Fee Review-notes | 6/15/1999 | | 7/20/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 6/16/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7792 issued 6-16-99 to Burger King for the play area.
|
INSP-Final Inspection | 6/10/1999 | 6/11/1999 | 6/11/1999 | A | PASS |
Joe Tawney
|
|
|
06/11/99 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 6/9/1999 | 6/11/1999 | 6/11/1999 | P | PASS |
Carl Dependahl
|
|
|
06/11/99 340 - blake ###-#### card to cont
|
Permanent Occupancy | | 6/11/1999 | 6/11/1999 | | DONE |
|
|
|
|
Temporary occupancy | | | 6/11/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3851 issued 6-11-99 to Burger King.
|
Code Occupancy Approval | | | 6/11/1999 | | PASS |
|
|
|
Final requested by Blake ###-#### INSPECTION SHOWED ALL CONDITIONS OF DRH97-0244 HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
|
INSP-Final Inspection | 6/9/1999 | 6/10/1999 | 6/10/1999 | P | FAIL |
Joe Tawney
|
|
|
06/10/99 406 - REINSP FAIL EXIT SIGN & EMERG LIGHT
|
INSP - Framing/Rough-in | 6/7/1999 | 6/7/1999 | 6/7/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - APPROVED RESUBFORFRAMECHANGES;FILED
|
INSP - Framing/Rough-in | 6/4/1999 | 6/4/1999 | 6/4/1999 | P | PART |
Carl Dependahl
|
|
|
06/04/99 340 - beam ok; conf re final
|
INSP-Final Inspection | 6/3/1999 | 6/4/1999 | 6/4/1999 | A | FAIL |
Joe Tawney
|
|
|
06/04/99 406 - FINAL FAIL EXIT SIGNS, FIRE EXT, EMERG LIGHT
|
INSP - Framing/Rough-in | 5/27/1999 | 5/28/1999 | 5/28/1999 | A | PART |
Carl Dependahl
|
|
|
05/28/99 340 - CFRM-OK CEILING FRAMING
|
INSP - Foundation | 5/27/1999 | 5/27/1999 | 5/27/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - ISOLATED INT FTG BPOURED W/O INSP, SEND REPORT OR ENG'S LETT
|
Print Occupancy Form | | | 5/20/1999 | | MLS |
|
|
|
|
Inspection Record Card- Bld | | | 5/20/1999 | | |
|
|
|
|
INSP - Framing/Rough-in | 5/17/1999 | 5/18/1999 | 5/18/1999 | A | FAIL |
Carl Dependahl
|
|
|
05/18/99 340 - ###-#### BLAKE//FRAMING; c/n, need clarify beam & ftg
|
INSP - Framing/Rough-in | 5/14/1999 | 5/14/1999 | 5/14/1999 | P | PART |
Carl Dependahl
|
|
|
05/14/99 340 - Blake ###-#### ok to ins. ext wall, keep c/n
|
INSP - Framing/Rough-in | 5/13/1999 | 5/13/1999 | 5/13/1999 | P | FAIL |
Carl Dependahl
|
|
|
05/13/99 340 - roof sheathing/ Blake ###-####; c/n resubs, truss eng'g,
|
INSP - Foundation | 4/23/1999 | 4/23/1999 | 4/26/1999 | P | FAIL |
Carl Dependahl
|
|
|
04/23/99 340 - fnd wall, sent to 316 in error; poured w/o insp, work chk
|
INSP - Foundation | 4/23/1999 | 4/23/1999 | 4/23/1999 | P | FAIL |
Jim Sly
|
|
|
04/23/99 316 - Done by Carl D.
|
INSP - Foundation | 4/22/1999 | 4/22/1999 | 4/22/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - BOLTS FOR STEEL COL'S; NEED FILL AT BASE PLATES & SPEC INSP
|
INSP - Foundation | 4/12/1999 | 4/12/1999 | 4/12/1999 | P | PART |
Carl Dependahl
|
|
|
04/12/99 340 - footing\\###-####; ftgs, rebar ok
|
INSP - Framing/Rough-in | 3/31/1999 | 3/31/1999 | 3/31/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - REC'D RESUB FOR FRAMING AT GREENHSE; NO CAL FOR INSP
|
Plan resubmittals received | | | 3/17/1999 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS FROM PATRICK McKEEGAN, FORWARDED SAME TO CARL DEPENDHAL. DAR 3/17/99
|
Permit EXTENDED | | | 12/7/1998 | | OK |
|
|
|
Pat McKeegan requested 180 day extention on 11/30/98. This is OK with me. Dave Hattrick
|
Issue PAID IN FULL permit | | | 8/26/1998 | | |
|
|
|
|
Telephone call | | | 8/18/1998 | | PASS |
|
|
|
PAT MCKEEGAN IS WAITING FOR THE OWNERS TO SEND A CHECK
|
Office Staff conference/action | | | 8/13/1998 | | PASS |
|
|
|
CUSTOMER CAME IN PAT MCKEEGAN WILL PICK UP PLANS NEXT WEEK
|
Office Staff conference/action | | | 8/3/1998 | | PASS |
|
|
|
Mike Hashim faxed over a letter of extesion to dave/dave okay'd extension for 30 days
|
Telephone call | | | 7/14/1998 | | PASS |
|
|
|
called Pat ###-####
|
Inspection Record Card- Bld | | | 7/14/1998 | | |
|
|
|
|
Print Occupancy Form | | | 7/14/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/10/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/10/1998 | | PEND |
|
|
|
received resubmittals on 7/6/98 found on my desk 7/10/98 were mailed in and given to me from Cathy's desk.
|
Plan Reviewer's activity | | | 7/10/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 1/29/1998 | | 7/1/1998 | | PASS |
Mike Phillips
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/1/1998 | | PAS\ |
|
|
|
|
Plan Reviewer's activity | | | 6/25/1998 | | FAIL |
|
|
|
Requested submittal of calculations for snow drifting and CABO/ANSI letter of what items of existing building will be upgraded at this time.
|
Routing - FIRE | 6/24/1998 | | 6/25/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 6/22/1998 | | 6/23/1998 | | PASS |
|
|
|
approved per DRH97-0244. Landscaping shall comply with drawing in Design Review file.
|
Plan resubmittals received | | | 6/18/1998 | | |
|
|
|
RECEIVED 4 COPIES OF REVISED SHEETS A1.0, A2.1, A3.2, AND S1.1. ROUTED TO MIKE P.
|
90 day tracking............. | | 1/26/1998 | 4/26/1998 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 1/27/1998 | | 3/24/1998 | | PASS |
|
|
|
CONTACTED PAT MCKEEGAN AT###-#### TO TAKE PLANS OUT TO ACHD. I WILL ROUTE TO ACHD WHEN I RECEIVE PLANS. NO ACHD FEES REQUIRED PER MGG.
|
Routing - FIRE | 2/3/1998 | | 2/12/1998 | | FAIL |
|
|
|
|
Plan Reviewer's activity | | | 2/4/1998 | | FAIL |
|
|
|
Sent correction report to Architect
|
Print Pending Permit.LaserJet4 | | | 2/4/1998 | | FAIL |
|
|
|
Sent correction letter to Architect.
|
Routing - PLANNING | 1/29/1998 | | 1/30/1998 | | FAIL |
|
|
|
X-REF: DRH97-0244. DESIGN REVIEW CONDITION HAVE NOT BEEN MET/INDICATED ON A REVISED PLAN. REVIEWED BY MGS.
|
Plan assigned to (JCM) | 1/26/1998 | | 1/29/1998 | | PASS |
John Menard
|
|
|
|
Routing - PLUMBING | 1/28/1998 | | 1/29/1998 | | |
|
|
|
No review required.
|
Routing - PUBLIC WORKS | 1/26/1998 | | 1/28/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 1/26/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 1/26/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 1/26/1998 | | PASS |
|
|
|
CONTACTED PAT MCKEEGAN AND ASKED IF HE WOULD LIKE TO SUBMIT AN ACHD SET. HE HAD ONLY SUBMITTED 2 FULL COPIES. HE STATED THAT HE WOULD SUBMIT AN ACHD SET. WITH HIS 2 FULL COPIES HE SUBMITTED ONE COPY OF STRUCT. CALCS. KMM 1-27-98 RECEIVED ACHD COPIES. ROUTED TO ACHD VIA PAT
|
Application received | | | 1/23/1998 | | |
|
|
|
|
INSP - Framing/Rough-in | 6/7/1999 | 6/7/1999 | | | |
|
|
|
|