Permanent Occupancy | | 10/9/1998 | 10/9/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/9/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7453 issued 10-9-98 to the Idaho Medical Assn. (addn.)
|
INSP - Final | 7/17/1998 | 7/17/1998 | 7/17/1998 | P | PASS |
Wes Worcester
|
|
|
07/17/98 342 - Scheduled by Hello!. Contact phone is [3714620].
|
INSP - Final | 7/16/1998 | 7/16/1998 | 7/16/1998 | P | PART |
Wes Worcester
|
|
|
07/16/98 342 - Scheduled by Hello!. Contact phone is [3714620].
|
INSP-Final Inspection | 7/15/1998 | 7/15/1998 | 7/15/1998 | P | PASS |
Rick Jackson
|
|
|
reschedule from 7/14 occ approved
|
INSP-Final Inspection | 7/14/1998 | 7/14/1998 | 7/14/1998 | P | NR |
Rick Jackson
|
|
|
galen ###-#### or ###-#### plans not on site. rescheduled for 7/15
|
Code Occupancy Approval | | | 7/14/1998 | | PASS |
|
|
|
Meets requirements of plans.
|
INSP - Framing/Rough-in | 6/11/1998 | 6/11/1998 | 6/11/1998 | P | PASS |
|
|
|
06/11/98 333 - FRAM-OK FRAMING
|
INSP - Framing/Rough-in | 6/4/1998 | 6/5/1998 | 6/5/1998 | A | PART |
Wes Worcester
|
|
|
06/04/98 342 - walls ok only!. Contact phone is [3714620].
|
INSP - Framing/Rough-in | 6/4/1998 | 6/5/1998 | 6/4/1998 | P | CANC |
Wes Worcester
|
|
|
Scheduled by Hello!. Contact phone is [3714620]. Cancelled by Hello! (Last update by [HLO]). Contact: [3714620].
|
90 day tracking............. | | 3/5/1998 | 6/3/1998 | | PEND |
|
|
|
|
INSP - Framing/Rough-in | 5/27/1998 | 5/28/1998 | 5/28/1998 | A | PART |
Wes Worcester
|
|
|
05/28/98 342 - shr nailing ok!. Contact phone is [3458944].
|
INSP - Foundation | 5/1/1998 | 5/4/1998 | 5/4/1998 | P | PASS |
Wes Worcester
|
|
|
Scheduled by Hello!. Contact phone is [3458944].
|
INSP - Foundation | 5/4/1998 | 5/4/1998 | 5/4/1998 | A | NR |
Wes Worcester
|
|
|
05/04/98 342 - Scheduled by Hello!. Contact phone is [3458944].
|
INSP - Foundation | 4/30/1998 | 4/30/1998 | 4/30/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - c/n removed
|
INSP - Foundation | 4/30/1998 | 4/30/1998 | 4/30/1998 | P | FAIL |
Wes Worcester
|
|
|
04/30/98 342 - GALEN/###-#### - FOOTING INSP. after 2:30 not ready, need
|
Telephone call | | | 4/28/1998 | | |
|
|
|
called mike simmons gave $ amount
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 4/28/1998 | | |
|
|
|
|
Print Occupancy Form | | | 4/28/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/28/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 4/24/1998 | | 4/28/1998 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 4/28/1998 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 3/6/1998 | | 4/22/1998 | | PASS |
|
|
|
CONTACTED MIKE TO TAKE PLANS OUT TO ACHD ACHD FEES DUE. ACHD FEES PAID 4/24/98 RECEIPT NUMBER 98-1369
|
Print Pending Permit.LaserJet4 | | | 4/15/1998 | | PASS |
|
|
|
Needs achd approval.
|
Routing Off Site - STRUCTURAL | 3/6/1998 | | 4/9/1998 | | PASS |
|
|
|
GAVE PLANS TO ARLAN TO EVALUATE FOR OUTSIDE ENGINEERING. WE ARE DOING ENG.
|
Plan assigned to (JML) | 3/10/1998 | | 4/9/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/3/1998 | | 4/9/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 4/9/1998 | | |
|
|
|
RECEIVED RESUBS. 2-SHEET A_6 REVISED AND 1 SET OF PLANS. FORWADED TO JOHN LEVIEN. DAR
|
Plan resubmittals received | | | 4/7/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTAL ON REVISED DRAWING IN RESPONSE TO PLAN REVIEW
|
Application received | | | 4/3/1998 | | |
|
|
|
|
Routing - PUBLIC WORKS | 4/2/1998 | | 4/2/1998 | | PASS |
|
|
|
|
Routing - FIRE | 3/23/1998 | | 3/31/1998 | | PASS |
|
|
|
PACKAGE #1
|
Telephone call | | | 3/25/1998 | | FAIL |
|
|
|
I received a key plan from Mike of ZGA showing the entire building with it's exiting and concluded that a rated corridor is required unless the occupant load is reduced which could be done by putting a private exit out of the existing conference room. This was communicated to Mike by phone
|
Routing - PLAN CHECK | 3/16/1998 | | 3/23/1998 | | FAIL |
|
|
|
SENT PLAN REVIEW FINDINGS TO MICHAEL OF ZGA ARCH. BY FZX AND MAIL. NEED RESPONSE FROM SAME. SENDING TO FIRE.
|
Routing - PLUMBING | 3/12/1998 | | 3/16/1998 | | PASS |
|
|
|
PACKAGE #1
|
Routing - PLANNING | 3/10/1998 | | 3/12/1998 | | PASS |
|
|
|
PACKAGE #1 P&Z approved per DRH98-0034
|
Plan assigned to (JCM) | 3/6/1998 | | 3/10/1998 | | PASS |
John Menard
|
|
|
|
Received Certificate of Value | | | 3/10/1998 | | PASS |
|
|
|
REQUIRES PLUMB. ELECT. AND MECH. VALUES CONTACTED MIKE SIMMONDS OF THIS NEED. 3-10-98 RECEIVED REVISED CERT. OF VALUE WITH PLUMB. ELEC. AND MECH. VALUES CALLED OUT.
|
Routing - PUBLIC WORKS | 3/6/1998 | | 3/9/1998 | | FAIL |
|
|
|
PACKAGE #1 BRIAN MURPHY STATED THAT GRADING AND DRAINAGE PLANS ARE NOT REQUIRED. REQUIRES STREET LIGHT PLAN PER BILL COLSON. 3/9/98
|
Plan routing begun/NEW & ADDTN | | | 3/6/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/6/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 3/5/1998 | | PEND |
|
|
|
|
Application received | | | 3/4/1998 | | |
|
|
|
|
Plan assigned to (MYS) | 3/5/1998 | | 3/6/1997 | | |
Marlene Southard
|
|
|
|