INSP - Framing/Rough-in | 9/24/1998 | 9/24/1998 | 9/25/2009 | P | PART |
|
|
|
09/25/98 338 - made ok to cover except at the plmg walls ok to cover the
|
INSP-Final Inspection | 10/29/1998 | 10/30/1998 | 10/30/1998 | P | PASS |
|
|
|
TERRY DIGITAL PAGER 1-###-#### detectors tested
|
Permanent Occupancy | | 10/30/1998 | 10/30/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 10/30/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7477 issued 10-30-98 to the Finish Line.
|
INSP-Final Inspection | 10/21/1998 | 10/22/1998 | 10/23/1998 | P | PART |
Joe Tawney
|
|
|
10/22/98 406 - TERRY ###-#### FINAL OK FOR TEMP OCC DUCT DET TO BE SUPERVISED BY MALL PANEL
|
INSP - Final | 10/21/1998 | 10/22/1998 | 10/22/1998 | P | PART |
|
|
|
10/22/98 338 - ok for temp signed by 406
|
INSP-Final Inspection | 10/16/1998 | 10/19/1998 | 10/19/1998 | P | CANC |
Joe Tawney
|
|
|
10/19/98 406 - terry- 1-###-#### digital pager fn insp CANCELLED
|
INSP - Final | 10/16/1998 | 10/19/1998 | 10/19/1998 | P | CANC |
|
|
|
10/19/98 338 - cancelled by terry
|
INSP - Wall cover | 10/5/1998 | 10/8/1998 | 10/9/1998 | A | PART |
|
|
|
10/08/98 338 - made framing on thr racking system
|
INSP-Sprinkler Rough-in/Hydro | 10/5/1998 | 10/8/1998 | 10/9/1998 | A | CANC |
Joe Tawney
|
|
|
10/08/98 406 - Scheduled by Hello!. Contact phone is [3234940]. CANCELLED
|
INSP-Sprinkler Rough-in/Hydro | 10/5/1998 | 10/7/1998 | 10/7/1998 | A | PART |
Joe Tawney
|
|
|
10/07/98 406 - TERRY 1-###-#### PAGER SPKLR ROUGH IN OK EXC ADD ONE HEAD UNDER DUCT IN CORRIDOR
|
INSP - Energy code compliance | 10/5/1998 | 10/7/1998 | 10/7/1998 | A | PART |
|
|
|
10/07/98 338 - MADE OK FOR START OF SHELVING
|
INSP - Concrete | 10/5/1998 | 10/7/1998 | 10/7/1998 | A | PASS |
|
|
|
10/07/98 338 - MADE OK FOR CORE DRILLING PATCHES
|
INSP-Sprinkler Rough-in/Hydro | 10/1/1998 | 10/2/1998 | 10/2/1998 | A | FAIL |
Rick Jackson
|
|
|
terry ###-####pager overspaced heads in sales and storage rooms; hanger on head in sales; obstructions over 4ft require heads
|
INSP-Final Inspection | 10/1/1998 | 10/2/1998 | 10/2/1998 | A | NR |
Rick Jackson
|
|
|
terry ###-#### this inspection added as a mistake
|
Plan resubmittals received | | | 10/1/1998 | | PASS |
|
|
|
RECEIVED ONE COPY OF DETAIL OF SHELVING UNIT TO BE ATTACHED TO FLOOR. REVISED PER EARLIER DETAILS SENT. ROUTED TO. PERRY PAINE
|
INSP - Foundation | 9/18/1998 | 9/18/1998 | 9/18/1998 | P | PASS |
|
|
|
09/18/98 338 - terry 1-###-#### demolition insp. conference to chec
|
Issue PAID IN FULL permit | | | 9/2/1998 | | |
|
|
|
|
Telephone call | | | 8/31/1998 | | PASS |
|
|
|
LEFT MESS AT 1-###-#### FOR TERRY THAT PLANS ARE READY
|
Print Occupancy Form | | | 8/31/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 8/31/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/1998 | | PASS |
|
|
|
Approved per attachments & notes.
|
Routing - PLAN CHECK | 6/29/1998 | | 8/28/1998 | | PASS |
|
|
|
Received resubmittals from architect in response to plan review comments.
|
Plan resubmittals received | | | 8/28/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/28/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/28/1998 | | |
|
|
|
RECEIVED REVISED STRUCT. CALCS. AND SHEETS G-1, G-2, G-3, G-4, A-1, A-1A, A-2, A-3, A-4, A-4A, A-5, A-6, M-1, M-2, E-1, E-2, E-3,. ROUTED TO DAN STUART. KMM
|
Plan assigned to (DRS) | 5/28/1998 | | 8/28/1998 | | PASS |
Dan Stuart
|
|
|
08/28/98 16:58:15 DRS - this action updated by action script from <<>> in Case No. BLD98-1439
|
Plan Review Completed(1st rev) | | | 6/26/1998 | | PASS |
|
|
|
DRS has conditions to be met prior to covering framing
|
Routing - FIRE | 6/25/1998 | | 6/26/1998 | | PASS |
|
|
|
as noted on plans - no report
|
Print Pending Permit.LaserJet4 | | | 6/25/1998 | | PEND |
|
|
|
|
Routing - PLAN CHECK | 6/19/1998 | | 6/25/1998 | | |
|
|
|
Completed review. Copied comments and corrections to architect for response. Will issue permit when fire department completed plan review with condition that the framing inspection will not be approved until architect has supplied required details for storefron support & the support for water heater if being installed above toilet room.
|
Routing - PLAN CHECK | 5/29/1998 | | 6/19/1998 | | |
|
|
|
picked up plan to start review.
|
Plan assigned to (MYS) | 5/21/1998 | | 5/28/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/28/1998 | | PEND |
|
|
|
|
Routing - PUBLIC WORKS | 5/28/1998 | | 5/28/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/21/1998 | | PASS |
|
|
|
|
Application received | | | 5/21/1998 | | |
|
|
|
|