Permit NumberBLD98-00675
StatusFinaled
Name GARTH JENSEN
Site Address 2150 W BOISE AVE
Project NameLDS OFFICE ANNEX
Customer Number 
ePlanReviewNo
Description
CHURCH OF JESUS CHRIST OF LATTER DAY SAINTS * TO CONSTRUCT A NEW 1,268 SQ. FT. DETACHED OFFICE ANNEX. ALL PER APPROVED PLANS. CU#84-91 MODIFICATION AA-81-97 PC#154-98
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent occupancy  2/18/1999 PASS
Perm. Occ. Cert. #7640 issued 2-18-99 to Church of Jesus Christ of Latter Day Saints.
INSP - Final2/12/19992/12/19992/12/1999 PASS
DetailsJim Storey
02/12/99 301 - FNL -OK FINAL
Permanent Occupancy 2/12/19992/12/1999 DONE
Details
Fee Review-notes10/13/1998 1/28/1999
INSP - Final1/7/19991/7/19991/7/1999PPART
DetailsJim Storey
01/07/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok for tenp oc
PubWorks Occupancy Approval  1/7/1999 DONE
Drainage project complete 01/07/99. R.Cummings
INSP-Final Inspection1/6/19991/6/19991/6/1999PPASS
DetailsRick Jackson
rick- beeper ###-#### fn fire insp annex approved for occupancy
Code Occupancy Approval  1/6/1999 PASS
BUILDING ALL DONE INCLUDING LANDSCAPE, SOME PARKING NEEDS STRIPED BUT THIS WORK WILL BE PART OF BLD98-0619 THAT IS NOT COMPLETED.
INSP - Framing/Rough-in10/16/199810/16/199810/16/1998 PASS
DetailsJim Storey
/ / 301 - FRAM-OK FRAMING
INSP - Framing/Rough-in10/16/199810/16/199810/16/1998 PASS
DetailsJim Storey
/ / 301 - FRAM-OK FRAMING
INSP - Framing/Rough-in10/16/199810/16/199810/16/1998 PASS
DetailsJim Storey
/ / 301 - FRAM-OK FRAMING
INSP - Framing/Rough-in10/15/199810/15/199810/15/1998PPART
DetailsJim Storey
10/15/98 301 - dave ###-#### pager CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in9/16/19989/16/19989/17/1998PPART
DetailsJim Storey
09/17/98 301 - rick ###-#### nailing inspection on roof sheeting RF -OK ROOF NAILING
Inspection Record Card- Bld  9/17/1998
INSP - Framing/Rough-in8/7/19988/7/19988/7/1998 PART
DetailsJim Storey
08/07/98 301 - foundation wall ###-#### peepper ready 11:00 placed w/special insp. pending report.
INSP - Framing/Rough-in8/6/19988/7/19988/6/1998APART
DetailsJim Storey
foundation wall ###-#### peepper ready 11:00 placed w/special insp. pending report.
INSP - Foundation8/4/19988/4/19988/4/1998PPART
DetailsJim Storey
08/04/98 301 - ###-#### RICK ###-#### PAGER FRMS-OK FORMS
Print Occupancy Form  8/4/1998
90 day tracking............. 3/17/19986/15/1998
(F) Reprint permit  5/28/1998
Issue PAID IN FULL permit  5/27/1998
Telephone call  4/15/1998
called secretary gave $ amount
Inspection Record Card- Bld  4/15/1998
Print Occupancy Form  4/15/1998
PLANS/APPL TAKEN TO FRONT DESK  4/15/1998 PASS
Routing - PLAN CHECK4/9/1998 4/15/1998 PASS
Plan assigned to (ADS)3/18/1998 4/15/1998 PASS
Details
Plan resubmittals received  4/13/1998
Routing - FIRE4/2/1998 4/9/1998 PASS
PACKAGE #1--OK
Routing - PUBLIC WORKS3/27/1998 4/1/1998 PASS
Routing - PLUMBING3/27/1998 3/27/1998 PASS
PACKAGE #1
Routing - PLANNING3/23/1998 3/26/1998 PASS
PACKAGE #1 AA-81-97; passed per approved plans
Routing Off Site - A.C.H.D3/24/1998 3/24/1998 PASS
PACKAGE #2 CONTACTED BILL WAITE TO TAKE PLANS OUT TO ACHD. ACHD FEES PAID RECEIPT #98-1102 DAR
Routing - PUBLIC WORKS3/17/1998 3/20/1998 FAIL
PACKAGE #1 REQUIRES DRAINAGE PLAN PER BRIAN M.
Plan assigned to (JCM)3/17/1998 3/18/1998 PASS
DetailsJohn Menard
Plan routing begun/NEW & ADDTN  3/17/1998 PASS
Routing Off Site - STRUCTURAL3/17/1998 3/17/1998
WE WILL BE DOING ENG. PER JOHN M.
Received Certificate of Value  3/16/1998 PASS
PLAN CHECK FEE PAID UNDER PERMIT #BLD98-0619
Plans ACCEPTED BY PLAN CHECK  3/16/1998 PASS
RECEIVED ONE SET OF PACKAGE #1 NO PROJECT MANUAL ONE SET OF PACKAGE #2 (ACHD) ONE COPY OF PACKAGE #3 - WE WILL BE DOING ENG. PER JOHN M.
Application received  3/16/1998
Routing - PLAN CHECK4/1/1998