Fee Review-notes | 6/20/2003 | 6/20/2003 | 6/20/2003 | | DONE |
|
|
|
|
Permanent occupancy | | | 2/16/2001 | | DONE |
|
|
|
Perm. Occ. Cert. #8572 issued 2-16-01 to Preco.
|
Code Occupancy Approval | | | 2/15/2001 | | PASS |
|
|
|
THE ZONING CERTIFICATE WAS VOID BUT NEW PERMIT TAKEN OUT UNDER DRH99-00220 AND BLD00-01504, NOW ALL CONDITIONS ARE MET, FINAL SIGNED OFF.
|
Permanent Occupancy | | 2/14/2001 | 2/14/2001 | | DONE |
|
|
|
|
BLD-Final | 2/13/2001 | 2/14/2001 | 2/14/2001 | A | PART |
Russ Owen
|
|
|
Bill Morris, ###-####ok for perm oc pending p&z approval. 2/14/2001 1:27:45 PM
|
Code Occupancy Approval | | | 8/18/1999 | | |
|
|
|
Final Occupancy requested by Bill Morris ###-#### Bill explained that this is a cleanup inspection as Code Enforcement has not signed off on the Occupancy Card.
|
INSP - Final | 8/17/1999 | 8/17/1999 | 8/17/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/17/99 340 - BILL ###-####; c/n, p&z, stairs, tie-downs, etc. recall
|
INSP-Final Inspection | 8/12/1999 | 8/16/1999 | 8/16/1999 | A | PART |
Joe Tawney
|
|
|
08/16/99 406 - REINSP OK FOR CERT OF COMPLETION/PERM OCC
|
INSP - Final | 8/12/1999 | 8/13/1999 | 8/13/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/13/99 340 - fire will be going out am today bill ###-####; FAILED FIR
|
INSP - Final | 9/2/1998 | 9/2/1998 | 9/2/1998 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - FINAL FAIL FIRE EXT SPKLR OBSTR EXIT SIGNS HYD CALCS
|
90 day tracking............. | | 4/10/1998 | 7/9/1998 | | PEND |
|
|
|
|
(F) Reprint permit | | | 5/13/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 5/6/1998 | | |
|
|
|
|
Telephone call | | | 5/6/1998 | | PASS |
|
|
|
talked to mike capshaw to verify that plans are ready
|
Plan assigned to (M_P) | 4/16/1998 | | 5/5/1998 | | PASS |
Mike Phillips
|
|
|
05/05/98 10:24:41 DAR - this action updated by action script from <<>> in Case No. BLD98-0974
|
Print Occupancy Form | | | 5/5/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/5/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/5/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/4/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/4/1998 | | PASS |
|
|
|
|
Routing - FIRE | 4/22/1998 | | 4/23/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 4/22/1998 | | PEND |
|
|
|
WAITING FOR ACHD AND FIRE DEPARTMENT APPROVALS.
|
Plan Reviewer's activity | | | 4/22/1998 | | PEND |
|
|
|
WAITING FOR FIRE, ACHD APPROVALS.
|
Routing - PLANNING | 4/20/1998 | | 4/20/1998 | | PASS |
|
|
|
X-Ref. CZC98-0017
|
Routing - PUBLIC WORKS | 4/17/1998 | | 4/20/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 4/10/1998 | | 4/16/1998 | | |
Marlene Southard
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 4/16/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE. ACHD APPROVAL TO BE OBTAINED BY OWNER/APPLICANT PRIOR TO PERMIT ISSUANCE.
|
Routing Off Site - A.C.H.D | 4/16/1998 | | 4/16/1998 | | PASS |
|
|
|
THIS NEEDS ACHD APPROVAL FOR POSSIBLE IMPACT FEES. OWNER/APPLICANT MUST SOLICIT NECESSARY APPROVAL. fee receipt #98-1424
|
Recd Pcfee & Taken To Pln CK | | | 4/10/1998 | | PEND |
|
|
|
|
Application received | | | 4/10/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 4/23/1998 | | | | |
|
|
|
|