Permit Information
Permit NumberBLD98-00777
StatusExpired
Name IDAHO ICE WORLD (FOUNDATION)
Site Address 7072 S EISENMAN RD
Project NameIDAHO ICE WORLD-FNDTN
Customer Number 
ePlanReviewNo
Description
IDAHO ICEWORLD FOUNDATION - TO CONSTRUCT A NEW 83,750 SQ. FT. CONCRETE FOUNDATION FOR SUPPORT OF THE FUTURE PROPOSED IDAHO ICEWORLD FACILITY BUILDING. THIS PERMIT ALSO INCLUDES RELATED UNDERGROUND UTILITIES. THIS IS THE PHASE TWO PERMIT OF A THREE PHASED BUILDING PERMIT PROCESS. NO CONSTRUCTION BEYOND THE FOUNDATION IS ALLOWED UNDER THIS PERMIT. ALL PER THE APPROVED ENGINEERED PLANS ON FILE. THE OWNER AND/OR THE OWNER'S AGENT UNDERSTANDS THAT THIS FOUNDATION PERMIT IS BEING ISSUED WITHOUT ASSURANCE THAT THE PHASE THREE (BUILDING) PERMIT MAY NOT BE APPROVED; IT IS ALSO UNDERSTOOD THAT IF ANY FOUNDATION MODIFICATIONS ARE REQUIRED BY THE PHASE THREE PLAN SUBMITTALS, THOSE FOUNDATION FIELD MODIFICATIONS MUST BE COMPLIED WITH. CUP98-0035/DRH98-0050/PC#180-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Expired1/12/20011/12/20011/12/2001APASS
DetailsJim Storey
Added by Inspector: 301 On 1/12/2001 9:27:17 AM
Receive PAYMENT IN FULL  8/3/1999
Fee Review-notes9/9/1998 5/5/1999
per gc
(F) Reprint permit  5/3/1999
INSP - Framing/Rough-in12/17/199812/17/199812/17/1998PPART
DetailsRuss Owen
12/17/98 407 - told them it would not require an inspection to pour this
INSP - Framing/Rough-in11/3/199811/3/199811/3/1998PPART
DetailsRuss Owen
refered architect to plan review as the side walls of the hocky bench area walls have fire retardant wood and a plastic board for finish this does not meet type II construction. One in each rink.
INSP - Framing/Rough-in11/2/199811/2/199811/2/1998PPART
DetailsRuss Owen
noted to contractor man door at zamboni room does not have correct rating.
INSP-Conference10/26/199810/26/199810/26/1998APART
DetailsRuss Owen
profit meeting.
INSP - Framing/Rough-in10/15/199810/15/199810/15/1998 PART
DetailsRuss Owen
/ / 407 - taled with contractor about fire assembly windows.
INSP - Framing/Rough-in10/12/199810/12/199810/12/1998 PART
DetailsRuss Owen
/ / 407 - ceiling in lockers.
INSP - Framing/Rough-in10/7/199810/7/199810/7/1998 PART
DetailsRuss Owen
/ / 407 - walk thru contractor has not installed wall joint fire stopi notified to correct at cmu walls.
INSP - Framing/Rough-in9/29/19989/29/19989/29/1998 PART
DetailsRuss Owen
/ / 407 - walk thru with builder progress check.
INSP - Framing/Rough-in9/25/19989/25/19989/25/1998 PART
DetailsRuss Owen
/ / 407 - Talked with contractor about fire stoping ceiling assemblies protection.
INSP - Framing/Rough-in9/23/19989/23/19989/23/1998 PART
DetailsRuss Owen
/ / 407 - Talked with builder about the need for verification of fire wood.said he would verify.
INSP - Framing/Rough-in9/17/19989/17/19989/17/1998 PART
DetailsRuss Owen
/ / 407 - meet with architect about ceiling changed details for upper construction.
INSP - Framing/Rough-in9/10/19989/10/19989/10/1998 PASS
DetailsRuss Owen
/ / 407 - talked with builder and architect about upper ceiling
INSP - Framing/Rough-in9/9/19989/9/19989/9/1998PPART
DetailsRuss Owen
09/09/98 407 - meet with architect about corrections ,fire assembly for
INSP - Framing/Rough-in9/2/19989/2/19989/2/1998AFAIL
DetailsRuss Owen
inspections of ceilings and fire walls partial inspections have corrections for the continuity of the 3 hr fire wall,also upper 1 hour lid,and they have not started the 3 required shafts,left correction notice on site.
90 day tracking............. 3/24/19986/22/1998 PEND
INSP - Foundation5/19/19985/19/19985/19/1998PPART
DetailsJim Storey
05/19/98 301 - PLACED W/SPECIAL INSP. PENDING REPORT.
INSP - Framing/Rough-in5/4/19985/4/19985/4/1998PPART
DetailsRuss Owen
need refirgeration lines inspected by the designer told yhis to contractor.NG AT 1:30.
INSP - Foundation4/30/19984/30/19985/1/1998PPART
DetailsRuss Owen
04/30/98 407 - unable to make inspection today.special inspector / phil
INSP - Foundation4/28/19984/29/19984/30/1998APART
DetailsRuss Owen
04/29/98 407 - no one at the job site,went out late pm,unable to make it meetings.(###-####--footing special inspection on job
INSP - Foundation4/21/19984/21/19984/21/1998PPART
DetailsRuss Owen
04/21/98 407 - this wall has been poured but contractor said special ins
INSP - Foundation4/15/19984/16/19984/16/1998APART
DetailsRuss Owen
04/16/98 407 - ok, site visit,also special inspector on site.
Issue PAID IN FULL permit  4/15/1998
Telephone call  4/14/1998
LEFT MESSAGE ON VOICE MAIL FOR GARY HIMES
Inspection Record Card- Bld  4/14/1998
PLANS/APPL TAKEN TO FRONT DESK  4/14/1998 PASS
Print Occupancy Form  4/14/1998
Plan assigned to (JCM)3/25/1998 4/14/1998 PASS
DetailsJohn Menard
Routing - PLAN CHECK4/10/1998 4/14/1998 PASS
PACKAGE #2
Routing Off Site - STRUCTURAL4/7/1998 4/13/1998 PASS
SENT RESUBS TO CH2MHILL
Routing - FIRE4/10/1998 4/10/1998 PASS
Routing - PUBLIC WORKS4/9/1998 4/10/1998 PASS
Plan resubmittals received  4/8/1998 PEND
RECEIVED RESUBMITTALS AND GIVEN TO JOHN M.
Plan resubmittals received  4/7/1998 PEND
RECEIVED RESUBMITTAL FOR RE-PLOTS OF S2.3, S2.4,S2.5,S3.1
Plan Reviewer's activity  4/6/1998 PEND
FAXED CHERYL PEARSE AT HUMMEL'S OFFICE A COPY OF THE STRUCTURAL ENGINEER'S REVIEW LIST REQUESTING WRITTEN RESPONSES. FOLLOWED UP WITH A CALL TO CHERYL TO VERIFY THAT SHE DID RECEIVE THE FAXED INFORMATION.
Routing Off Site - STRUCTURAL3/25/1998 4/6/1998 FAIL
PACKAGE #2 SENT TO CH2MHILL VIA PDQ WRITTEN RESPONSE REQUIRED
Routing - PLANNING4/2/1998 4/2/1998 PASS
X-REF. DRH98-0050
Routing - PLANNING3/31/1998 4/2/1998 PASS
APPROVED AND SENT ON TO TEMPRA WILSON FOR DESIGN REVIEW. THERE ARE TWO APPPLICATION NUMBERS FOR THIS PROJECT. CUP97-100 WAS THE ORIGINAL APPROVAL AND CUP98-035 WAS THE MODIFICATION. CONDITIONS OF APPROVAL ARE ATTACHED TO PLANS FOR BOTH CUP'S.
Routing - PLUMBING4/2/1998 4/2/1998 PASS
PACKAGE #1
Plans ACCEPTED BY PLAN CHECK  3/25/1998 PASS
Received Certificate of Value  3/25/1998 PASS
Routing - PLAN CHECK3/24/1998 3/25/1998
Plan assigned to (MYS)3/24/1998 3/25/1998
DetailsMarlene Southard
Routing - PUBLIC WORKS3/25/1998 3/25/1998 FAIL
PACKAGE #1 REQUIRES DRAINAGE PLAN, TIED TO SITE PLAN APPROVAL BM
Plan routing begun/NEW & ADDTN  3/25/1998 PASS
Application received  3/24/1998
Recd Pcfee & Taken To Pln CK  3/24/1998 PEND