Permanent Occupancy | | 8/30/1999 | 8/30/1999 | | DONE |
|
|
|
|
INSP - Final | 8/27/1999 | 8/30/1999 | 8/30/1999 | A | PASS |
Carl Dependahl
|
|
|
08/30/99 340 - Carl, I have a ltr. from Ronald Roberts re: this project. Call me for details, thanks - Cathy (Gary - ###-####)
|
Permanent occupancy | | | 8/30/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7876 issued 8-30-99 to "On the Border Cafe" at the Boise Spectrum.
|
CHANGE STATUS TO (I) | | | 8/27/1999 | | PASS |
|
|
|
aud fees paid
|
Receive PAYMENT IN FULL | | | 7/19/1999 | | |
|
|
|
|
CHANGE STATUS TO (F) | | | 4/9/1999 | | FEES |
|
|
|
FEES DUE ADDITIONAL VALUE FROM SUBS
|
INSP - Final | 4/6/1999 | 4/6/1999 | 4/6/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP - Final | 4/2/1999 | 4/2/1999 | 4/2/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - HAS T/O, KEEP C/N; CONF W/ SUPT.
|
INSP-Final Inspection | 3/30/1999 | 3/31/1999 | 3/31/1999 | A | FAIL |
Joe Tawney
|
|
|
03/31/99 406 - REINSP FAIL ALARM PANEL DOOR DROP OUT
|
Fee Review-notes | 12/18/1998 | | 3/28/1999 | | |
|
|
|
|
INSP-Alarm Testing | 3/26/1999 | 3/26/1999 | 3/26/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ALARM SYSTEM PASS
|
INSP-Final Inspection | 3/22/1999 | 3/23/1999 | 3/23/1999 | A | FAIL |
Joe Tawney
|
|
|
03/23/99 406 - REINSP FAIL ALARM SIG, ACCESS CONTOL, SPKLR PROTECTION
|
Temporary occupancy | | | 3/17/1999 | | PASS |
|
|
|
Temp. Occ. Cert. #3795 issued 3-17-99 to "On The Border" restaurant.
|
INSP - Final | 3/12/1999 | 3/12/1999 | 3/12/1999 | P | FAIL |
Carl Dependahl
|
|
|
03/12/99 340 - Scheduled by Hello!. Contact phone is [8632924]. need other finals, finish roof; ok for t/o, card to cont...make copy of
|
INSP-Alarm Testing | 3/11/1999 | 3/11/1999 | 3/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - ALARM & SPKLR TEST OK
|
INSP-Alarm Testing | 3/11/1999 | 3/11/1999 | 3/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - ALARM & SPKLR TEST OK
|
INSP-Alarm Testing | 3/11/1999 | 3/11/1999 | 3/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - ALARM & SPKLR TEST OK
|
Code Occupancy Approval | | | 3/11/1999 | | PASS |
|
|
|
Bond Posted for $33,000.00 - still need part. undergrd. sprklr system, landscaping, bike rack and above-grade h/c signs (6). CAM EVERYTHING IS IN NOW - MEETS COMPLIANCE W/ DRH98-0031
|
INSP-Sprinkler Rough-in/Hydro | 3/9/1999 | 3/9/1999 | 3/9/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ABOVE GROUND HYDRO TEST
|
INSP - Wall cover | 2/17/1999 | 2/18/1999 | 2/18/1999 | P | CANC |
Russ Owen
|
|
|
02/18/99 407 - to many inspections to get to,will try later.
|
INSP - Wall cover | 2/12/1999 | 2/12/1999 | 2/12/1999 | | FAIL |
Carl Dependahl
|
|
|
02/12/99 340 - Scheduled by Hello!. Contact phone is [8632924]. c/n, su facing at attic, fireblock...etc...no further cover
|
INSP-Supply line flush | 2/9/1999 | 2/9/1999 | 2/9/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SUPPLY LINE FLUSH
|
INSP-Sprinkler Rough-in/Hydro | 1/22/1999 | 1/22/1999 | 1/22/1999 | | FAIL |
Joe Tawney
|
|
|
/ / 406 - SPKLR ROUGH IN UPRITHT HDS & PIPING FAIL OVER SPACE IN DININ INCOMPL
|
INSP - Framing/Rough-in | 1/6/1999 | 1/6/1999 | 1/12/1999 | P | PART |
|
|
|
01/06/99 338 - madeok to insulate
|
INSP - Framing/Rough-in | 12/21/1998 | 12/22/1998 | 12/22/1998 | A | PART |
|
|
|
12/22/98 338 - made ok for roof nailing only
|
Issue PAID IN FULL permit | | | 10/21/1998 | | |
|
|
|
|
Print Occupancy Form | | | 10/19/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 10/12/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 10/12/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 5/29/1998 | | 10/12/1998 | | PASS |
Mike Phillips
|
|
|
10/12/98 09:25:05 M_P - this action updated by action script from <<>> in Case No. BLD98-1449
|
Routing - PUBLIC WORKS | 10/8/1998 | | 10/9/1998 | | PASS |
|
|
|
Routing to P.W. for further review seating copacity has increased. nO ADDITIONAL FEES REQUIRED PER LOUISE.
|
Plan Reviewer's activity | | | 10/8/1998 | | PEND |
|
|
|
Sending back to P.W. for further review. Seating capacity has increased.
|
Plan resubmittals received | | | 9/30/1998 | | PASS |
|
|
|
RECEIVED REVISED KITCHEN DRAWINGS TAKEN TO MIKE P.
|
Plan resubmittals received | | | 9/28/1998 | | |
|
|
|
two current sets of revised drawings,one current response letter to building comments, one current responce letter to Fire Dept comments,
|
INSP - Foundation | 9/14/1998 | 9/15/1998 | 9/14/1998 | A | FAIL |
|
|
|
09/15/98 338 - ROD ###-#### INSP FT & REBAR this per mit is not issued n
|
Plan Review Completed(1st rev) | | | 9/8/1998 | | FAIL |
|
|
|
UBC issues
|
Routing - FIRE | 9/3/1998 | | 9/6/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/2/1998 | | FAIL |
|
|
|
Sent correction report.
|
Plan resubmittals requested | | | 9/2/1998 | | FAIL |
|
|
|
Requested additional information.
|
Print Pending Permit.LaserJet4 | | | 9/2/1998 | | FAIL |
|
|
|
REQUESTED ADDITIONAL INFORMATION TO BE SUBMITTED FOR REVIEW.
|
Routing - PUBLIC WORKS | 8/31/1998 | | 8/31/1998 | | PASS |
|
|
|
|
Routing - PLUMBING | 8/12/1998 | | 8/14/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 8/12/1998 | | PASS |
|
|
|
RECEIVED REVISED CERT. OF VALUE.
|
Application received | | | 8/12/1998 | | |
|
|
|
RECEIVED A LETTER REQUESTING AN EARLY FOUNDATION PERMIT. ROUTED TO MIKE P.
|
Routing - PLANNING | 8/7/1998 | | 8/12/1998 | | PASS |
|
|
|
approved per DRH98-0031/
|
Routing - PUBLIC WORKS | 8/4/1998 | | 8/7/1998 | | PASS |
|
|
|
|
Routing Off Site - C.D.H | 6/1/1998 | | 8/3/1998 | | PASS |
|
|
|
CONTACTED TAMARA ROGERS AT ###-#### TO TAKE PLANS OUT TO CDH. SENT BOTH COPIES ( OFFICE AND ISSUE )
|
Telephone call | | | 7/8/1998 | | |
|
|
|
Phoned and talked to Doug Cobb about CDH requirements. He said he has been tring to get a hold of Bud Fullerton at CDH for sometime. He will try again.
|
Plan Reviewer's activity | | | 6/4/1998 | | |
|
|
|
Review complete waiting for package plans to return from routing to review for uniformity and then send review comments to Architect.
|
Plan routing begun/NEW & ADDTN | | | 6/1/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 5/21/1998 | | 5/29/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 5/29/1998 | | PASS |
|
|
|
|
Received Certificate of Value | | | 5/29/1998 | | PEND |
|
|
|
CALLED TAMARUA ROGERS AT ###-#### TO LET HER KNOW THAT CERT. OF VALUE NEEDS TO BE SIGNED.
|
Recd Pcfee & Taken To Pln CK | | | 5/21/1998 | | PASS |
|
|
|
|
Application received | | | 5/21/1998 | | |
|
|
|
THIS WAS TAKEN IN BY PAT E. RITA WAS ON BREAK.
|