Permit Information
Permit NumberBLD98-01328
StatusFinaled
Name BSU FOUNDATION
Site Address 1019 S EUCLID ST
Project NameBSU ENGINEERING BLDG
Customer Number 
ePlanReviewNo
Description
CONSTRUCT NEW 18,000 SQ FT TWO STORY TYPE II-1HR VOCATIONAL CLASSROOM BUILDING AT BSU. THE FIRST FLOOR WILL HAVE 14,448 SQ FT AND THE SECOND FLOOR WILL HAVE 4,512 SQ FT. THE BUILDING IS FULLY FIRE SPRINKLERED WITH SPRINKLERS BEING USED FOR ONE HOUR SUBSTITUTION. OTHER WORK INCLUDES GRADING, PAVING, LANDSCAPING AND ALL OTHER SITE IMPROVEMENTS. ALL WORK IS PER APPROVED PLANS PC98-291, CUP98-0029 MLO
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes6/24/20036/24/20036/24/2003 DONE
Additional values from subcontractors.
Permanent occupancy  1/12/2000 DONE
Perm. Occ. Cert. #8083 issued 1-12-00 to the B.S.U. Engineering Bldg.
BLD-Final1/10/20001/11/20001/11/2000APASS
DetailsJim Storey
Call 1st - Harry Allen @ ###-####. Final ok.
Permanent Occupancy 1/11/20001/11/2000 DONE
Details
Receive PAYMENT IN FULL  12/23/1999 DONE
Code Occupancy Approval  11/23/1999 PASS
ALL CONDITIONS OF CUP98-00029 HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
BLD-Other10/27/199910/28/199910/28/1999APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/27/1999 at 14:21:02. Contact: ###-####. Ok for temp. C/N w/harry
Temporary occupancy  10/28/1999 PART
Temp. Occ. Cert. #3934 issued 10-28-99 to B.S.U. Civil Engineering.
FIRE-Final Inspection10/26/199910/27/199910/27/1999APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/26/1999 at 15:05:22. Contact: ###-####. Occ. Approved
FIRE-Final Inspection10/25/199910/26/199910/26/1999ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/25/1999 at 15:40:52. Contact: ###-####. Contractor to reschedule
BLD-Final10/22/199910/26/199910/26/1999ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/22/1999 at 14:26:46. Contact: ###-####. Harry called and canceled.
BLD-Final10/22/199910/25/199910/25/1999ANR
DetailsJim Storey
Harry Allen ###-#### Harry called and canceled
FIRE-Final Inspection10/22/199910/22/199910/22/1999PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/22/1999 at 10:09:08. Contact: ###-####. Met with State Farm Marshall to test alarms- alarms not ready- reinspected fee assessed
Code Occupancy Approval  10/12/1999 FAIL
Temporary signed - One planter at center of court to be completed. Doors on enclosure and light at southwest corner of building to be finished.
FIRE-Final Inspection10/5/199910/5/199910/5/1999PFAIL
DetailsRick Jackson
Forest ###-#### not a final - underground supply line hydro-pass; overhead sprinklers complete-awaiting fire alarm connection
FIRE-Final Inspection9/30/199910/1/199910/1/1999PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/30/1999 at 15:35:39. Contact: ###-####. Need alarm plans; sprinlkers not complete
FIRE-Final Inspection9/30/199910/1/199910/1/1999PCANC
DetailsRick Jackson
Harry Allen ###-#### Double entry
FIRE-Final Inspection9/21/19999/22/19999/22/1999PFAIL
DetailsRick Jackson
forest ###-#### Sprinkler rough-in inspection- need spare head box; test alarms; repair leaking head; hydro test FDC
INSP-Supply line flush5/21/19995/21/19995/21/1999PPASS
DetailsRick Jackson
underground okay
INSP - Framing/Rough-in4/27/19994/28/19994/28/1999AFAIL
DetailsWes Worcester
04/28/99 342 - Scheduled by Hello!. Contact phone is [4264998]. unable
INSP - Framing/Rough-in3/30/19993/31/19993/31/1999APART
DetailsWes Worcester
03/31/99 342 - Scheduled by Hello!. repkace screws at door jambs, ck th
Fee Review-notes11/2/1998 3/23/1999
INSP-Conference3/8/19993/8/19993/8/1999APART
DetailsRick Jackson
with gen and 301 - reviewed plans and walk through of site
INSP - Foundation2/5/19992/5/19992/5/1999 PASS
DetailsJim Storey
/ / 301 - REVIEWED SPECIAL INSP REPORT AND ARCHOIVED TO CITY.
INSP - Foundation10/7/199810/8/199810/8/1998APART
DetailsRuss Owen
10/08/98 407 - stell in place looks good ,special insp required.
INSP - Foundation9/23/19989/24/19989/24/1998APART
DetailsWes Worcester
09/24/98 342 - poured, special inspector had already left 3898612].
INSP - Foundation9/17/19989/17/19989/17/1998 PART
DetailsJim Storey
/ / 301 - FTG -OK FOOTING 1-7 grid a, d.8 line special insp. on site pending repor
INSP - Foundation9/17/19989/17/19989/17/1998PCANC
DetailsRuss Owen
09/17/98 407 - trans to 301.Hello!. Contact phone is [3898612].
(F) Reprint permit  8/26/1998
Issue PAID IN FULL permit  8/25/1998
Print Occupancy Form  8/21/1998
PLANS/APPL TAKEN TO FRONT DESK  8/21/1998 PASS
Inspection Record Card- Bld  8/21/1998
Plan assigned to (MLO)5/12/1998 8/21/1998 PASS
DetailsMike Otto
Plan Reviewer's activity  8/18/1998 PEND
REFAXED SOILS REPORT BACK TO KEITH JONES FOR REVIEW OF ROOF DRAINAGE UNDER FOUNDATION. MLO
Routing - PUBLIC WORKS8/11/1998 8/12/1998 PASS
Plan resubmittals received  8/7/1998
RECEIVED 2 COPIES OF SITE PLAN SHEET A1.1 AND ONE COPY OF LETTER FROM JERRY LOWE. ROUTED TO MIKE O.
Plan resubmittals received  8/7/1998 PEND
RECEIVED REVSIED SITE PLANS. MLO
Routing - PLAN CHECK8/4/1998 8/6/1998 PASS
Meeting  8/6/1998 PEND
MET WITH ARCHITECT AND HAD PLANS REDLINED AND SIGNED BY ARCHITECT. MLO
Plan resubmittals requested  8/6/1998 PEND
REQUESTED ARCHITECT TO PROVIDE REVISED SITE PLAN. MLO
Meeting  8/5/1998 PEND
MET WITH JERRY LOWE REGARDING INCOMPLETE CORRECTIONS ON PLANS RECEIVED 8-4-98. MLO
Plan resubmittals received  8/4/1998 PEND
RESPONCE TO INTIAL PLAN REVIEW. MLO
Plan resubmittals received  8/3/1998
RECEIVED TWO COPIES OF REVISED SHEETS A0.4, CA2.1, CA2.2, CA3.1, CA9.1, CA10.2, CM1.1, CM2.1, CM2.2, CM3.1, CE2.1, CE3.1, CE3.2,. ONE COPY OF RESPONES TO CORRECTION ITEMS. ROUTED TO MIKE O.
Meeting  7/15/1998 PEND
MET WITH TWO ARCHITECTS AND FOUR MECHANCIAL ENGINEERS FROM CSHQA REGARDING PLAN REVIEW COMMENTS. MLO
Routing Off Site - STRUCTURAL7/7/1998 7/15/1998 PASS
RECEIVED THREE ADDITIOANL COMMENTS BUT NO FURTHER REVIEW REQURIED BY K. JONES. MLO
Routing - PLAN CHECK7/7/1998 7/10/1998 FAIL
Plan resubmittals requested  7/10/1998 FAIL
CORRECTIONS GIVEN TO ARHCITECT IN MEETING AT THE BUILDING DEPT. MLO
Plan resubmittals received  7/8/1998 PEND
RECEIVED CHEMICAL REPORT FROM ARCHITECT.
Plan resubmittals received  7/7/1998 PEND
RECEIVED RESUBMITTALS FROM CSHQA, FORWARDED SAME TO MIKE OTTO.
Plan resubmittals received  7/6/1998 PEND
RECEIVED RESUBMITTALS AT 5PM 7/2/98, LOGGED IN AT 0800AM 07/06/98, FORWARDED SAME TO MIKE OTTO.
Plan Review Completed(1st rev)  6/17/1998 FAIL
delayed 3 days in fire - no reviewer not all agencies approved
Routing - FIRE6/8/1998 6/17/1998 PASS
fire alarm plans req'd, HMMP required
Plan resubmittals requested  6/8/1998 FAIL
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
Routing - PLAN CHECK6/3/1998 6/8/1998 FAIL
Routing - PLUMBING5/28/1998 6/3/1998 PASS
Routing - PUBLIC WORKS5/14/1998 5/28/1998 FAIL
NEEDS DRAINAGE PLAN REVISION AND EASEMENTS.
Routing Off Site - STRUCTURAL5/11/1998 5/26/1998 FAIL
Routing - PLANNING5/12/1998 5/13/1998 PASS
Plans ACCEPTED BY PLAN CHECK  5/12/1998 PEND
Application received  5/7/1998