Case Summary (BLD) | | | 4/9/2015 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 12/23/1999 | | DONE |
|
|
|
|
Telephone call | | | 11/10/1999 | | DONE |
|
|
|
sundance office called and they are sending payment lh
|
(F) Reprint permit | | | 9/16/1999 | | DONE |
|
|
|
|
Permanent Occupancy | | 9/3/1999 | 9/3/1999 | | DONE |
|
|
|
|
INSP - Final | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PASS |
Carl Dependahl
|
|
|
09/03/99 340 - terry- ###-#### fn occ insp
|
INSP - Final | 8/25/1999 | 8/26/1999 | 8/26/1999 | A | FAIL |
Carl Dependahl
|
|
|
08/26/99 340 - terry ###-####; c/n, spec insp & eng's letter; shaft, etc
|
INSP - Framing/Rough-in | 8/16/1999 | 8/16/1999 | 8/16/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/16/99 340 - conf w/ contractor; will review previous actions. rec'd a
|
Code Occupancy Approval | | | 8/12/1999 | | PASS |
|
|
|
Meets compliance with DR - PASS (CAM)
|
INSP - Final | 7/22/1999 | 7/22/1999 | 7/22/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR CERT OF COMPLETION
|
INSP-Final Inspection | 6/10/1999 | 6/14/1999 | 6/14/1999 | A | FAIL |
Joe Tawney
|
|
|
06/14/99 406 - REINSP FAIL NFPA 72 FORM
|
INSP-Final Inspection | 5/24/1999 | 5/25/1999 | 5/25/1999 | P | FAIL |
Joe Tawney
|
|
|
05/25/99 406 - REINSP FAIL ADDRESS, FIRE DOORS, EMERG LIGHTS, REFR PIPIN
|
INSP-Final Inspection | 5/7/1999 | 5/10/1999 | 5/10/1999 | P | CANC |
Joe Tawney
|
|
|
05/10/99 406 - CANCELLED TO BE RESCHED
|
INSP-Sprinkler Rough-in/Hydro | 2/3/1999 | 2/3/1999 | 2/3/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - rough in of ext canopy FAIL PROVIDE PROTECTION IN CONCEALED
|
INSP-Final Inspection | 12/4/1998 | 12/7/1998 | 12/7/1998 | A | PART |
Joe Tawney
|
|
|
12/07/98 406 - JOHN ###-#### SCHEDULED W/JOE AT 10:30 ALARM SYSTM TEST OK ON TEST
|
INSP-Final Inspection | 12/2/1998 | 12/3/1998 | 12/4/1998 | P | FAIL |
Joe Tawney
|
|
|
12/03/98 406 - Scheduled by Hello!. SPKLR ROUGH IN FAIL BAKERY FINAL FAIL SPKLR SYSTEM NOT YET TESTED SUPRV
|
INSP - Wall cover | 12/2/1998 | 12/3/1998 | 12/3/1998 | P | PART |
|
|
|
12/02/98 338 - madeok
|
INSP-Supply line flush | 11/10/1998 | 11/10/1998 | 11/10/1998 | | NR |
Joe Tawney
|
|
|
/ / 406 - SUPPLY LINE FLUSH NOT READY TO BE WITNESSED BY JOHN ANDERSON
|
INSP-Conference | 10/20/1998 | 10/20/1998 | 10/20/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF WITH JOHN ANDERSON & STAN BUESS ABOUT SHUTTING DOWM SPK
|
INSP - Framing/Rough-in | 10/8/1998 | 10/8/1998 | 10/8/1998 | P | PART |
|
|
|
10/08/98 338 - made ok to start cover at the front entry soffit
|
INSP-Conference | 9/9/1998 | 9/10/1998 | 9/10/1998 | A | PART |
Joe Tawney
|
|
|
09/10/98 406 - JOHN ANDERSON ###-####-JOHN WILL CALL CONF ON EXITING DURING CONSTR WITH JOHN ANDERSON. NEED ARCH TO CLARIFY P
|
INSP - Foundation | 8/31/1998 | 8/31/1998 | 8/31/1998 | P | PART |
|
|
|
08/31/98 338 - R-BAR PLACED OK TO POUR WITH SPP INSP APPROVAL
|
Issue PAID IN FULL permit | | | 8/18/1998 | | |
|
|
|
|
Print Occupancy Form | | | 8/13/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/13/1998 | | |
|
|
|
|
Plan assigned to (ADS) | 5/4/1998 | | 8/4/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/30/1998 | | 8/4/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/4/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/4/1998 | | |
|
|
|
RECEIVED2 COPIES OF ADDENDUM NO. 2 ROUTED TO ARLAN
|
Plan resubmittals received | | | 7/31/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS ON 8 1/2" BY 11 PAPER FORWARDED SAME TO ARLAN. ADVISED ARLAN THAT NORMALY WE ACCEPTED ON FULL SIZE CHANGE SHEETS. DAR
|
Routing - FIRE | 7/27/1998 | | 7/29/1998 | | PASS |
|
|
|
approved with corrections to sprinkler riser required.
|
90 day tracking............. | | 4/27/1998 | 7/26/1998 | | PEND |
|
|
|
|
Routing - PLANNING | 7/24/1998 | | 7/24/1998 | | PASS |
|
|
|
x-ref. DRH98-0115
|
Routing - PLUMBING | 7/17/1998 | | 7/20/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 7/15/1998 | | PEND |
|
|
|
RECEIVED RESUBS FROM PETERSEN STAGGS, FORWARDED SAME TO ARLAN SMITH
|
Routing - FIRE | 5/20/1998 | | 6/1/1998 | | FAIL |
|
|
|
Corrections required on phasing of sprinklers and exits,info needed on refer systems/machinery room.
|
Plan Review Completed(1st rev) | | | 6/1/1998 | | FAIL |
|
|
|
Not all agencies approved
|
Routing - PLAN CHECK | 5/18/1998 | | 5/20/1998 | | FAIL |
|
|
|
Initial plan review report faxed to achitect.
|
Plan resubmittals requested | | | 5/20/1998 | | FAIL |
|
|
|
Initial plan review report faxed to architect.
|
Routing - PLUMBING | 5/13/1998 | | 5/18/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 5/12/1998 | | 5/13/1998 | | FAIL |
|
|
|
The applicant still needs to submit a design review application.
|
Routing - PUBLIC WORKS | 5/8/1998 | | 5/12/1998 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 5/4/1998 | | 5/8/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 4/27/1998 | | 5/4/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/4/1998 | | PEND |
|
|
|
RECEIVED 3 SETS OF PLANS AND SPECS. SHEET 1.2 NOT SIGNED. CALLED TIM STAGGS
|
Recd Pcfee & Taken To Pln CK | | | 4/27/1998 | | PEND |
|
|
|
|
Application received | | | 4/27/1998 | | |
|
|
|
|
Fee Review-notes | 9/10/1998 | | 3/23/1998 | | |
|
|
|
|