Permit Information
Permit NumberBLD97-03708
StatusFinaled
Name DR. THOMAS MCKIM (ADA PLSTC & RECON SRGY)
Site Address 900 N LIBERTY ST
Project NameST ALS OFFICE #5
Customer Number 
ePlanReviewNo
Description
(DR THOMAS MCKIM - ADA PLASTIC & RECONSTRUCTIVE SURGERY) This building is fully fire sprinkled. To create and complete a 2,712 square foot medical office tenant space on the 3rd floor of St. Al's MOB #5. Work is to include a 1-hr corridor connecting the building stair enclosures, a restroom accessible to the disabled, a medical gas storage room, interior nonbearing walls, and suspended ceilings all per approved drawings and plan check conditions on file. The fire sprinkler system shall comply with NFPA 13 as regulated by the Fire Department. Patients rendered incapable of unassisted self-preservation shall never exceed five (5) at any time. PC-805-97 **CJW**
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  3/1/1999 PASS
Perm. Occ. Cert. #7659 issued 3-1-99 to Dr. Thomas McKim - Ada Plastic and Reconstructive Surgery.
Permanent Occupancy 2/25/19992/25/1999 DONE
Details
Print Occupancy Form  2/25/1999 PASS
reprint, lost card.
INSP - Occup. violation notice11/18/199811/18/199811/18/1998 FAIL
Details
/ / 338 - ISSUED OCC VIOLATION TO KCI INC SIGNED BY CECIL.
INSP - Occup. violation notice11/18/199811/17/199811/18/1998 FAIL
Details
/ / 338 - ISSUED OCC VIOLATION TO KCI INC SIGNED BY CECIL.
Temporary occupancy  7/10/1998 PASS
Temp. Occ. Cert. #3655 issued 7-10-98 to Dr. Thomas McKim.
INSP-Final Inspection7/9/19987/9/19987/9/1998PPART
DetailsRick Jackson
RON ###-#### PAGER awaiting smoke/fire damper requirements in corridor wall. temp occ approved
INSP - Final7/8/19987/9/19987/9/1998ANR
Details
07/09/98 338 - ###-#### still need fire lifesafety and sprink ok by r. j
INSP-Final Inspection7/2/19987/7/19987/7/1998PFAIL
DetailsRick Jackson
RON ###-#### PAGER dampers, med gas identification and certification, suite #, NFPA 72, tested alarms - okay
INSP - Framing/Rough-in5/14/19985/14/19985/15/1998PPART
Details
05/15/98 338 - 3rd floor north end of bldg. ron ###-#### pager
INSP-Conference5/6/19985/6/19985/6/1998PPART
DetailsJoe Tawney
05/06/98 406 - ron ###-#### pager floor 3 CONF ON MOVING S/F DAMPER OK IF STRUCTURAL CAN BE ACCOMPLISHED PER PERRY
INSP - Framing/Rough-in3/30/19983/31/19983/31/1998APART
Details
made ok to start hanging drywall will check fire caulking at another date
90 day tracking............. 12/18/19973/18/1998 PEND
Issue PAID IN FULL permit  3/10/1998
INSP - Final2/25/19992/25/19992/25/1998APASS
DetailsCarl Dependahl
ok per 338...new card to contractor.
Telephone call  2/23/1998
called rob it said owner should be here with check this week
Inspection Record Card- Bld  1/20/1998
Telephone call  1/20/1998
CALLED ROB GAVE HIM THE $ AMOUNT
Print Occupancy Form  1/20/1998
PLANS/APPL TAKEN TO FRONT DESK  1/16/1998 PASS
Drawings approved, with conditions, as noted and attached.
Plan assigned to (CJW)12/23/1997 1/16/1998 PASS
DetailsCarl Westfall
01/16/98 15:19:19 CJW - this action updated by action script from <<>> in Case No. BLD97-3708
Routing - FIRE1/8/1998 1/15/1998 PASS
testing condition printout  1/7/1998
Print permit w/o conditions  1/7/1998
Plan Reviewer's activity  1/5/1998 PASS
UBC plan review started Jan. 5, 1998 and finished Jan. 7,1997. Drawings approved, with conditions, as noted and attached to the approved drawings.
Routing - PLUMBING12/29/1997 12/31/1997 PASS
Routing - PUBLIC WORKS12/29/1997 12/29/1997 PASS
Plan routing begun/TENANTS  12/23/1997
Route to PUBLIC WORKS, PLUMBING, PLAN CHECK and FIRE.
Plan assigned to (MYS)12/18/1997 12/23/1997
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  12/18/1997 PEND
Application received  12/18/1997
Routing - PLAN CHECK1/15/1998