Fee Review-notes | 6/24/2003 | 6/24/2003 | 6/24/2003 | | DONE |
|
|
|
Additional values from subcontractors.
|
Permanent occupancy | | | 1/12/2000 | | DONE |
|
|
|
Perm. Occ. Cert. #8083 issued 1-12-00 to the B.S.U. Engineering Bldg.
|
BLD-Final | 1/10/2000 | 1/11/2000 | 1/11/2000 | A | PASS |
Jim Storey
|
|
|
Call 1st - Harry Allen @ ###-####. Final ok.
|
Permanent Occupancy | | 1/11/2000 | 1/11/2000 | | DONE |
|
|
|
|
Receive PAYMENT IN FULL | | | 12/23/1999 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 11/23/1999 | | PASS |
|
|
|
ALL CONDITIONS OF CUP98-00029 HAVE BEEN MET, FINAL OCCUPANCY SIGNED OFF.
|
BLD-Other | 10/27/1999 | 10/28/1999 | 10/28/1999 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/27/1999 at 14:21:02. Contact: ###-####. Ok for temp. C/N w/harry
|
Temporary occupancy | | | 10/28/1999 | | PART |
|
|
|
Temp. Occ. Cert. #3934 issued 10-28-99 to B.S.U. Civil Engineering.
|
FIRE-Final Inspection | 10/26/1999 | 10/27/1999 | 10/27/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/26/1999 at 15:05:22. Contact: ###-####. Occ. Approved
|
FIRE-Final Inspection | 10/25/1999 | 10/26/1999 | 10/26/1999 | A | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/25/1999 at 15:40:52. Contact: ###-####. Contractor to reschedule
|
BLD-Final | 10/22/1999 | 10/26/1999 | 10/26/1999 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 10/22/1999 at 14:26:46. Contact: ###-####. Harry called and canceled.
|
BLD-Final | 10/22/1999 | 10/25/1999 | 10/25/1999 | A | NR |
Jim Storey
|
|
|
Harry Allen ###-#### Harry called and canceled
|
FIRE-Final Inspection | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/22/1999 at 10:09:08. Contact: ###-####. Met with State Farm Marshall to test alarms- alarms not ready- reinspected fee assessed
|
Code Occupancy Approval | | | 10/12/1999 | | FAIL |
|
|
|
Temporary signed - One planter at center of court to be completed. Doors on enclosure and light at southwest corner of building to be finished.
|
FIRE-Final Inspection | 10/5/1999 | 10/5/1999 | 10/5/1999 | P | FAIL |
Rick Jackson
|
|
|
Forest ###-#### not a final - underground supply line hydro-pass; overhead sprinklers complete-awaiting fire alarm connection
|
FIRE-Final Inspection | 9/30/1999 | 10/1/1999 | 10/1/1999 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 09/30/1999 at 15:35:39. Contact: ###-####. Need alarm plans; sprinlkers not complete
|
FIRE-Final Inspection | 9/30/1999 | 10/1/1999 | 10/1/1999 | P | CANC |
Rick Jackson
|
|
|
Harry Allen ###-#### Double entry
|
FIRE-Final Inspection | 9/21/1999 | 9/22/1999 | 9/22/1999 | P | FAIL |
Rick Jackson
|
|
|
forest ###-#### Sprinkler rough-in inspection- need spare head box; test alarms; repair leaking head; hydro test FDC
|
INSP-Supply line flush | 5/21/1999 | 5/21/1999 | 5/21/1999 | P | PASS |
Rick Jackson
|
|
|
underground okay
|
INSP - Framing/Rough-in | 4/27/1999 | 4/28/1999 | 4/28/1999 | A | FAIL |
Wes Worcester
|
|
|
04/28/99 342 - Scheduled by Hello!. Contact phone is [4264998]. unable
|
INSP - Framing/Rough-in | 3/30/1999 | 3/31/1999 | 3/31/1999 | A | PART |
Wes Worcester
|
|
|
03/31/99 342 - Scheduled by Hello!. repkace screws at door jambs, ck th
|
Fee Review-notes | 11/2/1998 | | 3/23/1999 | | |
|
|
|
|
INSP-Conference | 3/8/1999 | 3/8/1999 | 3/8/1999 | A | PART |
Rick Jackson
|
|
|
with gen and 301 - reviewed plans and walk through of site
|
INSP - Foundation | 2/5/1999 | 2/5/1999 | 2/5/1999 | | PASS |
Jim Storey
|
|
|
/ / 301 - REVIEWED SPECIAL INSP REPORT AND ARCHOIVED TO CITY.
|
INSP - Foundation | 10/7/1998 | 10/8/1998 | 10/8/1998 | A | PART |
Russ Owen
|
|
|
10/08/98 407 - stell in place looks good ,special insp required.
|
INSP - Foundation | 9/23/1998 | 9/24/1998 | 9/24/1998 | A | PART |
Wes Worcester
|
|
|
09/24/98 342 - poured, special inspector had already left 3898612].
|
INSP - Foundation | 9/17/1998 | 9/17/1998 | 9/17/1998 | | PART |
Jim Storey
|
|
|
/ / 301 - FTG -OK FOOTING 1-7 grid a, d.8 line special insp. on site pending repor
|
INSP - Foundation | 9/17/1998 | 9/17/1998 | 9/17/1998 | P | CANC |
Russ Owen
|
|
|
09/17/98 407 - trans to 301.Hello!. Contact phone is [3898612].
|
(F) Reprint permit | | | 8/26/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/25/1998 | | |
|
|
|
|
Print Occupancy Form | | | 8/21/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/21/1998 | | |
|
|
|
|
Plan assigned to (MLO) | 5/12/1998 | | 8/21/1998 | | PASS |
Mike Otto
|
|
|
|
Plan Reviewer's activity | | | 8/18/1998 | | PEND |
|
|
|
REFAXED SOILS REPORT BACK TO KEITH JONES FOR REVIEW OF ROOF DRAINAGE UNDER FOUNDATION. MLO
|
Routing - PUBLIC WORKS | 8/11/1998 | | 8/12/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/7/1998 | | |
|
|
|
RECEIVED 2 COPIES OF SITE PLAN SHEET A1.1 AND ONE COPY OF LETTER FROM JERRY LOWE. ROUTED TO MIKE O.
|
Plan resubmittals received | | | 8/7/1998 | | PEND |
|
|
|
RECEIVED REVSIED SITE PLANS. MLO
|
Routing - PLAN CHECK | 8/4/1998 | | 8/6/1998 | | PASS |
|
|
|
|
Meeting | | | 8/6/1998 | | PEND |
|
|
|
MET WITH ARCHITECT AND HAD PLANS REDLINED AND SIGNED BY ARCHITECT. MLO
|
Plan resubmittals requested | | | 8/6/1998 | | PEND |
|
|
|
REQUESTED ARCHITECT TO PROVIDE REVISED SITE PLAN. MLO
|
Meeting | | | 8/5/1998 | | PEND |
|
|
|
MET WITH JERRY LOWE REGARDING INCOMPLETE CORRECTIONS ON PLANS RECEIVED 8-4-98. MLO
|
Plan resubmittals received | | | 8/4/1998 | | PEND |
|
|
|
RESPONCE TO INTIAL PLAN REVIEW. MLO
|
Plan resubmittals received | | | 8/3/1998 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED SHEETS A0.4, CA2.1, CA2.2, CA3.1, CA9.1, CA10.2, CM1.1, CM2.1, CM2.2, CM3.1, CE2.1, CE3.1, CE3.2,. ONE COPY OF RESPONES TO CORRECTION ITEMS. ROUTED TO MIKE O.
|
Meeting | | | 7/15/1998 | | PEND |
|
|
|
MET WITH TWO ARCHITECTS AND FOUR MECHANCIAL ENGINEERS FROM CSHQA REGARDING PLAN REVIEW COMMENTS. MLO
|
Routing Off Site - STRUCTURAL | 7/7/1998 | | 7/15/1998 | | PASS |
|
|
|
RECEIVED THREE ADDITIOANL COMMENTS BUT NO FURTHER REVIEW REQURIED BY K. JONES. MLO
|
Routing - PLAN CHECK | 7/7/1998 | | 7/10/1998 | | FAIL |
|
|
|
|
Plan resubmittals requested | | | 7/10/1998 | | FAIL |
|
|
|
CORRECTIONS GIVEN TO ARHCITECT IN MEETING AT THE BUILDING DEPT. MLO
|
Plan resubmittals received | | | 7/8/1998 | | PEND |
|
|
|
RECEIVED CHEMICAL REPORT FROM ARCHITECT.
|
Plan resubmittals received | | | 7/7/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM CSHQA, FORWARDED SAME TO MIKE OTTO.
|
Plan resubmittals received | | | 7/6/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS AT 5PM 7/2/98, LOGGED IN AT 0800AM 07/06/98, FORWARDED SAME TO MIKE OTTO.
|
Plan Review Completed(1st rev) | | | 6/17/1998 | | FAIL |
|
|
|
delayed 3 days in fire - no reviewer not all agencies approved
|
Routing - FIRE | 6/8/1998 | | 6/17/1998 | | PASS |
|
|
|
fire alarm plans req'd, HMMP required
|
Plan resubmittals requested | | | 6/8/1998 | | FAIL |
|
|
|
CORRECTIONS MAILED AND FAXED TO ARCHITECT. MLO
|
Routing - PLAN CHECK | 6/3/1998 | | 6/8/1998 | | FAIL |
|
|
|
|
Routing - PLUMBING | 5/28/1998 | | 6/3/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 5/14/1998 | | 5/28/1998 | | FAIL |
|
|
|
NEEDS DRAINAGE PLAN REVISION AND EASEMENTS.
|
Routing Off Site - STRUCTURAL | 5/11/1998 | | 5/26/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 5/12/1998 | | 5/13/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/12/1998 | | PEND |
|
|
|
|
Application received | | | 5/7/1998 | | |
|
|
|
|