Permanent Occupancy | | 8/14/1998 | 8/14/1998 | | DONE |
|
|
|
|
INSP-Alarm Testing | 8/11/1998 | 8/14/1998 | 8/14/1998 | A | PASS |
Joe Tawney
|
|
|
08/14/98 406 - Scheduled by Hello!. Contact phone is [3767579]. REINSP OK FOR PERM OCC
|
INSP - Final | 8/13/1998 | 8/14/1998 | 8/14/1998 | A | PASS |
|
|
|
08/14/98 338 - done and signed by 406
|
Permanent occupancy | | | 8/14/1998 | | PASS |
|
|
|
Perm. Occ. Cert. #7347 issued 8-14-98 to Third Dimension Cuts.
|
INSP - Framing/Rough-in | 8/7/1998 | 8/10/1998 | 8/11/1998 | A | PART |
|
|
|
08/10/98 338 - madeok to drop in tiles need to secure the air diffusers
|
INSP-Final Inspection | 8/6/1998 | 8/7/1998 | 8/7/1998 | P | FAIL |
|
|
|
DOUG ###-#### NUMERICAL PAGER Not ready electrical not done, mech wrong for smoke evac , ceiling not in lights not in correction list left - smoke detector too close to diffuser - no one there to test, 1 sprinkler head wrong
|
INSP - Framing/Rough-in | 7/22/1998 | 7/22/1998 | 7/23/1998 | P | PART |
|
|
|
07/22/98 338 - CHUCK ###-#### made ok to cover 1 side on ele and plmg wa
|
INSP - Conference | 7/22/1998 | 7/22/1998 | 7/22/1998 | | PASS |
Alan Hauser
|
|
|
/ / 350 - had hvac contractor get permit
|
Issue PAID IN FULL permit | | | 7/14/1998 | | |
|
|
|
|
Routing - FIRE | 7/10/1998 | | 7/10/1998 | | PASS |
|
|
|
|
Plan assigned to (DRS) | 6/17/1998 | | 7/10/1998 | | PASS |
Dan Stuart
|
|
|
07/10/98 13:13:47 DRS - this action updated by action script from <<>> in Case No. BLD98-1526
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/10/1998 | | PASS |
|
|
|
|
Telephone call | | | 7/10/1998 | | |
|
|
|
CALLED PATRICIA AT THIRD DIMENSION PERMIT READY
|
Inspection Record Card- Bld | | | 7/10/1998 | | |
|
|
|
|
Print Occupancy Form | | | 7/10/1998 | | |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/10/1998 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 7/10/1998 | | 7/10/1998 | | PASS |
|
|
|
Routing to front desk to process for issuance of permit.
|
Routing - PLAN CHECK | 6/18/1998 | | 7/9/1998 | | PEND |
|
|
|
Picked up plan to begin plan review
|
Routing - PLAN CHECK | 7/9/1998 | | 7/9/1998 | | PASS |
|
|
|
Completed plan review. Comments to architect for response or clarification to structural inspector at site. No response required to plan review. Routing to Fire Dept. Will process for ermit issuance when approved by fire dept..
|
Print Pending Permit.LaserJet4 | | | 7/9/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/17/1998 | | 6/18/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 6/17/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 6/1/1998 | | 6/17/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 6/12/1998 | | PASS |
|
|
|
RECEIVED STAMPED AND SIGNED PLANS. ROUTED TO MARLENE
|
Plans ACCEPTED BY PLAN CHECK | | | 6/3/1998 | | FAIL |
|
|
|
PLANS NOT STAMPED OR SIGNED BY ARCH. OR ENG.. CONTACTED RON WOLFF AT ###-#### TO LET HIM KNOW OF THIS NEED. KMM
|
Received Certificate of Value | | | 6/1/1998 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/1/1998 | | |
|
|
|
|
Application received | | | 6/1/1998 | | |
|
|
|
|