90 day tracking............. | | 5/26/1998 | 8/24/1998 | | |
|
|
|
|
Permanent Occupancy | | 7/24/1998 | 7/24/1998 | | DONE |
|
|
|
|
Permanent occupancy | | | 7/24/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7328 issued 7-24-98 to Harbor Freight.
|
INSP - Final | 7/22/1998 | 7/23/1998 | 7/23/1998 | A | PASS |
Tom Arcoraci
|
|
|
07/23/98 408 - scott ###-#### call before you go out
|
INSP-Final Inspection | 7/22/1998 | 7/22/1998 | 7/22/1998 | P | PASS |
Joe Tawney
|
|
|
07/22/98 406 - final/ scott ###-#### call before going REINSP OK FOR PERM OCC
|
INSP - Final | 7/10/1998 | 7/13/1998 | 7/13/1998 | A | NR |
Tom Arcoraci
|
|
|
07/13/98 408 - ###-####
|
INSP-Final Inspection | 7/10/1998 | 7/10/1998 | 7/10/1998 | P | FAIL |
Joe Tawney
|
|
|
07/10/98 406 - dennis ###-#### FINAL FAIL EXIT DOORS EXIT LIGHTS EMERG LIGHTS
|
INSP - Framing/Rough-in | 6/29/1998 | 6/30/1998 | 6/30/1998 | A | FAIL |
Tom Arcoraci
|
|
|
06/30/98 408 - demising wall, grid ceiling./ ###-####
|
INSP - Framing/Rough-in | 6/12/1998 | 6/15/1998 | 6/15/1998 | A | PASS |
Tom Arcoraci
|
|
|
06/15/98 408 - FRAMING/ DENNIS ###-####
|
Print Occupancy Form | | | 6/10/1998 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 6/10/1998 | | |
|
|
|
|
Telephone call | | | 6/10/1998 | | PASS |
|
|
|
RICK TOEWS ###-####
|
Inspection Record Card- Bld | | | 6/10/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/10/1998 | | PASS |
|
|
|
|
Plan assigned to (CJW) | 6/2/1998 | | 6/9/1998 | | PASS |
Carl Westfall
|
|
|
06/09/98 16:34:58 CJW - this action updated by action script from <<>> in Case No. BLD98-1445
|
Plan Review Completed(1st rev) | | | 6/8/1998 | | PASS |
|
|
|
approval delayed 3 days - no back-up plan review
|
Routing - FIRE | 6/3/1998 | | 6/8/1998 | | PASS |
|
|
|
exit hardware and sprinklers.....no storage or display over 12 ft.
|
testing condition printout | | | 6/3/1998 | | |
|
|
|
|
Print permit w/o conditions | | | 6/3/1998 | | |
|
|
|
|
Plan assigned to (MYS) | 5/22/1998 | | 6/2/1998 | | |
Marlene Southard
|
|
|
|
Plan routing begun/TENANTS | | | 6/2/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plan Reviewer's activity | | | 6/2/1998 | | PASS |
|
|
|
UBC plan review started June 2, 1998 and finished June 3, 1998. Drawings were approved subject to the conditions of the plan review report that was attached to the approved drawings.
|
Routing - PUBLIC WORKS | 5/26/1998 | | 5/27/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 5/26/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/26/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/26/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 5/22/1998 | | |
|
|
|
|
Application received | | | 5/21/1998 | | |
|
|
|
|
Plan Review Report | | | | | |
|
|
|
|
Routing - PLAN CHECK | 6/8/1998 | | | | |
|
|
|
|