Permanent occupancy | | | 5/21/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7258 issued 5-21-98 to New Horizons Computer Learning Center.
|
Permanent Occupancy | | 5/15/1998 | 5/15/1998 | | DONE |
|
|
|
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/14/1998 | P | PASS |
Carl Dependahl
|
|
|
###-#### ###-####pager card signed at site
|
INSP - Final | 5/14/1998 | 5/14/1998 | 5/14/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Final Inspection | 5/12/1998 | 5/13/1998 | 5/13/1998 | P | CANC |
Joe Tawney
|
|
|
05/13/98 406 - ###-#### CANCELLED RESCHED TO 5/14/98
|
INSP - Final | 5/11/1998 | 5/11/1998 | 5/11/1998 | A | FAIL |
Carl Dependahl
|
|
|
need fire ok for final.
|
INSP - Final | 5/11/1998 | 5/8/1998 | 5/11/1998 | | |
Joe Tawney
|
|
|
|
INSP - Framing/Rough-in | 5/7/1998 | 5/8/1998 | 5/8/1998 | P | CANC |
Carl Dependahl
|
|
|
TONY/###-#### - STRUCTURAL FINAL. not framing...will recall w/ BLD97-2104.
|
INSP-Final Inspection | 5/7/1998 | 5/8/1998 | 5/8/1998 | A | NR |
Joe Tawney
|
|
|
05/08/98 406 - TONY/###-#### - FIRE LIFE SAFETY & SPRINKLER FINAL INSP. REINSP NOT READY
|
INSP - Final | 5/6/1998 | 5/7/1998 | 5/7/1998 | P | FAIL |
Carl Dependahl
|
|
|
tony ###-#### w/ bld97-2104...need fire ok
|
INSP-Final Inspection | 5/5/1998 | 5/6/1998 | 5/7/1998 | A | FAIL |
Joe Tawney
|
|
|
05/06/98 406 - ###-#### REINSP FAIL SPKLR COVERAGE IN ROOM 108 OR CLASSROOM #6
|
INSP - Foundation | 5/5/1998 | 5/6/1998 | 5/6/1998 | P | FAIL |
Wes Worcester
|
|
|
05/06/98 342 - ###-#### still no answer....maybe needs a final and if so signatures
|
90 day tracking............. | | 12/3/1997 | 3/3/1998 | | PEND |
|
|
|
|
INSP - Final | 2/19/1998 | 2/20/1998 | 2/20/1998 | A | PART |
Carl Dependahl
|
|
|
TONY ###-#### OR ###-####...c/n need fire, corridor penetrations detailed.
|
INSP-Final Inspection | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | FAIL |
Joe Tawney
|
|
|
02/19/98 406 - TONY ###-#### OR ###-#### REINSP FOR FINAL FAIL SPKLR OBSTRUCTION APPR ALARM SUBMITTAL
|
INSP - Final | 2/19/1998 | 2/18/1998 | 2/18/1998 | A | FAIL |
Carl Dependahl
|
|
|
KEEP C/N; CONF RE C/N
|
INSP-Final Inspection | 2/17/1998 | 2/17/1998 | 2/18/1998 | P | PASS |
Joe Tawney
|
|
|
02/17/98 406 - TONY ###-#### REINSP FOR FINAL OK FOR TEMP OCC ì
|
INSP - Final | 2/17/1998 | 2/17/1998 | 2/17/1998 | P | FAIL |
Carl Dependahl
|
|
|
TONY ###-####ba w/BLD97-2104...FIRESTOPS AT CORR, OTHER PERM SIG'S. OK FOR T/0 CARDS TO CONTRACTOR
|
INSP-Sprinkler Rough-in/Hydro | 2/6/1998 | 2/13/1998 | 2/13/1998 | A | FAIL |
Joe Tawney
|
|
|
02/13/98 406 - tony pager ###-#### fast beep fire panel\\Tony called bac please FINAL FAIL ALARM SUBMITTAL SPKLR HDS OBSTRUCTED FIRE EXT
|
INSP - Final | 2/12/1998 | 2/13/1998 | 2/13/1998 | P | NR |
Carl Dependahl
|
|
|
###-#### pager
|
INSP - Framing/Rough-in | 2/10/1998 | 2/11/1998 | 2/11/1998 | P | PART |
Carl Dependahl
|
|
|
ceiling grid tony ###-#### pager...LOOKS OK, CHECK DRAFT STOP AT FINAL???
|
INSP - Framing/Rough-in | 1/26/1998 | 1/27/1998 | 1/27/1998 | P | NR |
Wes Worcester
|
|
|
01/27/98 342 - NEW HORIZONS COMPUTER--TONY ###-####
|
INSP - Framing/Rough-in | 1/28/1998 | 1/27/1998 | 1/27/1998 | P | PART |
Carl Dependahl
|
|
|
WES UNABLE TO DO, CORRIDOR WALLS AND PARTITIONS OK TO COVER, WILL ADD PARTITION & SEISMIC BRACING LATER. ELEC OK; NEED COMPLETE HTG OK
|
INSP - Framing/Rough-in | 1/27/1998 | 1/27/1998 | 1/27/1998 | P | PART |
Carl Dependahl
|
|
|
PER WES & BA OK TO COVER WALLS
|
Issue PAID IN FULL permit | | | 1/26/1998 | | |
|
|
|
|
Print Occupancy Form | | | 1/26/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 1/26/1998 | | |
|
|
|
|
Telephone call | | | 1/26/1998 | | |
|
|
|
called and gave them $ amount
|
(F) Reprint permit | | | 1/26/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/23/1998 | | PASS |
|
|
|
issue
|
Routing - PLAN CHECK | 1/23/1998 | | 1/23/1998 | | PASS |
|
|
|
issued
|
Routing - FIRE | 1/22/1998 | | 1/23/1998 | | PASS |
|
|
|
|
Plan assigned to (PRP) | 12/9/1997 | | 1/23/1998 | | PASS |
|
|
|
started routing 12/9/97 REVIEWED 12/17/97- CORRECTIONS REQUIRED, FORWARD TO FIRE. FINAL RESUBS RECEIVED 1/22/98 TO ADDRESS CORRECTIONS. FIRE TO REVIEW FOR FINAL APPROVAL. 01/23/98 15:35:40 PRP - this action updated by action script from <<>> in Case No. BLD97-3581
|
Routing - PLAN CHECK | 1/21/1998 | | 1/22/1998 | | PASS |
|
|
|
TO FIRE
|
Routing - FIRE | 1/20/1998 | | 1/21/1998 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 1/21/1998 | | PEND |
|
|
|
RESUBS RECEIVED FROM HOSFORD, LARSON, RUDEEN
|
Plan resubmittals requested | 1/20/1998 | | 1/20/1998 | | PASS |
|
|
|
RECEIVED SUFFECIENT RESUBMITTALS TO ADDRESS PROBLEMS. PASS, FORWARD TO FIRE FOR FINAL APPROVAL. 1/22/98.
|
Plan Reviewer's activity | | | 1/20/1998 | | FAIL |
|
|
|
reviewed resubs and compare with corrections previously required. Changes did NOT completly address all items. Prepare additional correction notice and fax to arch, assemble and forward to Fire for rereview.
|
Plan resubmittals received | | | 1/20/1998 | | |
|
|
|
2 COPIES OF E2.01 E2.02 AND E2.03 ROUTED TO DICK PIERCE
|
Routing - PLAN CHECK | 12/24/1997 | | 1/20/1998 | | FAIL |
|
|
|
back to Fire
|
Routing - FIRE | 12/17/1997 | | 12/23/1997 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 12/17/1997 | | PASS |
|
|
|
REVIEWED PLANS AND RED LINE, PREPARE CORRECTION NOTICE AND FAX TO ARCH, INPUT TO TIDEMARK, FORWARD TO FIRE.
|
Print Pending Permit.LaserJet4 | | | 12/17/1997 | | PEND |
|
|
|
FILES
|
Plan resubmittals requested | 12/17/1997 | | 12/17/1997 | | FAIL |
|
|
|
see reviewer's activity 1/20/98
|
Routing - PUBLIC WORKS | 12/9/1997 | | 12/12/1997 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 12/3/1997 | | 12/9/1997 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 12/9/1997 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Application received | | | 12/3/1997 | | |
|
|
|
|