Receive PAYMENT IN FULL | | | 8/20/1999 | | |
|
|
|
|
(F) Reprint permit | | | 4/26/1999 | | |
|
|
|
|
Fee Review-notes | 9/24/1998 | | 3/31/1999 | | DONE |
|
|
|
|
Permanent occupancy | | | 3/1/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7658 issued 3-1-99 to St. Al's Hospital for the information resources remodel and expansion area in basement.
|
INSP - Final | 2/25/1999 | 2/25/1999 | 2/25/1999 | P | PASS |
Carl Dependahl
|
|
|
02/25/99 340 - card to cont.
|
Permanent Occupancy | | 2/25/1999 | 2/25/1999 | | DONE |
|
|
|
|
INSP - Final | 2/23/1999 | 2/23/1999 | 2/24/1999 | P | NR |
Carl Dependahl
|
|
|
###-#### voice for Cecil please call first\\basement of Bosie Medical Arts center...unable to contact. GS may have this one??
|
INSP-Final Inspection | 2/18/1999 | 2/22/1999 | 2/23/1999 | P | PASS |
Joe Tawney
|
|
|
02/22/99 406 - ###-#### Cecil FINAL OK FOR CERT OF COMPLETION
|
INSP-Sprinkler Rough-in/Hydro | 9/16/1998 | 9/16/1998 | 9/16/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON SPKLR RI AND HYDRO TEST OF PREACTION SYSTEM IN BASEMEN
|
Inspection Record Card- Bld | | | 8/11/1998 | | |
|
|
|
|
Print Occupancy Form | | | 8/11/1998 | | |
|
|
|
|
Telephone call | | | 8/11/1998 | | PASS |
|
|
|
TALKED TO PAMELA AT ###-#### PLANS ARE READY
|
Issue PAID IN FULL permit | | | 8/11/1998 | | |
|
|
|
|
Plan assigned to (CJW) | 6/11/1998 | | 8/10/1998 | | PASS |
Carl Westfall
|
|
|
08/10/98 14:18:30 CJW - this action updated by action script from <<>> in Case No. BLD98-1609
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/1998 | | PASS |
|
|
|
|
Routing - FIRE | 8/10/1998 | | 8/10/1998 | | PASS |
|
|
|
|
testing condition printout | | | 8/10/1998 | | |
|
|
|
|
Print permit w/o conditions | | | 8/10/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/10/1998 | | PASS |
|
|
|
Drawings approved, with conditions, after resubmittal review.
|
Routing - PLAN CHECK | 7/6/1998 | | 8/10/1998 | | |
|
|
|
|
Plan resubmittals received | | | 8/7/1998 | | |
|
|
|
RECEIVED ONE COPY OF UNSIGNED REVISED SHEET A2.1, AND ONE RESPONSE LETTER. ROUTED TO CARL W.
|
Routing - FIRE | 6/29/1998 | | 7/2/1998 | | |
|
|
|
FM-200 substitution for sprinklers must be approved by the chief
|
Plan Review Completed(1st rev) | | | 7/2/1998 | | FAIL |
|
|
|
UBC and UFC issues
|
Plan Reviewer's activity | | | 6/23/1998 | | |
|
|
|
UBC plan review started June 23, 1998 and finished June 29, 1998. A response from the architect is required. See conditions list.
|
Routing - PUBLIC WORKS | 6/12/1998 | | 6/15/1998 | | PASS |
|
|
|
|
Plan routing begun/TENANTS | | | 6/11/1998 | | |
|
|
|
Route to PUBLIC WORKS, PLAN CHECK and FIRE.
|
Plan assigned to (MYS) | 6/8/1998 | | 6/11/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 6/8/1998 | | PASS |
|
|
|
|
Application received | | | 6/5/1998 | | |
|
|
|
|
Received Certificate of Value | | | 6/5/1998 | | PASS |
|
|
|
|