Permit Information
Permit NumberBLD98-00313
StatusFinaled
Name JOHN MCNULTY
Site Address 14088 W BATTENBERG CT
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 1965 sq. ft. one story single family dwelling with a 808 sq. ft. attached three car garage a 228 sq. ft. covered entry porch and a 210 sq. ft. partially covered concrete patio per approved plans, attached engineering/red-lined plans and requirement lists. ACHD #98-0773 PC #110 CU #50-94 DJO
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled2/8/20012/8/20012/8/2001APASS
DetailsJim Sly
Added by Inspector: 316 On 2/8/2001 9:12:24 AM
INSP - Final4/21/19984/22/19984/22/1998APASS
DetailsTom Arcoraci
04/22/98 408 - ###-####/JOHN.
INSP - Framing/Rough-in3/17/19983/18/19983/18/1998PPASS
DetailsJim Sly
03/18/98 316 - john ###-#### ì
INSP - Energy code compliance3/17/19983/18/19983/18/1998PPASS
DetailsJim Sly
03/18/98 316 - JOHN ###-#### ì
INSP - Wall cover3/9/19983/10/19983/10/1998APASS
DetailsJim Sly
03/10/98 316 - SHEER WALL NAILING--OK
Issue PAID IN FULL permit  2/23/1998
Plan assigned to (DJO)2/9/1998 2/19/1998 PASS
DetailsDan Overy
02/19/98 14:09:41 DJO - this action updated by action script from <<>> in Case No. BLD98-0313
Telephone call  2/19/1998
TRYED TO CALL HAS NOT SET UP MAIL BOX COULDN'T LEAVE MESSAGE
Print Pending Permit.LaserJet4  2/19/1998 PASS
Inspection Record Card- Bld  2/19/1998
Plans ACCEPTED BY PLAN CHECK  2/19/1998 PASS
Routing - FRONT DESK2/17/1998 2/19/1998 PASS
PLANS/APPL TAKEN TO FRONT DESK  2/19/1998 PASS
INSP - Concrete2/17/19982/18/19982/18/1998APART
DetailsJim Sly
02/17/98 316 - Height, foot width and soil OK...Setbacks appear OK but n
Routing - PUBLIC WORKS2/13/1998 2/17/1998 PASS
Print Pending Permit.LaserJet4  2/13/1998
Routing - PLANNING2/11/1998 2/11/1998 PASS
APPROVED BY ANGELA BROSIOUS
Office Staff conference/action  2/11/1998 PASS
gave to dan for approval of early start
Routing - PLANNING2/9/1998 2/10/1998 FAIL
denied by Angela Brosious
Office Staff conference/action  2/10/1998 FAIL
put in drawer
Telephone call  2/10/1998
TALKED TO JOHN AT BUILDERS WEST, PLAN FAILED, BRINGING REVISED SITE PLANS.
Application received  2/9/1998