Permanent Occupancy | | 4/8/1999 | 4/8/1999 | | DONE |
|
|
|
|
INSP - Final | 4/8/1999 | 4/8/1999 | 4/8/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - OK FOR PERM C/O, CARD TO CONT.
|
INSP - Final | 4/8/1999 | 4/8/1999 | 4/8/1999 | P | PASS |
Joe Tawney
|
|
|
04/08/99 406 - PERMIT WAS SIGNED OFF PERM 3/25/99
|
Permanent occupancy | | | 4/8/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7728 issued 4-8-99 to Peterson Motors for a showroom & ofc. addn.
|
INSP-Final Inspection | 3/25/1999 | 3/25/1999 | 3/25/1999 | P | PASS |
Joe Tawney
|
|
|
03/25/99 406 - REINSP OK FOR PERM OCC OR CERT OF COMPLETION
|
Code Occupancy Approval | | | 2/8/1999 | | PASS |
|
|
|
Charlie of CM Company requested Final (####-#### Voice Pager/###-####). Inspection revealed though the proj. was complete - they did not construct according to approved plans DRH98-0025. I advised Charlie to have architect provide "As Built Plans" to Tempra Wilson Design Review Analyst and see if they could get them approved. The proj. as built is actually a better design and provides better traffic flow - but, unfortunately was not approved as such. Contacted Tempra Wilson who responded bvy E-Mail 2/8/99 - Filed plans - O.k.
|
INSP - Final | 9/30/1998 | 9/30/1998 | 9/30/1998 | P | PART |
|
|
|
09/30/98 338 - made ok for the temp occ cert
|
Temporary occupancy | | | 9/30/1998 | | PASS |
|
|
|
Temp. Occ. Cert. #3707 issued 9-30-98 to Peterson Motors.
|
INSP - Final | 9/29/1998 | 9/29/1998 | 9/29/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC OF SHOWROOM NO OCC OF REAR AREA
|
INSP-Sprinkler Rough-in/Hydro | 9/28/1998 | 9/28/1998 | 9/28/1998 | P | NR |
Joe Tawney
|
|
|
09/28/98 406 - CHARLIE ###-#### REINSP NOT READY COULD NOT TEST DUCT DET
|
INSP-Final Inspection | 9/24/1998 | 9/25/1998 | 9/25/1998 | A | FAIL |
Rick Jackson
|
|
|
jeff ###-#### install remote LED's for duct detectors
|
INSP-Sprinkler Rough-in/Hydro | 9/18/1998 | 9/18/1998 | 9/18/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON HYDRO TEST OF SPKLR ADDITION
|
INSP-Conference | 9/17/1998 | 9/17/1998 | 9/17/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - PROFIT MEETING ON NEW SHOWROOM PERRY, PAT, AND ME
|
INSP - Framing/Rough-in | 9/8/1998 | 9/9/1998 | 9/9/1998 | A | PART |
|
|
|
09/09/98 338 - ceiling grid made ok told elec. to tighten up the wraps o
|
INSP-Sprinkler Rough-in/Hydro | 9/8/1998 | 9/9/1998 | 9/9/1998 | P | PART |
Joe Tawney
|
|
|
09/09/98 406 - JEFF ###-#### OK ON ROUGH IN OF SHOWROOM OK TO COVER ì
|
INSP - Framing/Rough-in | 8/20/1998 | 8/21/1998 | 8/20/1998 | A | PART |
|
|
|
08/21/98 338 - BRIAN ###-#### MADE OK TO COVER WITH SP INSP AND ELE APPR
|
INSP - Framing/Rough-in | 8/17/1998 | 8/17/1998 | 8/17/1998 | P | PART |
|
|
|
08/17/98 338 - made ok to cover sofit as the sp insp is completed for th
|
INSP - Framing/Rough-in | 7/23/1998 | 7/24/1998 | 7/24/1998 | P | PART |
|
|
|
07/24/98 338 - MADE OK WITH SP INSP APPROVAL
|
INSP - Framing/Rough-in | 7/22/1998 | 7/23/1998 | 7/23/1998 | P | PART |
|
|
|
07/23/98 338 - made ok with sp insp approval
|
INSP - Framing/Rough-in | 7/16/1998 | 7/17/1998 | 7/17/1998 | A | PART |
|
|
|
07/17/98 338 - made ok with sp insp approval
|
INSP - Framing/Rough-in | 7/17/1998 | 7/17/1998 | 7/17/1998 | | PART |
|
|
|
07/17/98 338 - madeok with sp insp approval
|
INSP - Framing/Rough-in | 7/15/1998 | 7/15/1998 | 7/16/1998 | P | PART |
|
|
|
07/16/98 338 - made ok to pour with sp insp approval
|
INSP - Foundation | 7/13/1998 | 7/13/1998 | 7/13/1998 | P | PART |
|
|
|
07/13/98 338 - mad ok for part footings ok to pour witrh sp insp blessin
|
INSP - Foundation | 7/9/1998 | 7/10/1998 | 7/10/1998 | A | PART |
|
|
|
07/10/98 338 - BRYAN ###-#### done by 342 passed with corrections in his
|
Telephone call | | | 6/11/1998 | | PASS |
|
|
|
TALKED TO DAVID MOE ###-#### THAT PLANS ARE READY
|
Issue PAID IN FULL permit | | | 6/11/1998 | | |
|
|
|
|
Print Occupancy Form | | | 6/10/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 5/22/1998 | | 6/10/1998 | | PASS |
|
|
|
|
Plan assigned to (ADS) | 5/12/1998 | | 6/10/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 6/9/1998 | | |
|
|
|
received responses to structural plan review.
|
Routing Off Site - STRUCTURAL | 5/12/1998 | | 6/9/1998 | | |
|
|
|
SENT TO CH2MHILL RECEIVED REPLY FROM HOWIE. RESUBS REQUIRED TO US OR HOWIE, OUR CALL.
|
Plan resubmittals received | | | 5/29/1998 | | |
|
|
|
ceiling design for lateral loads
|
Plan resubmittals requested | | | 5/29/1998 | | FAIL |
|
|
|
faxed initial nonstructural review report to architect and applicant - need ceiling bracing detail. I spoke to Wes Edwards (architect) on the phone after he recieved the fax.
|
Routing - FIRE | 5/19/1998 | | 5/22/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 5/18/1998 | | 5/19/1998 | | FAIL |
|
|
|
pending structural review, fire dept. approval. Seismic design for ceiling needed.
|
Routing - PLANNING | 5/14/1998 | | 5/14/1998 | | PASS |
|
|
|
DRH98-0025
|
Routing - PUBLIC WORKS | 5/12/1998 | | 5/14/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 5/7/1998 | | 5/12/1998 | | PASS |
Marlene Southard
|
|
|
|
Application received | | | 5/7/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/7/1998 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 5/7/1998 | | | | PEND |
|
|
|
|