Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD98-01628
StatusFinaled
Name CITY OF BOISE
Site Address 1025 S CAPITOL BLVD
Project Name 
Customer Number 
ePlanReviewNo
Description
CITY OF BOISE HOUSING AND COMMUNITY DEVELOPMENT * TO CONVERT EXISTING MOTEL SUITES(BEDROOMS AND BATHS) LOCATED IN THE NORTHWEST WING, TO STORAGE ROOMS, CONFERENCE ROOM, HALLWAY AND FOUR OFFICES. WORK TO INCLUDE REMOVAL OF HOT TUBS & RESTROOM FIXTURES, INSTALL NEW NONBEARING WALLS, NEW DOORS TO BE ACCESSIBLE & INSTALL ACCESSIBLE DOOR HARDWARE, NEW SINK IN NEW COUNTER AT CONFERENCE ROOM AND SUSPENDED CEILING. TO PROVIDE NEW 6 FOOT OPENING IN WALL FOR EXITING PURPOSES OF THE BAR / RESTAURANT AREA TO ALLOW THE LOCK-UP OF THE HOUSING & DEVELOPMENT SERVICES OFFICES AFTER WORK DAY. ALL PER APPROVED PLANS WITH NOTES & ATTACHMENTS THERETO. PC#363-98/drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final3/9/20113/9/20113/9/2011PDONE
DetailsBob Archibald
Original scope of work never finaled. Scope of work under BLD10-02792 was a remodel of the same area and has had a final inspection.
Office final  3/9/2011 DONE
Fee Review-notes12/18/1998 3/31/1999
INSP - Framing/Rough-in6/16/19986/16/19986/16/1998PPASS
Details
06/16/98 333 - FRAM-OK FRAMING
Print Occupancy Form  6/12/1998
Inspection Record Card- Bld  6/12/1998
PLANS/APPL TAKEN TO FRONT DESK  6/12/1998 PASS
Issue PAID IN FULL permit  6/12/1998 PASS
paid under je781636215
Plan Review Completed(1st rev)  6/11/1998 PASS
Routing - PLAN CHECK6/11/1998 6/11/1998 PASS
RECEIVED PLAN BACK FROM P.W. PROCESSING FOR PERMIT ISSUANCE.
Plan assigned to (DRS)6/8/1998 6/11/1998 PASS
DetailsDan Stuart
06/11/98 18:36:15 DRS - this action updated by action script from <<>> in Case No. BLD98-1628
Routing - PUBLIC WORKS6/10/1998 6/11/1998 PASS
Print Pending Permit.LaserJet4  6/10/1998 PEND
Routing - PLAN CHECK6/9/1998 6/10/1998 PEND
Routing to public works.
Routing - PLAN CHECK6/8/1998 6/8/1998
Plans checked in by Kathy Miller and brought to my desk in preparation for plan review.
Plan routing begun/TENANTS  6/8/1998
Received Certificate of Value  6/8/1998 PASS
Plans ACCEPTED BY PLAN CHECK  6/8/1998 PASS
Application received  6/8/1998
Meeting  6/5/1998
Moke Hopkins brought in floor plan & application for review and to receive assistants with application. Will make notes on plan concerning altering door located on North end of new hallway. The door is to be removed as part of phase 2 when new enclosed hallway is constructed or to be reversed within six months to swing out to allow latch side clearance for accessibility per discussion with Moke Hopkins.
Meeting  5/28/1998
Approximate this date - reviewed first phase of project, conversion of sleeping room suite's to offices, conference and storage rooms, with Marlene Southard, Moke Hopkins & Jim Fackrell. This project to give city agency immediate office areas. Next phase to address new construction of exterior wall to create enclosed hallway from the office, conference room area to the main reception area.
Routing - FRONT DESK6/11/1998