-97 REGARDING THE PROEPRTY LINE EXIT PROBLEM. HE WILL RESOLVE AND RESPOND. MO . 12-29-97 - ARCHITECT IS STILL WORKING ON RESOLUTION OF ABOVE PLANS SENT TO FIRE FOR REVIEW. MO
Routing - PLUMBING12/4/1997 12/8/1997 PASS
Routing - PLANNING11/24/1997 12/4/1997 PASS
X-REF: CUP97-0054 & DRH97-0059. APPROVED BY SAR & TKW.
Routing - PUBLIC WORKS11/17/1997 11/24/1997 PASS
Routing Off Site - C.D.H11/12/1997 11/17/1997 PASS
CONTACTED TIM SKAGGS AT ###-#### TO TAKE PLANS OUT TO CDH. DAVE CARNAHAN IS THE CONTACT PERSON FOR DELIVERIES AT ###-####
Plan assigned to (RGG)11/12/1997 11/14/1997 PEND
Application received  11/12/1997
Plan assigned to (MYS)11/12/1997 11/12/1997 PEND
DetailsMarlene Southard
Plans ACCEPTED BY PLAN CHECK  11/12/1997 PASS
ONE SUBMITTAL OF TWO (ONE SET) SUBMITTED PACKAGE #1 ONE SUBMITTAL OF TWO (ONE ACHD SET) SUBMITTED PACKAGE #2 NO ENG. SUBMITTAL
Received Certificate of Value  11/12/1997 PASS
REVISED CERT. OF VALUE IN WALL FILE GAVE TWO CERT. OF VALUE TO MIKE O TO PUT WITH THE ACHD SET.
Plan routing begun/NEW & ADDTN  11/12/1997 PASS
Gay Receipt For Partial Pay  11/12/1997
Routing - ELECTRICAL11/12/1997 11/12/1997 PASS
NO REVIEW FIELD VERIFY
Routing Off Site - C.D.H7/28/1998  
7/28/98 CALLED DAVE CARNAHAN TO TAKE PLANS TO CDH. 8/11/98 PLANS HAVE NOT BEEN PICKED-UP. CALLED SCOTT EDENS AND ADVISED MODIFICATION PLANS HAVE NO BEEN PICKED-UP. HE SAID HE WOULD TAKE CARE OF THE PROBLEM.