(F) Reprint permit | | | 8/12/1998 | | PASS |
|
|
|
|
(F) Reprint permit | | | 8/5/1998 | | PASS |
|
|
|
|
Permanent Occupancy | | 7/25/1998 | 7/25/1998 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/29/1998 | 6/1/1998 | 7/15/1998 | A | PASS |
|
|
|
rick ###-#### final occ
|
Permanent occupancy | | | 7/15/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7312 issued 7-15-98 to the Grove Hotel 4th floor offices.
|
CHANGE STATUS TO (I) | | | 7/14/1998 | | |
|
|
|
|
Fee Review-notes | 7/14/1998 | | 7/14/1998 | | |
|
|
|
|
INSP - Final | 7/7/1998 | 7/7/1998 | 7/7/1998 | | PART |
|
|
|
/ / 333 - PROFIT MEETING
|
INSP - Final | 7/2/1998 | 7/2/1998 | 7/2/1998 | P | PASS |
|
|
|
07/02/98 333 - 4th floor/rick ###-####
|
INSP - Framing/Rough-in | 6/30/1998 | 7/1/1998 | 7/1/1998 | P | PASS |
|
|
|
07/01/98 333 - sign ok
|
INSP-Final Inspection | 6/26/1998 | 6/29/1998 | 6/29/1998 | P | FAIL |
Rick Jackson
|
|
|
couldn't test roll-up doors, alarm plans, smoke evac not ready
|
INSP-Final Inspection | 6/24/1998 | 6/24/1998 | 6/24/1998 | P | FAIL |
Rick Jackson
|
|
|
rick ###-#### alarms, roll up shutters didn't work with alarms, strobe in vending
|
CHANGE STATUS TO (F) | | | 6/23/1998 | | |
|
|
|
|
INSP - Final | 6/15/1998 | 6/15/1998 | 6/15/1998 | P | PART |
|
|
|
06/15/98 333 - SILLS OK
|
INSP - Final | 6/11/1998 | 6/11/1998 | 6/11/1998 | A | FAIL |
|
|
|
06/11/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
Temporary occupancy | | | 6/4/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3631 issued 6-4-98 to the Grove Hotel, 4th floor.
|
INSP - Final | 6/3/1998 | 6/3/1998 | 6/3/1998 | P | PART |
|
|
|
06/03/98 333 - cn placed temp ok
|
INSP-Final Inspection | 6/2/1998 | 6/3/1998 | 6/3/1998 | A | PART |
Rick Jackson
|
|
|
requested by gen contractor for am temp occ approved. suites not ready to occupy
|
INSP-Final Inspection | 6/1/1998 | 6/2/1998 | 6/2/1998 | A | FAIL |
Rick Jackson
|
|
|
Rick ###-#### temp occ. c/n issued. alarms not ready, smoke evac calcs needed, etc.
|
INSP - Final | 6/1/1998 | 6/2/1998 | 6/2/1998 | A | FAIL |
|
|
|
06/02/98 333 - not ready
|
INSP-Final Inspection | 6/1/1998 | 6/1/1998 | 6/1/1998 | P | FAIL |
Rick Jackson
|
|
|
fire alarm panel not working. lan smith notified of situation and will talk to owners
|
INSP - Final | 5/29/1998 | 6/1/1998 | 6/1/1998 | A | FAIL |
|
|
|
06/01/98 333 - not ready
|
INSP - Final | 5/28/1998 | 5/29/1998 | 5/29/1998 | A | CANC |
|
|
|
05/29/98 333 - canc by Rick
|
INSP-Final Inspection | 5/28/1998 | 5/29/1998 | 5/29/1998 | A | FAIL |
|
|
|
4TH FLOOR--TEMP OCC--RICK ###-#### Left list, smoke exhaust not functional, areas of corridor not detected, not lit by npormal or emergency lights, elevators do not recall from this floor.
|
INSP - Final | 5/27/1998 | 5/28/1998 | 5/28/1998 | P | FAIL |
|
|
|
05/28/98 333 - not ready
|
INSP - Framing/Rough-in | 5/19/1998 | 5/20/1998 | 5/20/1998 | P | PART |
|
|
|
05/20/98 333 - grid ok
|
INSP - Framing/Rough-in | 5/15/1998 | 5/18/1998 | 5/18/1998 | P | FAIL |
Jim Storey
|
|
|
05/18/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 4/1/1998 | 4/1/1998 | 4/1/1998 | P | PASS |
|
|
|
04/01/98 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 3/27/1998 | 3/30/1998 | 3/30/1998 | A | PART |
|
|
|
03/30/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to cover al
|
INSP - Framing/Rough-in | 3/11/1998 | 3/11/1998 | 3/11/1998 | P | PART |
|
|
|
03/11/98 333 - upper walls ok
|
INSP - Framing/Rough-in | 3/10/1998 | 3/10/1998 | 3/10/1998 | P | FAIL |
|
|
|
03/10/98 333 - cover without insp
|
(F) Reprint permit | | | 3/5/1998 | | |
|
|
|
|
testing condition printout | | | 3/4/1998 | | |
|
|
|
|
Print permit w/o conditions | | | 3/4/1998 | | |
|
|
|
|
Telephone call | | | 3/4/1998 | | |
|
|
|
called left message
|
Inspection Record Card- Bld | | | 3/4/1998 | | |
|
|
|
|
Print Occupancy Form | | | 3/4/1998 | | |
|
|
|
|
Telephone call | | | 3/4/1998 | | |
|
|
|
left message for skip on answeringmachine
|
Issue PAID IN FULL permit | | | 3/4/1998 | | |
|
|
|
|
Print permit w/o conditions | | | 3/2/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 2/27/1998 | | PASS |
|
|
|
The original permit (BLD97-1950) covered both the 3rd and 4th floor work. This permit was created because the owner wanted to use separate contractors for the the 3rd and 4th floor work. This permit (BLD98-0482) covers the 4th floor. The former permit (BLD97-1950) has been altered to cover only the 3rd floor.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 2/27/1998 | | PASS |
|
|
|
New permit for 4th floor only taken to the permits desk.
|
Application received | | | 2/10/1998 | | |
|
|
|
|