PAST DUE BALANCE | | 10/23/1998 | 11/24/1998 | | |
|
|
|
jay jackson and assoc. has past due permit
|
INSP - Final | 10/5/1998 | 10/6/1998 | 10/6/1998 | A | PASS |
Jim Storey
|
|
|
10/06/98 301 - Final - Gary or Wert, ###-#### - this is the one we talke FNL -OK FINAL be unlocked for you!
|
INSP - Final | 9/30/1998 | 10/1/1998 | 10/1/1998 | A | PASS |
Jim Storey
|
|
|
10/01/98 301 - GARY ###-#### insp performed on 9/28/98 and passed job stil look the same as before. ì
|
INSP - Wall cover | 8/21/1998 | 8/24/1998 | 8/24/1998 | A | PASS |
Russ Owen
|
|
|
sheetrock at the firewall.
|
INSP - Framing/Rough-in | 8/10/1998 | 8/10/1998 | 8/11/1998 | P | PASS |
Russ Owen
|
|
|
08/10/98 407 - gary ###-#### ì
|
INSP - Framing/Rough-in | 8/7/1998 | 8/7/1998 | 8/7/1998 | | PART |
Jim Storey
|
|
|
08/07/98 301 - ###-#### or gary at ###-#### to meet for the insp russ o did insp.
|
INSP - Framing/Rough-in | 8/6/1998 | 8/7/1998 | 8/6/1998 | A | FAIL |
Jim Storey
|
|
|
###-#### or gary at ###-#### to meet for the insp russ o. performed insp.
|
INSP - Framing/Rough-in | 8/3/1998 | 8/3/1998 | 8/3/1998 | P | FAIL |
Jim Storey
|
|
|
08/03/98 301 - gary ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED do not cover 16 idems on 2 c/ be on site for reinsp.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/3/1998 | | |
|
|
|
CHANGE PER DAVE
|
CHANGE STATUS TO (I) | | | 8/3/1998 | | |
|
|
|
CHANGE PER DAVE
|
INSP - Framing/Rough-in | 7/28/1998 | 7/29/1998 | 7/29/1998 | A | FAIL |
Jim Storey
|
|
|
07/29/98 301 - gary ###-#### reinspection trans to russ o. already performed insp. notice posted.
|
INSP - Framing/Rough-in | 7/27/1998 | 7/27/1998 | 7/27/1998 | A | FAIL |
Russ Owen
|
|
|
left corrections.
|
INSP-Conference | 6/30/1998 | 6/30/1998 | 7/1/1998 | P | CANC |
Russ Owen
|
|
|
06/30/98 407 - conf/ rob ###-####
|
INSP - Framing/Rough-in | 6/18/1998 | 6/19/1998 | 6/19/1998 | A | PASS |
Russ Owen
|
|
|
06/19/98 407 - ###-#### nailing
|
INSP - Foundation | 5/18/1998 | 5/19/1998 | 5/19/1998 | A | CANC |
Russ Owen
|
|
|
FOOTING/ I went out on 05/18/98 they called me on cell phone the foundation had to be moved back 2 foot to meet set backs.
|
INSP - Foundation | 5/18/1998 | 5/18/1998 | 5/18/1998 | P | PASS |
Russ Owen
|
|
|
I was called out by cell phone to inspect,went out footings are now with in the set backs.
|
INSP - Foundation | 5/15/1998 | 5/15/1998 | 5/15/1998 | P | FAIL |
Russ Owen
|
|
|
05/15/98 407 - need to maintain set back of 20 foot at the front.
|
Plan assigned to (M_P) | 4/23/1998 | | 5/13/1998 | | PASS |
Mike Phillips
|
|
|
|
Issue PAID IN FULL permit | | | 5/13/1998 | | |
|
|
|
|
Telephone call | | | 5/7/1998 | | PASS |
|
|
|
TALKED TO GARY AMES TO VERIFY THAT PLANS ARE READY
|
Inspection Record Card- Bld | | | 5/6/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 5/5/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 5/5/1998 | | PASS |
|
|
|
|
CHANGE STATUS TO (R) | | | 5/5/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/5/1998 | | 5/5/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 4/24/1998 | | 5/4/1998 | | PASS |
|
|
|
Approved per CU-4-95 & DR-70-95.
|
Plan Reviewer's activity | | | 5/1/1998 | | PEND |
|
|
|
WAITING FOR APPROVALS FROM OTHER DEOPARTMENTS
|
Routing - PUBLIC WORKS | 4/23/1998 | | 4/23/1998 | | PASS |
|
|
|
|
Application received | | | 4/23/1998 | | |
|
|
|
|
PLACE HOLD ON JOB | | 12/24/1998 | | | |
|
|
|