Permit Information
Permit NumberBLD97-03761
StatusExpired
Name ASIN HOMES
Site Address 1510 ROBERTS RD
Project NameROBERTS OFFICE II
Customer Number 
ePlanReviewNo
Description
ROBERTS OFFICE BUILDING PHASE II * TO CONSTRUCT A NEW 3,360 SQ. FT. OFFICE BUILDING that will include 3 office suites. Floors, walls & Roof are of cumbustible construction. North wall 1hr F.R. w/out parapet per exception 5 of UBC709.4.1. DRH97-223 PC#819-97 ads
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final9/16/19989/16/19989/17/1998PPASS
DetailsJim Storey
09/17/98 301 - Scheduled by Hello!. Contact phone is [8702712]. FNL -OK FINAL signed temp pending others.
Code Occupancy Approval  9/15/1998 PASS
PARKING LANDSCAPE AND FENCE IN AS REQUIRED, FINAL SIGNED OFF.
INSP - Final9/10/19989/11/19989/11/1998AFAIL
DetailsJim Storey
09/11/98 301 - MIKE ###-#### FN OCC INSP CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP-Final Inspection9/10/19989/11/19989/11/1998APASS
DetailsRick Jackson
MIKE ###-#### RE-INSP ON FN occ approved for shell only
INSP-Conference9/9/19989/9/19989/9/1998PFAIL
DetailsRick Jackson
SCOTT ###-#### BULD UNLOCKED request was for final inspection. needs address and suite numbers, extinguishers, check draft stops
Code Occupancy Approval  9/9/1998 FAIL
MISSING 3' AND 5' SOUTH PROPERTY LINE FENCE TO BUFFER RESIDENCE AND PARKING LOT STRIPPING, WILL FAX BID TO COMPLETE AND POST BOND BEFORE I WILL SIGN.
INSP - Framing/Rough-in6/24/19986/24/19986/24/1998PPASS
DetailsJim Storey
06/24/98 301 - nailing ceiling lids/mike ###-####
INSP - Energy code compliance6/22/19986/22/19986/22/1998PPASS
DetailsJim Storey
06/22/98 301 - INSL-OK INSULATION-ENERGY CODE
INSP - Framing/Rough-in6/19/19986/19/19986/19/1998PNR
DetailsCarl Dependahl
not insp; conf w/ 316 & contractor.
INSP - Framing/Rough-in6/19/19986/19/19986/19/1998APASS
DetailsJim Sly
06/19/98 316 - OK as per discussion with George Slane, Wes W. and Carl D
SUPER- Supervisor's review6/22/1998 6/19/1998 D
conferance with contractor as to openings in roof on wall on property line and no parput. for this constuction no opening within 10 feet on the roof per the approved plan and one hour constuction on the property line wall the ceiling and supporting constuction. ok to proceed. review with inspectors. it is one hour constuction not one hour with protected openings in the ceiling.
INSP - Framing/Rough-in6/16/19986/17/19986/18/1998PFAIL
DetailsJim Storey
06/17/98 301 - c/n 709.4.1 ecpception 5.2
INSP - Framing/Rough-in6/3/19986/4/19986/4/1998APART
DetailsJim Storey
06/04/98 301 - SHEER WALL MIKE ###-#### sheer nailling ok
INSP - Framing/Rough-in6/2/19986/2/19986/2/1998PFAIL
DetailsJim Storey
06/02/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP-Conference5/18/19985/18/19985/18/1998PFAIL
DetailsJim Storey
05/18/98 301 - no one on site for conf.
INSP - Foundation4/29/19984/29/19984/30/1998PPASS
Details
R-BAR PLACEDne ###-####
INSP - Foundation4/29/19984/29/19984/29/1998 PASS
Details
04/30/98 338 - made ok setbacks appear ok rear also ready to cover
INSP - Foundation4/29/19984/29/19984/29/1998 PASS
Details
04/30/98 338 - made ok setbacks appear ok rear also ready to cover
INSP - Foundation4/27/19984/28/19984/28/1998APASS
DetailsJim Storey
04/28/98 301 - FRMS-OK FORMS-REBAR
90 day tracking............. 12/23/19973/23/1998 PEND
(F) Reprint permit  2/13/1998
Telephone call  2/12/1998 PASS
mark ###-####
Print Occupancy Form  2/12/1998
Issue PAID IN FULL permit  2/12/1998
Inspection Record Card- Bld  2/12/1998
Print Occupancy Form  2/12/1998
Received Certificate of Value  2/11/1998 PASS
Final Values
PLANS/APPL TAKEN TO FRONT DESK  2/11/1998 PASS
Routing Off Site - A.C.H.D2/11/1998 2/11/1998 PASS
Impact fee paid ACHD receipt # 98-0793.
Routing Off Site - A.C.H.D12/29/1997 2/3/1998 FAIL
PACKAGE #2 CONTACTED MARK SANDERS AT ###-#### TO TAKE PLANS OUT TO ACHD. ACHD FEES DUE
Routing - PLAN CHECK1/16/1998 1/30/1998 PASS
Plan assigned to (ADS)12/29/1997 1/30/1998 PASS
Details
Routing - FIRE1/15/1998 1/16/1998 PASS
PACKAGE #1
Routing - PLAN CHECK1/14/1998 1/15/1998 PASS
Plans approved as drawn with the attached notes. ADS
Routing - PLUMBING1/14/1998 1/14/1998 PASS
PACKAGE #1
Routing - PUBLIC WORKS1/12/1998 1/13/1998 PASS
Routing - PLANNING12/31/1997 1/8/1998 PASS
PACKAGE #1 X-REF: DRH97-0223. APPROVED BY TKW.
Routing - PUBLIC WORKS12/31/1997 12/31/1997 FAIL
PACKAGE #1 REQUIRES THREE MORE COPIES OF DRAINAGE PLANS.
Routing Off Site - STRUCTURAL12/29/1997 12/29/1997
PER JOHN MENARD WE WILL BE DOING ENGINEERING.
Plan routing begun/NEW & ADDTN  12/29/1997 PASS
Plans ACCEPTED BY PLAN CHECK  12/29/1997 PASS
PLANS SUBMITTED UNDER 3 PACKAGE DEAL 1. PACKAGE #1 2 SEPARATE SUBMITTALS (IN HOUSE) 2. PACKAGE #2 2 SEPARATE SUBMITTALS (ACHD) 3. PACKAGE #3 ONE SUBMITTAL (OUTSIDE ENG.) WE WILL DO ENG. PER JOHN M. 4. DRAINAGE CALC. 5. NO PROJECT MANUEL OR STRUCTURAL CALCS. ( SUBMITTED UNDER 1994 UBC SECTION 2326) KMM
Plan assigned to (MYS)12/23/1997 12/29/1997 PASS
DetailsMarlene Southard
Received Certificate of Value  12/23/1997 PASS
Recd Pcfee & Taken To Pln CK  12/23/1997
Application received  12/23/1997