Permit Information
Permit NumberBLD98-00758
StatusFinaled
Name STAN MOCK
Site Address 3660 N HARBOR LN
Project NameFINANCIAL PLANNING
Customer Number 
ePlanReviewNo
Description
FINANCIAL PLANNING SERVICES * TO CONSTRUCT A ONE STORY 4,704 SQ. FT. OFFICE BUILDING AND INTERIORS. THE BUILDING IS WOOD FRAMED AND NON-SPRINKLED. THE WEST WALL IS BEING BUILT TO 1-HOUR REQUIREMENTS FOR EXTERIOR WALL CONSTRUCTION WITH THE ANTICIPATION OF A NEW LOT LINE BEING ESTABLISHED IN THE FUTURE BETWEEN 10-20' FROM THE WEST WALL. (PARKING LOT IS NOT A PART OF THIS PROJECT). DRH98-0041 PC#177-98 JML
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  2/18/2004  
Fee Review-notes7/23/1998 12/15/1998
Permanent Occupancy 10/2/199810/2/1998 DONE
Details
Permanent occupancy  10/2/1998 PASS
Perm. Occ. Cert. #7442 issued 10-2-98 to Financial Planning Services.
Temporary occupancy  10/1/1998 PASS
Temp. Occ. Cert. #3709 issued 10-1-98 to Financial Planning Services.
INSP-Final Inspection9/30/19989/30/19989/30/1998PPASS
DetailsRick Jackson
fire lanes completed - occ approved
INSP - Final9/28/19989/28/19989/28/1998PNR
DetailsWes Worcester
09/28/98 342 - JOE ###-#### tried 2 times and was busy
INSP - Final8/31/19988/31/19988/31/1998PFAIL
DetailsCarl Dependahl
joe 870-*7356...need pub wks ok & plan onsite
INSP - Final8/28/19988/28/19988/28/1998PNR
DetailsCarl Dependahl
2:00 if possible...STILL NEED OTHER SIG'S, TEMP ON FIRE.
INSP - Final8/28/19988/28/19988/28/1998ANR
DetailsCarl Dependahl
CONF ONLY W/ SUPT. RE FINAL REQ'S
INSP - Final8/27/19988/28/19988/28/1998ACANC
DetailsWes Worcester
08/28/98 342 - joe ###-####
INSP-Final Inspection8/27/19988/28/19988/28/1998APART
DetailsRick Jackson
joe ###-#### temp occ approved. awaiting parking lot and fire lane
INSP - Framing/Rough-in8/26/19988/26/19988/26/1998PPASS
DetailsCarl Dependahl
rec'd surveyor's letter...west wall ok. Clg grid & partition bracing in ok
INSP - Final8/26/19988/26/19988/26/1998PFAIL
DetailsCarl Dependahl
late pm joe ###-####...need all other ok's
INSP - Framing/Rough-in8/24/19988/24/19988/24/1998ANR
DetailsCarl Dependahl
conf only w/ Joe, supt...need surveyors letter or string line for measurements of p.l. at west.
INSP - Framing/Rough-in8/20/19988/20/19988/20/1998PFAIL
DetailsCarl Dependahl
conf w/ Marlene re set backs; rec'd new plat. c/n previously asked for surveyor's statement. keep c/n.( note: walls framed & approved to cover, need min. 10' to west wall.
INSP - Framing/Rough-in8/13/19988/17/19988/17/1998APART
DetailsCarl Dependahl
JOE ###-#### FRAM AND WALLCOVER...int partitions ok...need bracing per plan at grid.
INSP - Framing/Rough-in8/7/19988/7/19988/7/1998PNR
DetailsCarl Dependahl
keep c/n...still need survey, etc.
INSP - Framing/Rough-in7/27/19987/27/19987/27/1998PFAIL
DetailsCarl Dependahl
C/N. NEED VERIFY TRUSS BRACING FIX, COMPLETE FIREBLOCKING AT WALL PENETRATIONS ABOVE CLG. STILL NEED SURVEY REPORT.
INSP - Energy code compliance7/27/19987/27/19987/27/1998PFAIL
DetailsCarl Dependahl
INSULATION JOE ###-####
INSP - Conference7/24/19987/24/19987/24/1998 PASS
DetailsCarl Dependahl
/ / 340 - conf w/ Tamura re prop line & survey report...need report fo
INSP - Framing/Rough-in7/6/19987/6/19987/6/1998PFAIL
DetailsCarl Dependahl
r/i ###-#### joe c/n, need truss bracing at webs per eng'g, nail-off hangers, bolt saddles. survey & detail for 1hr. wall pending per previous c/n. ok to continue.
INSP - Framing/Rough-in6/30/19986/30/19986/30/1998PPART
DetailsCarl Dependahl
joe ###-#### ext walls only ok per elec
INSP - Framing/Rough-in6/29/19986/29/19986/29/1998PNR
DetailsCarl Dependahl
keep c/n, need fireblock ext wall prior to cover. still need survey report.
INSP - Framing/Rough-in6/26/19986/26/19986/26/1998PFAIL
DetailsCarl Dependahl
cover inspection joe ###-####...wants ext walls; need complete insulation, seal penetrations, need arch's detail for deletion of a-35's at truss blocks & proposed modification to 1hr (west) wall & survey report. ok to cover except as noted.
INSP - Framing/Rough-in6/23/19986/24/19986/24/1998APART
DetailsCarl Dependahl
06/24/98 340 - west wall nailing/joe ###-#### ok, need detail for possible modificatiion for gyp (1hr ) at attic/fasci also need survey report for prop. line
INSP - Framing/Rough-in6/22/19986/22/19986/22/1998PNR
DetailsCarl Dependahl
conference/ joe ###-#### not frame insp; bldr asked for partials...ok if passed other insps
90 day tracking............. 3/23/19986/21/1998 PEND
INSP - Foundation6/8/19986/8/19986/8/1998PPART
DetailsCarl Dependahl
conf only; pending survey, discussed west wall (1hr) w/ John Levien and Joe of Beniton Const.
INSP - Foundation6/5/19986/5/19986/5/1998PFAIL
DetailsCarl Dependahl
joe ###-#### sub panel before cover hte floor placed vents at (1hr.) west fdn wall...no one onsite, didn't leave c/n...need surveyor's letter; is > 10' from pl??unprotected opening?
INSP - Foundation6/1/19986/1/19986/1/1998PPART
DetailsCarl Dependahl
Joe Sanford ###-#### NEED SURVEYOR'S LETTER, WALLS LOOK OK. NEED HD-2A'S AT NW CORNER
INSP - Foundation5/28/19985/28/19985/28/1998PPART
DetailsCarl Dependahl
ready after 2 cel ###-#### joe footing...c/n, need suveyor's verification. part only, need south side perimeter, other pads, ftgs appear ok.
(F) Reprint permit  5/28/1998
Issue PAID IN FULL permit  5/27/1998
Plan assigned to (JML)3/24/1998 5/26/1998 PASS
Details
Routing - PLAN CHECK5/26/1998 5/26/1998 PASS
PW approval recieved 5/22/98
Inspection Record Card- Bld  5/26/1998
Print Occupancy Form  5/26/1998
Telephone call  5/26/1998
CALLED STAN PERMIT READY
Print Pending Permit.LaserJet4  5/26/1998 PASS
APPROVED WITH CONDITIONS
PLANS/APPL TAKEN TO FRONT DESK  5/26/1998 PASS
Plan resubmittals received  5/22/1998
recieved resubmittals and sent them to John Levien
Routing - PLAN CHECK5/18/1998 5/22/1998 PASS
still needs PW approval
Routing - PUBLIC WORKS5/22/1998 5/22/1998 PASS
Plan resubmittals received  5/19/1998 PEND
RECEIVED RESUBMITTALS FROM TAMURA AND ASSOCIATES. FORWARDED SAME TO JOHN L.
Routing - FIRE5/13/1998 5/15/1998 PASS
PACKAGE #1
Routing - PLAN CHECK5/6/1998 5/8/1998 FAIL
plan need corrected ( no findings were sent to the architect ) project on hold until the sub-division is approved. (Approval has been recieved from Marlene to proceed with the review as if it is not being sub-divided. Plans still need corrected. Findings sent to Arch by fax and mail and sent on for further review. jml 5-13-98)
Meeting  5/8/1998
Met with Doug Tamura to discuss phasing of parking lot. Parking lot is to be constructed per original plans, unless Doug provides phasing documentation and Staff approves the documentation. MGS
Plan resubmittals received  5/8/1998
RECEIVED RESUBMITTALS AND TAKEN TO JOHN L.
Plan Reviewer's activity  5/8/1998 FAIL
I did a plan review, but the property is actively being sub-divided and therefore no permit can be issued. Apon learning of the sub-division problem I notified John Price and Doug Tamari ( Arch.) that the plans would not proceed any further until the plan is approved. I also gave John a heads up on what were the significant issues that I found when doing the review.Doug requested approval of a permit based on the original lot. I told him that no permit can be issued while the plat is in process.
Routing - PLANNING4/27/1998 5/6/1998 PASS
PACKAGE #1, approved per DRH98-0041 and as noted on building permit plans, and conditions of this permit.
Routing - PLANNING4/29/1998 4/29/1998 PASS
CROSS REF. CUP98-0039 WHICH WAS A MODIFICATION OF CUP96-0019. THERE IS ALSO A DESIGN REVIEW APPLICAION WHICH IS DR-41-98
Routing - PLUMBING4/28/1998 4/28/1998 PASS
Plan resubmittals received  4/27/1998 PEND
RECEIVED PLUMBING RESUBMITTALS AND TAKEN TO BILL V.
Routing - PUBLIC WORKS3/24/1998 4/27/1998 FAIL
PACKAGE #1 REQUIRES DRAINAGE PLAN
Routing - PLUMBING4/24/1998 4/27/1998 FAIL
PACKAGE #1
Routing Off Site - A.C.H.D3/24/1998 3/25/1998 PASS
PACKAGE #2 CONTACTED JOHN PRICE AT ###-#### TO TAKE PLANS OUT TO ACHD. ACHD FEES PAID 5/8/98
Routing Off Site - STRUCTURAL3/24/1998 3/24/1998
PACKAGE #3 GAVE PLANS TO JOHN TO EVALUATE FOR OUTSIDE ENG. WE WILL BE DOING ENG. PER JOHN M. KMM
Plan routing begun/NEW & ADDTN  3/24/1998 PASS
Plan assigned to (JCM)3/24/1998 3/24/1998 PASS
DetailsJohn Menard
Received Certificate of Value  3/24/1998 PEND
SEE ACTION 007 PEND
Plans ACCEPTED BY PLAN CHECK  3/24/1998 PEND
PACKAGE #1 DID NOT HAVE REQUIRED SETS FOR GRADING AND DRAINAGE OR CALCS. HOWEVER BRIAN LOOKED AT PLANS AND HE WILL BE ASKING FOR REVISIONS. SO I WILL ROUTE TO HIM FIRST AND HE WILL ASK FOR 5 SETS OF NEW G & D PLANS. SPOKE WITH JOHN ABOUT THERE NOT BEING ANY PLUMB. AND MECH. PLANS. THEY ARE GOING OUT TO BID AND WILL RECEIVE THEM FROM THE BIDDER. I TOLD HIM THIS WILL PUT PLANS ON HOLD FOR ISSUING. PLUMB. AND PLAN REVIWER WILL NEED TO LOOK AT THEM BEFORE ISSUING. ALSO I WILL NEED A REVISED CERT. OF VALU. WITH PLUMB. AND MECH. ON IT. KMM
Plan assigned to (MYS)3/23/1998 3/24/1998
DetailsMarlene Southard
Application received  3/23/1998
Recd Pcfee & Taken To Pln CK  3/23/1998 PEND
Routing - PLAN CHECK3/23/1998 3/21/1948