SUPER- Supervisor's review | 6/2/1998 | 6/2/1998 | 6/2/1998 | | |
|
|
|
stetson homes reviewd safety glazing requirements and they will change glazing adjacent to rear door of house. per their approved plan and they have already put in a new smoke detector per their approved plan on the second floor.
|
Receive PAYMENT IN FULL | | | 5/27/1998 | | |
|
|
|
|
CHANGE STATUS TO (I) | | | 5/27/1998 | | |
|
|
|
|
INSP - Final | 5/20/1998 | 5/21/1998 | 5/21/1998 | A | NR |
Wes Worcester
|
|
|
05/21/98 342 - 9AM APT W/GEORGE, CARL, JOHN AND ELECTRICIAN no approved invoice and letter, not ready
|
INSP - Final | 5/21/1998 | 5/21/1998 | 5/21/1998 | P | PASS |
Carl Dependahl
|
|
|
c/n ok; smoke det in, rec'd invoice & time table for installation of temp glass...faxed l/c to stetson hms. lc 015762
|
INSP - Final | 5/20/1998 | 5/20/1998 | 5/20/1998 | P | NR |
Wes Worcester
|
|
|
05/20/98 342 - ###-#### called John and will meet on site at 9am per Geo
|
INSP - Final | 5/16/1998 | 5/18/1998 | 5/18/1998 | P | FAIL |
Wes Worcester
|
|
|
05/18/98 342 - tempered glass, smk detector, winder out, no phone number bond, plan and engineering required
|
Routing - PUBLIC WORKS GRADING | 5/18/1998 | | 5/18/1998 | | BOND |
Rita DeYoung
|
|
|
Grading is approved. Minor revegetation is required for which a $250.00 bond must be submitted before the letter of compliance is issued.
|
INSP - Final | 5/5/1998 | 5/5/1998 | 5/5/1998 | P | FAIL |
Carl Dependahl
|
|
|
JOHN/###-#### - KEY ABOVE THE DOOR. nr, need eng's & pub. wks. ok...not complete insp
|
INSP - Framing/Rough-in | 3/10/1998 | 3/9/1998 | 3/9/1998 | P | PART |
Carl Dependahl
|
|
|
APPROVED RESUBMITTAL FOR EXERCISE RM & PORCH, PERMIT MODIFIED FOR INCREASE OF $10K VALUE BY LINDA
|
CHANGE STATUS TO (F) | | | 3/4/1998 | | FEES |
|
|
|
ADDITIONAL VALUE OF 10,000.00 ADDED ADDITIONAL ROOM. FEES DUE. LH/CD
|
INSP - Framing/Rough-in | 2/26/1998 | 2/26/1998 | 2/26/1998 | P | PART |
Carl Dependahl
|
|
|
DISCUSSED RESUB W/ JOHN OF STETSON HMS ###-####
|
INSP - Framing/Rough-in | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PART |
Carl Dependahl
|
|
|
reinsp...GOT RESUB, WILL REVIEW FOR ADDED AREA AND BEAM(FL.) W/ DJO...OK TO BEGIN COVER
|
INSP - Energy code compliance | 2/25/1998 | 2/25/1998 | 2/25/1998 | P | PART |
Carl Dependahl
|
|
|
JOHN ###-####
|
INSP - Framing/Rough-in | 2/23/1998 | 2/24/1998 | 2/24/1998 | A | PART |
Carl Dependahl
|
|
|
john ###-####...pending review of resub. added floor area at exercise room; eng's letter not stamped. keep c/n ok to continue.
|
INSP - Framing/Rough-in | 2/19/1998 | 2/20/1998 | 2/20/1998 | A | FAIL |
Carl Dependahl
|
|
|
02/20/98 340 - JOHN ###-#### NEED ENG'S OK,RESUBMIT FOR PORCH, ADDED FLO INSUL.
|
INSP - Framing/Rough-in | 2/18/1998 | 2/19/1998 | 1/18/1998 | A | FAIL |
Carl Dependahl
|
|
|
JOHN ###-#### no eng'd plan onsite wrote generic c/n, told to recall
|
INSP - Foundation | 1/16/1998 | 1/16/1998 | 1/16/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 -
|
INSP - Conference | 1/16/1998 | 1/16/1998 | 1/16/1998 | P | PASS |
Carl Dependahl
|
|
|
W/ CONC. CONTRACTOR....INSP REQ'S...NEED ENG'S LETTER.
|
INSP - Footings | 1/15/1998 | 1/16/1998 | 1/16/1998 | P | PASS |
Wes Worcester
|
|
|
01/16/98 342 - READY 2:00-PROBLEM CALL RANDY AT ###-####
|
INSP - Conference | 1/15/1998 | 1/15/1998 | 1/15/1998 | P | PASS |
Carl Dependahl
|
|
|
REC'D ENG'D RESUB FOR FTG
|
INSP - Footings | 1/15/1998 | 1/15/1998 | 1/15/1998 | P | PART |
Carl Dependahl
|
|
|
randy ###-####...NEED TO ADD FTG ADDED AT PLAN CHK. OK TO PLACE AREAS READY, RECALL REMAINDER. NEED ENGS LETTER.
|
Issue PAID IN FULL permit | | | 1/14/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 1/14/1998 | | PASS |
|
|
|
REC. ALL ENG. AND INFO REQ.
|
Print Occupancy Form | | | 1/14/1998 | | |
|
|
|
|
Telephone call | | | 1/14/1998 | | |
|
|
|
called and told her permit is ready
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/14/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/14/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 1/14/1998 | | |
|
|
|
|
Plan assigned to (DJO) | 12/10/1997 | | 1/14/1998 | | PASS |
Dan Overy
|
|
|
01/14/98 09:15:13 DJO - this action updated by action script from <<>> in Case No. BLD97-3651
|
Plan Reviewer's activity | | | 1/7/1998 | | PEND |
|
|
|
Revision submitted. Incomplete. Contractor and engineer are sending additional revisions.
|
Plans ACCEPTED BY PLAN CHECK | | | 12/28/1997 | | PEND |
|
|
|
plans incomplete as submitted. Engineering, beams, wall bracing, calcs, etc. Informed contractor. Picked up for revisions.
|
Routing - PLANNING | 12/17/1997 | | 12/19/1997 | | PASS |
|
|
|
APPROVED BY RC.
|
Routing - PUBLIC WORKS | 12/10/1997 | | 12/17/1997 | | PASS |
|
|
|
|
Application received | | | 12/10/1997 | | |
|
|
|
|
Routing - PLAN CHECK | 12/19/1997 | | | | PEND |
|
|
|
|