Permanent Occupancy | | 3/20/1998 | 3/20/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/20/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7179 issued 3-20-98 to Ada County Operations for the mezzanine storage area expansion.
|
90 day tracking............. | | 12/15/1997 | 3/15/1998 | | PEND |
|
|
|
|
INSP - Final | 3/4/1998 | 3/5/1998 | 3/5/1998 | A | PASS |
|
|
|
03/05/98 338 - 10:30 a.m. no access called operations manager derrick le
|
INSP - Final | 3/3/1998 | 3/3/1998 | 3/3/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP FOR FINAL OK FOR CERT OF COMPLETION
|
INSP - Framing/Rough-in | 2/26/1998 | 2/27/1998 | 2/27/1998 | P | NR |
|
|
|
02/27/98 338 - what kind of insp is requestednks he is ready for a final
|
INSP-Sprinkler Rough-in/Hydro | 2/26/1998 | 2/27/1998 | 2/27/1998 | A | FAIL |
Joe Tawney
|
|
|
02/27/98 406 - robert ###-#### FINAL CONSTRUCTION OK SPKLR SYSTEM NEEDS ANNUAL INSPECTION FAIL
|
INSP - Framing/Rough-in | 2/19/1998 | 2/19/1998 | 2/19/1998 | P | PASS |
|
|
|
02/19/98 338 - madeok need to brace / block ends of joists at the stair
|
INSP - Footings | 2/4/1998 | 2/4/1998 | 2/4/1998 | | PASS |
|
|
|
/ / 338 - made ok r-bar placed
|
INSP - Footings | 2/4/1998 | 2/4/1998 | 2/4/1998 | | PASS |
|
|
|
/ / 338 - made ok r-bar placed
|
INSP - Footings | 2/3/1998 | 2/4/1998 | 2/4/1998 | A | NR |
|
|
|
02/04/98 338 - ken ###-#### no access
|
INSP - Framing/Rough-in | 1/22/1998 | 1/23/1998 | 1/23/1998 | A | PASS |
|
|
|
01/23/98 338 - this is a conference on the comparison of the existing bu new remodel plan for the mezz extension need to cut slab to be sure of questions
|
Issue PAID IN FULL permit | | | 1/21/1998 | | |
|
|
|
|
Telephone call | | | 1/20/1998 | | |
|
|
|
CALLED 1/20/98-LEFT MESSAGE ON MACHINE-
|
Print Occupancy Form | | | 1/20/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 1/20/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/1998 | | PASS |
|
|
|
No response from architect for new certificate of value for Sprinkler modification. Will request inspection of fire sprinklers any way and will issue permit.
|
Inspection Record Card- Bld | | | 1/20/1998 | | |
|
|
|
|
Plan assigned to (R_H) | 12/19/1997 | | 1/20/1998 | | PASS |
|
|
|
01/20/98 11:33:55 R_H - this action updated by action script from <<>> in Case No. BLD97-3677
|
Plan Reviewer's activity | | | 1/8/1998 | | PASS |
|
|
|
CALLED ROBERT STEWART / REQUESTED FINAL CERTIFICATE OF VALUE TO REFLECT THE SPRINKLER MODIFICATIONS THAT ARE REQUIRED.
|
Plan Reviewer's activity | | | 1/6/1998 | | PEND |
|
|
|
REVIEWED PLANS NO CORRECTIONS REQUIRED/ WILL ROUTE TO FIRE DEPARTMENT.
|
Plan routing begun/TENANTS | | | 12/19/1997 | | |
|
|
|
This plan to be reviewed by PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 12/15/1997 | | 12/19/1997 | | |
Marlene Southard
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 12/15/1997 | | PEND |
|
|
|
|
Application received | | | 12/15/1997 | | |
|
|
|
|
Routing - FIRE | 1/7/1998 | | 1/8/1997 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 1/8/1998 | | | | |
|
|
|
|