INSP-Final Inspection | 2/11/1999 | 2/11/1999 | 2/11/1999 | | CANC |
Joe Tawney
|
|
|
02/11/99 406 - brian ###-#### CANCEL WRONG PERMIT NUMBER ENTERED
|
CHANGE STATUS TO (I) | | | 11/30/1998 | | |
|
|
|
|
Receive PAYMENT IN FULL | | | 11/4/1998 | | |
|
|
|
|
INSP - Final | 8/14/1998 | 8/14/1998 | 8/14/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
Code Occupancy Approval | | | 7/27/1998 | | PASS |
|
|
|
Site inspection for Final - Complies with req. of DRH98-0072
|
INSP - Final | 7/24/1998 | 7/24/1998 | 7/24/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC BLDG NMBRS SUPRV PIV VALVE
|
INSP-Final Inspection | 7/8/1998 | 7/9/1998 | 7/9/1998 | P | FAIL |
Joe Tawney
|
|
|
07/09/98 406 - ###-####/ jeff FINAL NOT READY AND FAIL ON ALARM SYSTEM
|
INSP - Framing/Rough-in | 7/7/1998 | 7/8/1998 | 7/9/1998 | A | PART |
Tom Arcoraci
|
|
|
07/08/98 408 - Mike ###-#### 1045 relocatable RAMPS AND STAIRS OK NEED HAND RAILS
|
INSP-Final Inspection | 6/30/1998 | 6/30/1998 | 7/1/1998 | P | PART |
Joe Tawney
|
|
|
07/01/98 406 - jeff packhum ###-#### just call before you go out OK ON SPKLR ROUGH IN AND HYDRO TEST
|
Received partial PAYMENT | | | 6/29/1998 | | |
|
|
|
|
INSP - Framing/Rough-in | 6/19/1998 | 6/22/1998 | 6/22/1998 | A | PART |
Tom Arcoraci
|
|
|
06/22/98 408 - dave rymer ###-#### bld 7 west HOLD DOWNS OK
|
INSP - Framing/Rough-in | 6/16/1998 | 6/16/1998 | 6/16/1998 | P | PART |
Jim Sly
|
|
|
06/16/98 316 - ceiling inspection OK.....Need to call in after draft sto installation...
|
(F) Reprint permit | | | 6/12/1998 | | |
|
|
|
|
Issue & PRINT FEE-DUE permit | | | 6/11/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 6/9/1998 | | 6/10/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 6/10/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 6/10/1998 | | |
|
|
|
|
Plan assigned to (ADS) | 5/20/1998 | | 6/10/1998 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 6/9/1998 | | PART |
|
|
|
UBC plan check not approved, delayed in fire 4 days, no back-up
|
Routing - FIRE | 5/28/1998 | | 6/9/1998 | | PASS |
|
|
|
sprinklers for area increase - concealed spaces?, check FDC distance to Hydrant, outside control valve, monitoring
|
Routing - PLAN CHECK | 5/26/1998 | | 5/28/1998 | | FAIL |
|
|
|
Initial plan review report faxed to architect.
|
Routing - PUBLIC WORKS | 5/21/1998 | | 5/22/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 5/21/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLANNING, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 5/13/1998 | | 5/20/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/20/1998 | | PEND |
|
|
|
RECEIVED SSTRUCTURAL CALCULATIONS AND SERIAL NUMBERS FROM SAM BURROWS. BEGAN PROCESSING PLANS. DAR
|
Plans ACCEPTED BY PLAN CHECK | | | 5/13/1998 | | HOLD |
|
|
|
PERMIT ON HOLD UNTIL WE RECEIVE SERIAL NUMBERS OF UNITS AND STRUCTURAL CALCULATIONS FROM SAM BURROWS.
|
Issue & PRINT FEE-DUE permit | | | 5/13/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/13/1998 | | PEND |
|
|
|
|
Application received | | | 5/13/1998 | | |
|
|
|
|
Routing - PLANNING | 5/22/1998 | | 5/26/1909 | | PASS |
|
|
|
plans approved. Structures are existing; new ramps and roof covers okay for P & Z.
|