Permanent occupancy | | | 7/31/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7334 issued 7-30-98 to Kiddie Kandids at Boise Towne Square.
|
INSP - Final | 7/30/1998 | 7/30/1998 | 7/30/1998 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REISP OK FOR PERM OCC
|
INSP-Final Inspection | 7/30/1998 | 7/30/1998 | 7/30/1998 | | FAIL |
Joe Tawney
|
|
|
07/29/98 406 - matt ###-#### reinspection 2329 REINSP FAIL SMOKE DETECTOR FAILED TO SHUT DOWN AHU
|
INSP-Final Inspection | 7/27/1998 | 7/28/1998 | 7/28/1998 | P | NR |
Joe Tawney
|
|
|
07/28/98 406 - Scheduled by Hello!. Contact phone is [3225007]. NOT READY CONTR TRIED TO CANCEL INSPECTION
|
INSP - Final | 7/27/1998 | 7/28/1998 | 7/28/1998 | P | CANC |
|
|
|
07/27/98 338 - canc by ctr door does not work
|
INSP - Final | 7/24/1998 | 7/24/1998 | 7/24/1998 | P | FAIL |
|
|
|
07/24/98 338 - FIRE LIFE SAFETY AND ETC. MUST RECALLA TER THE FIRE INSP
|
INSP-Final Inspection | 7/23/1998 | 7/24/1998 | 7/24/1998 | P | FAIL |
Joe Tawney
|
|
|
07/24/98 406 - Scheduled by Hello!. Contact phone is [3225007]. FINAL FAIL DOOR HDWRE SMOKE DETECTOR FIRE EXT
|
INSP - Framing/Rough-in | 7/9/1998 | 7/10/1998 | 7/10/1998 | A | PART |
|
|
|
07/10/98 338 - CFRM-OK CEILING FRAMING
|
INSP - Wall cover | 6/30/1998 | 7/1/1998 | 7/2/1998 | A | PART |
|
|
|
ALSO DONE BY 342
|
INSP - Framing/Rough-in | 6/30/1998 | 7/1/1998 | 7/1/1998 | A | NR |
Wes Worcester
|
|
|
07/01/98 342 - Frank ###-#### postpone to 2 or 3 pm
|
INSP - Framing/Rough-in | 7/1/1998 | 7/1/1998 | 7/1/1998 | | PASS |
Wes Worcester
|
|
|
/ / 342 - 2-3pm
|
INSP - Wall cover | 6/29/1998 | 6/30/1998 | 6/30/1998 | P | PART |
|
|
|
06/30/98 338 - MAD EOK FOR THE FIRE CAULKING
|
INSP - Framing/Rough-in | 6/29/1998 | 6/30/1998 | 6/30/1998 | P | PART |
|
|
|
06/30/98 338 - PART MADE OK FOR THE FIRE CAULKING
|
INSP - Wall cover | 6/25/1998 | 6/26/1998 | 6/26/1998 | A | PART |
Carl Dependahl
|
|
|
scheduled by Hello!. Contact phone is [3225007]. First thing in the morning. per ba....OK TO COVER INT PARTITIONS STILL NEED INSP STORE FRONT PER DETAILS
|
INSP - Framing/Rough-in | 6/23/1998 | 6/24/1998 | 6/24/1998 | P | PART |
Carl Dependahl
|
|
|
06/24/98 340 - Scheduled by Hello!. Contact phone is [3225007]. not complete insp; seal 1 box on demising wall; keep c/n. "secondary wal inside tenant wall ok to cover 1 side only as per elec. insp. still need detail for storefront
|
INSP - Framing/Rough-in | 6/23/1998 | 6/23/1998 | 6/23/1998 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - c/n, no elec, need detail for support at store front per pla complete framing...soffits, hard lid, etc. Do not cover.
|
Plan resubmittals received | | | 6/12/1998 | | |
|
|
|
RECEIVED 3 SETS OF REVISED SHEETS ONLY AND ROUTED TO DAN S.
|
Issue PAID IN FULL permit | | | 6/9/1998 | | |
|
|
|
|
Telephone call | | | 6/8/1998 | | |
|
|
|
CALLED JEFF PERMIT READY ###-####
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/8/1998 | | PASS |
|
|
|
Approved based on conditions noted to architect.
|
Inspection Record Card- Bld | | | 6/8/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 6/8/1998 | | 6/8/1998 | | PASS |
|
|
|
Received plans back from Fire Dept. Processing for issuance - to receive submittals from architect prior to frame inspection approval.
|
Plan Review Completed(1st rev) | | | 6/8/1998 | | PASS |
|
|
|
held 3 days waiting for F_V, no back-up for plan review
|
Print Occupancy Form | | | 6/8/1998 | | |
|
|
|
|
Plan assigned to (DRS) | 5/15/1998 | | 6/8/1998 | | PASS |
Dan Stuart
|
|
|
06/08/98 16:00:48 DRS - this action updated by action script from <<>> in Case No. BLD98-1372
|
Routing - FIRE | 6/3/1998 | | 6/8/1998 | | PASS |
|
|
|
concealed spaces behind curved walls - no combustibles or sprinkle
|
Routing - PLAN CHECK | 5/29/1998 | | 6/3/1998 | | PEND |
|
|
|
Completed initial plan review. Comments sent by FAX to Loralee Chase & copy mailed. Routing plans to Fire Dept. for review.
|
Print Pending Permit.LaserJet4 | | | 6/3/1998 | | PEND |
|
|
|
Routing to fire dept.
|
Print Pending Permit.LaserJet4 | | | 6/3/1998 | | PEND |
|
|
|
Routing to fire dept.
|
Plan Reviewer's activity | | | 6/3/1998 | | |
|
|
|
Completed plan review. Corrections are required. As an effort to help the issuance of permits move along, the response to the items in question are to be submitted for review and approval prior to the call for framing inspection. This allows the contractor to prepare in areas not in question or to proceed at his own risk until answers are received & approved. This will be pointed out to the contractor verbally and is included in the plan review comments cover letter which is attached as a part of the approved plans plan review. If this is not agreeable to the involved parties the plans will be held.
|
Routing - PLAN CHECK | 5/18/1998 | | 5/29/1998 | | PEND |
|
|
|
Picked up plans to beginn review.
|
Routing - PUBLIC WORKS | 5/15/1998 | | 5/18/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/15/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 5/14/1998 | | 5/15/1998 | | |
Marlene Southard
|
|
|
|
Application received | | | 5/14/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/14/1998 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 6/8/1998 | | | | |
|
|
|
|