Code Occupancy Approval | | | 4/13/1999 | | PASS |
|
|
|
Temporary Occupancy requested by Rick ###-#### pager PAINTING OF TRIM AND SOME PARKING SPACES NOT MARKED, BID SENT IN FOR $588, THIS IS OK SO WITH THE REQUIRED 10 0/0 TOTAL BONDING AMOUNT IS $646.00. WILL SIGN TEMP WHEN BOND POSTED, GAVE INSTRUCTIONS TO RICK ON SITE. BOND POSTED WITH CATHY 2-5-99, TEMP OCCUPANCY SIGNED OFF. FINAL INSPECTION MADE 4-13-99, TRIM PAINTED AND PARKING MARKED, FINAL OCCUPANCY SIGNED OFF AND RELEASE OF BOND.
|
Permanent occupancy | | | 2/18/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7639 issued 2-18-99 to the Church of Jesus Christ of Latter Day Saints (addn.)
|
INSP - Final | 2/12/1999 | 2/12/1999 | 2/12/1999 | | PASS |
Jim Storey
|
|
|
02/12/99 301 - FNL -OK FINAL
|
Permanent Occupancy | | 2/12/1999 | 2/12/1999 | | DONE |
|
|
|
|
INSP - Final | 2/8/1999 | 2/8/1999 | 2/9/1999 | P | PART |
Jim Storey
|
|
|
02/08/99 301 - temp occ ok
|
INSP-Final Inspection | 2/5/1999 | 2/5/1999 | 2/5/1999 | P | PASS |
Rick Jackson
|
|
|
RICK ###-#### occ approved
|
CHANGE STATUS TO (F) | | | 1/28/1999 | | |
|
|
|
|
CHANGE STATUS TO (I) | | | 1/28/1999 | | FEES |
|
|
|
SEE BLD98-1691 OVERPAYMENT THERE WOULD HAVE BEEN FEES DUE ON THIS PERMIT LH
|
(F) Reprint permit | | | 1/28/1999 | | |
|
|
|
|
Fee Review-notes | 10/13/1998 | | 1/28/1999 | | |
|
|
|
|
Fee Review-notes | 8/6/1998 | | 1/28/1999 | | |
|
|
|
ADDTIONAL VALUE FROM SUBS
|
INSP-Conference | 1/6/1999 | 1/6/1999 | 1/6/1999 | P | PART |
Rick Jackson
|
|
|
verified damper operation with electrician; reviewed plans for final
|
INSP - Framing/Rough-in | 11/25/1998 | 11/27/1998 | 11/27/1998 | A | FAIL |
Jim Storey
|
|
|
11/27/98 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
|
INSP - Framing/Rough-in | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PASS |
Jim Storey
|
|
|
10/27/98 301 - rick ###-#### or ###-#### roof sheeting insp RF -OK ROOF NAILING
|
INSP - Framing/Rough-in | 10/23/1998 | 10/23/1998 | 10/23/1998 | P | NR |
Jim Storey
|
|
|
10/23/98 301 - rick ###-#### nailing on sheeting
|
Inspection Record Card- Bld | | | 9/17/1998 | | |
|
|
|
|
INSP - Concrete | 8/28/1998 | 8/28/1998 | 8/28/1998 | | PART |
Jim Storey
|
|
|
08/28/98 301 - stem wall/###-#### pouring 2:00 special inspector COVERED BY SPECIAL INSP PENDING REPORT.
|
INSP - Foundation | 8/25/1998 | 8/26/1998 | 8/26/1998 | A | PASS |
Jim Storey
|
|
|
08/26/98 301 - RICK ###-#### FOOTING INSPECTION MID MORNING IF POSSIBLE. LUNCH TIME NOT EARLY MORNING. FTG -OK FOOTING rebar ok pending special insp.
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | | PART |
Jim Storey
|
|
|
08/07/98 301 - placed w/special insp. pending report.
|
INSP - Framing/Rough-in | 8/6/1998 | 8/7/1998 | 8/6/1998 | A | PART |
Jim Storey
|
|
|
foundation placed w/special insp. pending report.
|
INSP - Foundation | 8/4/1998 | 8/4/1998 | 8/4/1998 | P | PASS |
Jim Storey
|
|
|
08/04/98 301 - RICK ###-#### ###-#### FRMS-OK FORMS
|
Print Occupancy Form | | | 8/4/1998 | | |
|
|
|
|
90 day tracking............. | | 3/11/1998 | 6/9/1998 | | PEND |
|
|
|
|
Telephone call | | | 5/27/1998 | | |
|
|
|
SECRETARY SAID SHE WILL GIVE MESSAGE TO CLYDE WIPPER AND HAVE HIM CALL ME BACK..GARTH IS NO LONGER THERE
|
Issue PAID IN FULL permit | | | 5/27/1998 | | |
|
|
|
|
Telephone call | | | 5/22/1998 | | MESS |
|
|
|
LEFT MESSAGE THAT PLANS ARE READY WITH MR. WARD HE WILL CALL RON THURBER AND LET HIM KNOW
|
Telephone call | | | 5/1/1998 | | MESS |
|
|
|
LEFT MESSAGE THAT PLANS ARE READY
|
Plan resubmittals received | | | 4/14/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS 4/13/98 FROM RON THURBER.
|
Print Occupancy Form | | | 4/14/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 4/14/1998 | | |
|
|
|
|
Telephone call | | | 4/14/1998 | | |
|
|
|
CALLED RON THURBER AND GAVE HIM $ AMOUNT
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/14/1998 | | PASS |
|
|
|
|
Plan assigned to (ADS) | 3/18/1998 | | 4/14/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 4/2/1998 | | 4/14/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 4/2/1998 | | 4/2/1998 | | PASS |
|
|
|
|
Routing - FIRE | 3/26/1998 | | 4/2/1998 | | PASS |
|
|
|
PACKAGE 31
|
Routing - PLAN CHECK | 3/25/1998 | | 3/26/1998 | | FAIL |
|
|
|
see action A012 this date.
|
Plan resubmittals requested | | | 3/26/1998 | | FAIL |
|
|
|
Faxed copy of initial plan review report to Bill Waite, architect.
|
Routing - PUBLIC WORKS | 3/24/1998 | | 3/25/1998 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN PER BRIAN MURPHY. 3//25/98.
|
Routing - PLUMBING | 3/20/1998 | | 3/24/1998 | | PASS |
|
|
|
PACKAGE #1
|
Routing Off Site - A.C.H.D | 3/17/1998 | | 3/24/1998 | | PASS |
|
|
|
PACKAGE #2 CONTACTED BILL WAITE TO TAKE PLANS OUT TO ACHD ACHD FEES PAID 3/23/98 RECEIPT #98-1102
|
Routing - PLANNING | 3/18/1998 | | 3/20/1998 | | PASS |
|
|
|
PACKAGE #1 Approved per AA-81-97 - Modificaction of CU-84-91
|
Plan assigned to (JCM) | 3/17/1998 | | 3/18/1998 | | PASS |
John Menard
|
|
|
|
Routing - PUBLIC WORKS | 3/17/1998 | | 3/18/1998 | | FAIL |
|
|
|
PACKAGE #1 MAY REQUIRE DRAINAGE PLAN PER BM 3/18/98
|
Plan routing begun/NEW & ADDTN | | | 3/17/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 3/17/1998 | | 3/17/1998 | | |
|
|
|
JOHN STATED WE WILL DO ENGINEERING.
|
Plan assigned to (MYS) | 3/11/1998 | | 3/17/1998 | | |
Marlene Southard
|
|
|
|
Routing - PLAN CHECK | 3/11/1998 | | 3/17/1998 | | |
|
|
|
|
Received Certificate of Value | | | 3/17/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 3/16/1998 | | PASS |
|
|
|
RECEIVED PACKAGE 1. TWO FULL COPIES OF PLANS PLUS THREE EXTRA COPIES OF CIVIL SHEETS FOR PW 2. TWO COPIES OF ACHD 3. ONE COPY OF PACKAGE #3. JOHN STATED WE WILL DO ENG. FOR BOTH NO SPEC. BOOKS
|
Plans ACCEPTED BY PLAN CHECK | | | 3/12/1998 | | HOLD |
|
|
|
CONTACTED BILL WAITE AT ###-#### TO REQUEST HE SUBMIT EACH BUILDING SEPARATELY USING THE NEW AND ADDITION PACKAGE SET. I WILL WAIT UNTIL I RECEIVE SEPARATE PLANS BEFOREWORKING UP PERMITS.
|
Recd Pcfee & Taken To Pln CK | | | 3/11/1998 | | PEND |
|
|
|
|
Application received | | | 3/11/1998 | | |
|
|
|
|