Permit Information
Permit NumberBLD98-01191
StatusFinaled
Name DARRELL JANSEN
Site Address 6850 S BUSINESS WAY
Project NameWHITEMAN INDUSTRIES
Customer Number 
ePlanReviewNo
Description
WHITEMAN INDUSTRIES * TO CONSTRUCT A NEW 133,130 SQ.FT., ONE STORY WITH MEZZANINE MANUFACTURING FACILITY. CONSTRUCTED OF PRECAST TILT-UP CONCRETE EXTERIOR WALL PANELS, CONCRETE SLAB FLOORS, STEEL COLUMNS, ROOF GIRDERS AND JOIST, METAL ROOF DECK AND INTERIOR METAL STUD PARTITIONS. THIS BUILDING IS FULLY FIRE SPRINKLED. THE SPRINKLERS ARE USED FOR ALLOWABLE AREA INCREASES. THIS PERMIT ALSO INCLUDES RELATED SITE IMPROVEMENTS. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. DRH97-0173/PC#269-98/JCM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Permanent Occupancy 8/5/19998/5/1999 DONE
Details
INSP - Final8/3/19998/5/19998/5/1999APASS
DetailsJim Storey
08/05/99 301 - ###-#### BRIAN
INSP-Final Inspection8/3/19998/5/19998/5/1999APASS
DetailsRick Jackson
10:00 AM TALKED TO RICK. BRIAN ###-#### occ approved
Permanent occupancy  8/5/1999 PASS
Perm. Occ. Cert. #7862 issued 8-5-99 to Whiteman Industries.
INSP-Conference8/3/19998/3/19998/3/1999APART
DetailsRick Jackson
requirements for final sign-off; set up final inspection for 8/5
INSP - Final7/21/19997/27/19997/27/1999AFAIL
DetailsJim Storey
07/27/99 301 - c/n
INSP-Final Inspection7/21/19997/27/19997/27/1999AFAIL
DetailsRick Jackson
BRIAN ###-#### LIFE SAFETY at 10:00 as per rick j. fire lanes
Code Occupancy Approval  7/26/1999 PASS
ALL CONDITIONS OF DRH97-0173 HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF AND BOND RELEASE
Code Occupancy Approval  7/21/1999
Final requested by Brian Henderson ###-####
SUPER- Supervisor's review4/1/19994/1/19994/1/1999
ready for final once spriklers clear and sign offs obtained.
SUPER- Supervisor's review2/16/19992/16/19992/16/1999
dave l. not finaled yet. waiting for spray booth info
SUPER- Supervisor's review2/5/19992/5/19992/5/1999
mechanical issues on line equipment settled and we can clear the issue of owner installed portable equipment
INSP-Conference1/26/19991/26/19991/26/1999 PART
DetailsRick Jackson
/ / 409 - SPRAY BOOTH APPROVED FOR USE
SUPER- Supervisor's review1/26/19991/26/19991/26/1999
marlene dave lightfoot jim storey myself ment concerning permit requirment for paint line installed from out of state. it is portable equip and can be removed so we permitted installation on the building permit and gas by local contractor
INSP-Conference1/25/19991/25/19991/25/1999APART
DetailsRick Jackson
discussed resubmittal on booth - they will submit info for the booth operation
INSP-Conference1/22/19991/22/19991/22/1999PFAIL
DetailsRick Jackson
discussed with VP the paint booth operation. placed not to occupy sticker on unit and issued c/n to not to use the paint booth until approved.
Print Occupancy Form  1/22/1999
Inspection Record Card- Bld  1/22/1999
INSP-Final Inspection1/20/19991/21/19991/21/1999AFAIL
DetailsRick Jackson
mike -###-#### fn fire insp exsisting paint booth inspection - unit removed from old shop and installed in new fab building: doesn't comply with NFPA or UFC - will discuss with plan check and inspections about shutting it down
SUPER- Supervisor's review1/20/19991/20/19991/20/1999
dave lightfoot working with storey to reconcile problem of lack of permits and fees on line equipment per lightfoots c/n
SUPER- Supervisor's review1/12/19991/12/19991/12/1999
confusion on fees and mec inspection. dave lightfoot is getting with drake mechanical to see what the problem was. dave is to fill me in and we will respond to the owner.
INSP-Alarm Testing1/12/19991/12/19991/12/1999APASS
DetailsRick Jackson
tested preaction system only. okay per plans. still need knox box, perm address, label annunciator
SUPER- Supervisor's review1/11/19991/11/19991/11/1999
reviewed paint equipment installed with owner. inspection needed to take place on gas lines. Dave lightfoot will check with mec contractor to find out why inspection was not called for
INSP - Final12/28/199812/29/199812/29/1998APART
DetailsJim Storey
12/29/98 301 - SCLG-OK SUSPENDED CEILING at main entry
INSP-Conference12/29/199812/29/199812/29/1998APART
DetailsRick Jackson
checked status for final; recheck preaction system functions
INSP - Framing/Rough-in12/21/199812/22/199812/22/1998APART
DetailsJim Storey
12/22/98 301 - TCO -TEMP C OF O ISSUED need follow up in 90 days
Temporary occupancy  12/22/1998 PASS
Temp. Occ. Cert. #3763 issued 12-22-98 to Whiteman Industries.
INSP - Final12/21/199812/21/199812/21/1998 NR
DetailsJim Storey
12/21/98 301 - jeff ###-#### temp occ insp
INSP - Final12/18/199812/21/199812/21/1998ANR
DetailsJim Storey
12/21/98 301 - jeff ###-#### temp occ insp
INSP-Final Inspection12/18/199812/21/199812/21/1998APART
DetailsRick Jackson
12/21/98 409 - JEFF...###-#### test preaction; perm address; NFPA 72 ansd central station certificate
INSP-Final Inspection12/18/199812/18/199812/18/1998PFAIL
DetailsRick Jackson
12/18/98 409 - sprinklers not complete in office area
INSP - Framing/Rough-in12/15/199812/15/199812/15/1998PPART
DetailsJim Storey
12/15/98 301 - SCLG-OK SUSPENDED CEILING
Temporary occupancy  12/15/1998 PASS
Temp. Occ. cert. #3759 issued 12-15-98 to Whiteman Industries, portion of warehouse only.
INSP - Final12/14/199812/14/199812/14/1998PPART
DetailsJim Storey
12/14/98 301 - TEMP OK FOR GRID LINE 1 THRU H IN F-1 OCC ONLY.
INSP-Final Inspection12/14/199812/14/199812/14/1998PPART
DetailsRick Jackson
temp occ approved for fab area grid lines a-h only. tested alarms, sprinklers, etc. preaction system not complete. office areas not ready
Code Occupancy Approval  12/10/1998 FAIL
REQUEST FOR TEMPORARY OCCUPANCY, BOND POSTED WITH CATHY FOR OVER $7,000 TO COMPLETE LANDSCAPE PER DR, I OKED THE AMOUNT AND SIGNED OFF FOR TEMPORARY OCCUPANCY.
INSP-Conference12/8/199812/8/199812/8/1998APART
DetailsRick Jackson
discussed requirements for temp occ with contractor and owners
INSP - Final12/7/199812/8/199812/8/1998ANR
DetailsJim Storey
12/08/98 301 - conf for temp occ. work in progess
Code Occupancy Approval  12/4/1998
Temporary requested by Casey ###-####. Contact either Casey or Joel with questions.
INSP-Conference12/2/199812/2/199812/2/1998PPART
DetailsRick Jackson
to determine requirements for moving in equipment and partial occupancy. off-site monitoring; extinguishers; tape on sprinkler heads; pre-action system plans; knox box; test alarms
INSP - Framing/Rough-in11/5/199811/6/199811/6/1998APART
DetailsTom Arcoraci
11/06/98 408 - JEFF--###-#### ok to cover one side of office area
INSP-Final Inspection11/5/199811/6/199811/6/1998PPART
DetailsJoe Tawney
11/06/98 406 - MIKE- ###-#### FIRE INSP OK ON ABOVE GROUND HYDRO TEST EXC FDC PIPING OK ON RI EXC OBSTR HEADS
INSP - Framing/Rough-in11/2/199811/2/199811/2/1998APART
DetailsJim Storey
11/02/98 301 - framing ok on a3 occ
INSP - Framing/Rough-in10/30/199810/30/199810/30/1998PFAIL
Details
10/30/98 333 - ###-####
INSP-Supply line flush10/22/199810/22/199810/22/1998PPASS
DetailsRick Jackson
underground flush okay
INSP-Sprinkler Rough-in/Hydro10/13/199810/13/199810/13/1998APART
DetailsRick Jackson
underground hydro okay. sway bracing needed as most areas not complete. okay to cover in 1st floor of bathroom areas (fab area)
INSP - Framing/Rough-in10/12/199810/12/199810/12/1998PPART
DetailsJim Storey
10/12/98 301 - JEFF ###-#### FRAM-OK FRAMING ì
INSP-Sprinkler Rough-in/Hydro9/24/19989/24/19989/24/1998APART
DetailsRick Jackson
checked approved plans and general area, recheck riser piping for hangers
Plan resubmittals received  9/15/1998
RESUBS OK'D BY DAVE LIGHTFOOT..HE WILL TAKE COPY TO JOB SITE..OTHER COPY WENT TO RECORDS
INSP - Concrete9/1/19989/1/19989/1/1998 PASS
DetailsJim Storey
09/01/98 301 - after lunch early afternoon terry ###-#### 2nd lift massonary restrooms ok
INSP - Concrete8/28/19988/28/19988/28/1998ACANC
DetailsRuss Owen
requires special insp. 08/28/98 407 - first thing in the morning terry ###-####
INSP - Concrete8/25/19988/26/19988/26/1998AFAIL
DetailsJim Storey
08/26/98 301 - terry ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED arch. and engineer of record submit info. to resolve 4 idems posted on site.
90 day tracking............. 4/28/19987/27/1998 PEND
(F) Reprint permit  7/13/1998
Print Occupancy Form  7/10/1998
Inspection Record Card- Bld  7/10/1998
Issue PAID IN FULL permit  7/10/1998
Routing - PLAN CHECK6/23/1998 7/9/1998 PASS
Plan assigned to (JCM)5/20/1998 7/9/1998 PASS
DetailsJohn Menard
Plan resubmittals received  7/9/1998 PASS
Telephone call  7/9/1998
CALL BILL MATTER PERMIT READY
PLANS/APPL TAKEN TO FRONT DESK  7/9/1998 PASS
Plan resubmittals requested  7/6/1998 PEND
FAXED BILL MATTER A REQUEST FOR AN ADDITIONAL RESUBMITTAL.
Routing - FIRE7/2/1998 7/2/1998 PASS
allowed permit approval pending delayed submittals on paint booths, haz mat plan, lp tank, and fire alarms
Routing - PUBLIC WORKS6/23/1998 6/23/1998 PASS
Plan Review Completed(1st rev)  6/19/1998 FAIL
UBC Public WKS and UFC fail
Routing - FIRE6/11/1998 6/19/1998 FAIL
need info on paint booth, powder coat booth and haz mat. alarm plans needed for delayed submittal
Plan resubmittals requested  6/11/1998 PEND
MAILED BILL MATTER A COPY OF THE CORRECTION LIST.
Routing - PLAN CHECK5/27/1998 6/11/1998 PEND
Routing Off Site - STRUCTURAL6/2/1998 6/5/1998 PEND
Plan resubmittals received  5/29/1998
RECIEVED RESUBMITTALS AND SENT THEM TO JOHN MENARD
Telephone call  5/28/1998 PASS
TALKED TO BILL MATTER TO VERIFY THAT PLANS ARE READY
Routing - PUBLIC WORKS5/26/1998 5/27/1998 FAIL
MANUFACTURING PROCESS CLEANER FLOW INFO OF BE PROVIDED TO WALT BAUMGARTNER AND NECESSARY TO COMPLETE FEES. PER BAD
Routing - PLUMBING5/19/1998 5/22/1998 PASS
Plan Reviewer's activity  5/22/1998 PEND
FAXED BILL MATTER A COPY OF THE STRUCTURAL PLAN REVIEW COMMENTS TO FORWARD TO THE ENGINEER OF RECORD TO RESPOND.
Plan assigned to (MYS)4/28/1998 5/20/1998
DetailsMarlene Southard
Routing - PLANNING5/13/1998 5/19/1998 PASS
drh97-0173
Routing Off Site - STRUCTURAL5/7/1998 5/18/1998 PEND
SENT TO ATWOOD HINZMAN AND JONES RECEIVED COMENTS FROM RILEY MAHAFFEY, SECOND REVIEW REQUIRED. 5/1998 DAR
Routing - PUBLIC WORKS5/7/1998 5/13/1998 FAIL
INCOMPLETE LEGAL DESCRIPTION, INCOMPLETE SITE PLAN, PROOF OF LEGAL LAND DIVISION, REQUIRES DRAINAGE PLAN APPROVAL PER JRICH MANUFACTURING PROCESS CLEANER FLOW INFO TO BE PROVIDED TO WALT BAUMGARTNER AND NECESSARY TO COMPLETE FEES PER BDUGGER.
Plans ACCEPTED BY PLAN CHECK  5/7/1998 PEND
RECEIVED PLANS AS REQUESTED. NEED SITE PLAN DEPICTING SITE UTILITIES, RECEIVED SAME ON 5/6/98
Routing - PLAN CHECK4/28/1998 5/7/1998 PEND
Recd Pcfee & Taken To Pln CK  4/28/1998 PEND
Application received  4/28/1998