INSP - Final | 6/4/1999 | 6/7/1999 | 6/7/1999 | A | PASS |
Wes Worcester
|
|
|
06/05/99 342 - ###-#### rich
|
INSP - Grading Inspection | 6/7/1999 | | 6/7/1999 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete, fine grading and revegetation are not. The engineer has recommended a bond of $750.00 for the incomplete work. This is acceptable and the grading is conditionally accepted upon receipt of the surety.
|
INSP - Final | 6/3/1999 | 6/4/1999 | 6/4/1999 | A | FAIL |
Wes Worcester
|
|
|
06/04/99 342 - Rich ###-#### need public wks sign off
|
INSP - Final | 5/27/1999 | 5/28/1999 | 5/28/1999 | A | FAIL |
Wes Worcester
|
|
|
05/27/99 342 - ###-#### Rich need driveway and p/w
|
INSP - Framing/Rough-in | 1/12/1999 | 1/12/1999 | 1/12/1999 | P | PASS |
Wes Worcester
|
|
|
01/12/99 342 - rich
|
INSP - Framing/Rough-in | 12/17/1998 | 12/18/1998 | 12/18/1998 | A | PASS |
Wes Worcester
|
|
|
12/18/98 342 - RICK ###-####
|
INSP - Framing/Rough-in | 12/15/1998 | 12/16/1998 | 12/16/1998 | A | PART |
Wes Worcester
|
|
|
bcec ok, will redo frame 12/17 am when insulated
|
INSP - Framing/Rough-in | 12/14/1998 | 12/14/1998 | 12/14/1998 | P | FAIL |
Wes Worcester
|
|
|
RICH- ###-#### FR INSP shear covered, truss engineering not on site, no one there
|
INSP - Framing/Rough-in | 12/9/1998 | 12/10/1998 | 12/10/1998 | A | FAIL |
Wes Worcester
|
|
|
RICH ###-#### truss eng, bcec, shr, pt lds, still need frplc insp
|
INSP - Wall cover | 8/27/1998 | 8/27/1998 | 8/27/1998 | P | PASS |
Wes Worcester
|
|
|
08/27/98 342 - donnie ###-####
|
INSP - Foundation | 8/24/1998 | 8/25/1998 | 8/25/1998 | A | PART |
Wes Worcester
|
|
|
08/24/98 342 - DONNY ###-####
|
SUPER- Supervisor's review | 7/24/1998 | 7/24/1998 | 7/24/1998 | | FAIL |
|
|
|
Had Tom A. contact design engineer. Engineer informed him he had not inspected foundation prior to cover. Instructed Tom to place a SWO on project, gave Tim H. a heads-up.
|
Print Pending Permit.LaserJet4 | | | 7/24/1998 | | |
|
|
|
|
INSP - Foundation | 7/22/1998 | 7/23/1998 | 7/23/1998 | A | PART |
Tom Arcoraci
|
|
|
07/23/98 408 - basement walls donny ###-#### LEFT C/N FOR ENG TO INSPECT AND OK
|
SUPER- Supervisor's review | 7/23/1998 | 7/23/1998 | 7/23/1998 | | PEND |
|
|
|
Spoke to Rich,###-####, regarding specific conditions listed on scope of permit regarding inspection of engineered systems. Rich is in disagreement of conditions and WILL GET BACK TO ME.
|
Print Pending Permit.LaserJet4 | | | 7/23/1998 | | |
|
|
|
|
INSP - Foundation | 7/9/1998 | 7/9/1998 | 7/9/1998 | P | NR |
Wes Worcester
|
|
|
07/09/98 342 - footing donny ###-####
|
INSP - Foundation | 7/9/1998 | 7/9/1998 | 7/9/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 - called back
|
Inspection Record Card- Bld | | | 6/25/1998 | | |
|
|
|
|
Print Occupancy Form | | | 6/25/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/25/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 6/24/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/24/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 6/24/1998 | | PASS |
|
|
|
RECEIVED WALL BRACE ENGINEERING.
|
Plan assigned to (DJO) | 5/1/1998 | | 6/24/1998 | | PASS |
Dan Overy
|
|
|
06/24/98 16:45:10 DJO - this action updated by action script from <<>> in Case No. BLD98-1217
|
Plan Reviewer's activity | | | 6/10/1998 | | PEND |
|
|
|
CONTACTED BUILDER, ARCHITECT, AND ENGINEER ABOUT INDICATING ALL BRACE PANEL AREAS. WALLS NOT MEETING PRESCRIPTIVE BRACING WILL BE ADDRESSED BY ENGINEER, BEFORE ISSUANCE OF PERMIT.
|
Plans ACCEPTED BY PLAN CHECK | | | 6/9/1998 | | PEND |
|
|
|
|
Routing - PLANNING | 5/28/1998 | | 5/28/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/28/1998 | | 5/27/1998 | | PASS |
|
|
|
|
Application received | | | 5/1/1998 | | |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 5/27/1998 | | 5/27/1997 | | PASS |
Rita DeYoung
|
|
|
Approved as Category 3
|
Routing - PLAN CHECK | 5/28/1998 | | | | PEND |
|
|
|
|