INSP - Final | 12/22/1998 | 12/23/1998 | 12/23/1998 | A | PASS |
Wes Worcester
|
|
|
12/23/98 342 - SCOTT ###-#### KEY IS ABOVE DOOR
|
INSP - Energy code compliance | 7/29/1998 | 7/29/1998 | 7/29/1998 | P | FAIL |
Carl Dependahl
|
|
|
07/29/98 340 -
|
INSP - Framing/Rough-in | 7/29/1998 | 7/29/1998 | 7/29/1998 | P | FAIL |
Carl Dependahl
|
|
|
07/29/98 340 - 2ND C/N, FIX TRUSS FIX, POVIDE REST TRUSS INFO & SPRINKLE
|
INSP - Energy code compliance | 7/28/1998 | 7/28/1998 | 7/28/1998 | | NR |
Carl Dependahl
|
|
|
07/28/98 340 -
|
INSP - Framing/Rough-in | 7/28/1998 | 7/28/1998 | 7/28/1998 | | NR |
Carl Dependahl
|
|
|
07/28/98 340 - scott ###-#### reinspection nr, need sprinklers rerouted
|
INSP - Framing/Rough-in | 7/27/1998 | 7/27/1998 | 7/27/1998 | P | FAIL |
Carl Dependahl
|
|
|
still need truss repair, etc
|
INSP - Framing/Rough-in | 7/24/1998 | 7/24/1998 | 7/24/1998 | P | FAIL |
Carl Dependahl
|
|
|
07/24/98 340 - SCOTT ###-#### REINSPECTION C/N, NEED TRUSS CALCS, SRINKLER R/I OK, ETC.
|
INSP - Energy code compliance | 7/24/1998 | 7/24/1998 | 7/24/1998 | P | NR |
Carl Dependahl
|
|
|
07/24/98 340 - ###-#### SCOTT REINSPECTION FRAME C/N
|
INSP - Framing/Rough-in | 7/16/1998 | 7/16/1998 | 7/16/1998 | P | FAIL |
Carl Dependahl
|
|
|
conf w/ bldr...need complete mech insp prior to insulation; htg sticker onsite apparently was only for f.p...keep c/n. no insp
|
INSP - Framing/Rough-in | 7/15/1998 | 7/15/1998 | 7/15/1998 | P | FAIL |
Carl Dependahl
|
|
|
scott ###-#### call before going so he can meet you. c/n need complete truss calcs; fireblocks, straps, nailing at brace panels, winder stairs, truss eng'r to ok holes at bottom chords attic trusses, support overnotched rafters at porch, plbg c/n, verify sprinkler r/i, elec, etc... will meet w/ bldr .
|
INSP - Foundation | 5/4/1998 | 5/1/1998 | 5/1/1998 | P | PART |
Carl Dependahl
|
|
|
FOUND WALL
|
INSP - Wall cover | 5/1/1998 | 5/1/1998 | 5/1/1998 | P | NR |
Carl Dependahl
|
|
|
matt ###-#### NOT WALL COVER ...FND.
|
INSP - Foundation | 4/30/1998 | 4/30/1998 | 4/30/1998 | P | PART |
Carl Dependahl
|
|
|
steve ###-####
|
INSP - Foundation | 4/29/1998 | 4/29/1998 | 4/29/1998 | P | FAIL |
Carl Dependahl
|
|
|
need eng's letter/resubmittal...added ftg size, compacted fill,etc. Glenn Johnson Hms
|
INSP - Foundation | 4/28/1998 | 4/28/1998 | 4/28/1998 | P | FAIL |
Carl Dependahl
|
|
|
footing steve ###-####...need plans & eng'g onsite
|
Issue PAID IN FULL permit | | | 4/22/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/14/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 4/14/1998 | | PASS |
|
|
|
contractor has modified plans for minimum 2'-8" brace panels.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/14/1998 | | |
|
|
|
|
Telephone call | | | 4/14/1998 | | |
|
|
|
CALLED GLENN GAVE $ AMOUNT AND ALSO TOLD HIM FEE DUES WILL HAVE TO BE PAID
|
Inspection Record Card- Bld | | | 4/14/1998 | | |
|
|
|
|
Plan assigned to (DJO) | 2/4/1998 | | 4/14/1998 | | PASS |
Dan Overy
|
|
|
04/14/98 09:58:52 DJO - this action updated by action script from <<>> in Case No. BLD98-0271
|
Plans ACCEPTED BY PLAN CHECK | | | 3/4/1998 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 3/4/1998 | | PEND |
|
|
|
ADDITIONAL ENGINEERING REQUIRED FOR WALL BRACING.
|
Routing - PLANNING | 2/10/1998 | | 2/18/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 2/4/1998 | | 2/10/1998 | | PASS |
|
|
|
|
Application received | | | 2/4/1998 | | |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 2/9/1998 | | 2/9/1997 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 3
|
Routing - PLAN CHECK | 2/18/1998 | | | | PEND |
|
|
|
|