Receive PAYMENT IN FULL | | | 5/24/2000 | | DONE |
|
|
|
|
Fee Review-notes | 10/15/1999 | 10/15/1999 | 3/15/2000 | | DONE |
|
|
|
still under const. check on 3/15/00-additional values from subs
|
Letter of compliance | | | 1/6/2000 | | DONE |
|
|
|
Letter of Compliance #18225 issued 1-6-00.
|
BLD-Final | 1/5/2000 | 1/5/2000 | 1/5/2000 | P | PASS |
Tom Arcoraci
|
|
|
Pat ###-####
|
BLD-Final | 12/30/1999 | 1/3/2000 | 1/3/2000 | A | FAIL |
Carl Dependahl
|
|
|
###-####. Keep C/N; need eng's letter recall.
|
FIRE-Final Inspection | 12/29/1999 | 12/29/1999 | 12/29/1999 | P | PASS |
Joe Tawney
|
|
|
PAt ###-####. Reinsp. ok for certificate of completion.
|
BLD-Final | 12/10/1999 | 12/14/1999 | 12/14/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 08:20:06. Contact: ###-####. Keep C/N.
|
Temporary occupancy | | | 12/14/1999 | | DONE |
|
|
|
Temp. Occ. Cert. #3955 issued 12-14-99 to the Emerald Research Bldg. #C.
|
FIRE-Final Inspection | 12/10/1999 | 12/13/1999 | 12/13/1999 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 18:44:15. Contact: ###-####. Final ok for temp. occ until 12/15/99.
|
BLD-Final | 12/10/1999 | 12/13/1999 | 12/13/1999 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 18:45:02. Contact: ###-####. C/N, ok to T/O.
|
FIRE-Final Inspection | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 11:50:32. Contact: ###-####. Final not ready.
|
FIRE-Hydro test above ground | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 14:44:14. Contact: ###-####. Ok on above ground hydro test. Sprinkler R/I C/N issued.
|
Code Occupancy Approval | | | 12/8/1999 | | PASS |
|
|
|
Meets compliance with DRH99-0046
|
Fee Review-notes | 12/18/1998 | | 10/26/1999 | | DONE |
|
|
|
|
FIRE-Sprinkler Rough-in | 10/22/1999 | 10/22/1999 | 10/22/1999 | P | CANC |
Joe Tawney
|
|
|
TRACY ###-#### CANCELLED BY TRACY NOT READY YET
|
FIRE-Supply Line Flush | 10/20/1999 | 10/20/1999 | 10/20/1999 | P | PART |
Joe Tawney
|
|
|
Ok on supply line flush
|
FIRE-Sprinkler Rough-in | 10/19/1999 | 10/20/1999 | 10/20/1999 | A | PART |
Joe Tawney
|
|
|
tracy ###-#### unground insp Ok on underground hydro test
|
(F) Reprint permit | | | 8/25/1999 | | |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 7/8/1999 | 7/8/1999 | 7/8/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON UNDERGROUND PIPING
|
INSP - Footings | 6/28/1999 | 6/28/1999 | 6/28/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - LOOKS OK, SPEC. INSP. ONSITE
|
INSP - Foundation | 6/22/1999 | 6/23/1999 | 6/23/1999 | A | PART |
Carl Dependahl
|
|
|
06/23/99 340 - spec insp onsite!. Contact phone is [8677613].
|
INSP - Foundation | 6/21/1999 | 6/21/1999 | 6/21/1999 | P | PART |
Carl Dependahl
|
|
|
06/21/99 340 - kleinfelder onsite, ftgs Contact phone is [8677613].
|
INSP - Foundation | 6/18/1999 | 6/18/1999 | 6/18/1999 | A | PART |
Carl Dependahl
|
|
|
06/18/99 340 - Scheduled by Hello!. Contact phone is [8677613]. SPEC IN
|
Inspection Record Card- Bld | | | 5/28/1999 | | |
|
|
|
|
Print Occupancy Form | | | 5/26/1999 | | |
|
|
|
|
Inspection Record Card- Bld | | | 5/26/1999 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 3/1/1999 | | |
|
|
|
|
Routing Off Site - A.C.H.D | 3/1/1999 | | 3/1/1999 | | PASS |
|
|
|
ACHD #99-4638
|
Print Occupancy Form | | | 8/25/1998 | | |
|
|
|
|
Telephone call | | | 8/25/1998 | | |
|
|
|
EXTENDED PER JTOOMBS UNTIL 1ST OF JANUARY 1999...DF
|
Inspection Record Card- Bld | | | 8/25/1998 | | |
|
|
|
|
Plan assigned to (JCM) | 6/11/1998 | | 8/24/1998 | | PASS |
John Menard
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/24/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM A.S.E., FORWARDED SAME TO JOHN MENARD.
|
Routing - PLAN CHECK | 8/13/1998 | | 8/24/1998 | | PASS |
|
|
|
|
Routing Off Site - STRUCTURAL | 8/17/1998 | | 8/19/1998 | | |
|
|
|
RESUBMITTALS RECEIVED AND SENT OUT TO ATWOOD HINZMAN AND JONES
|
Plan resubmittals received | | | 8/17/1998 | | |
|
|
|
RESUBS RECEIVED AND SENT TO ATWOOD
|
Routing - PLUMBING | 8/13/1998 | | 8/13/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 8/4/1998 | | 8/12/1998 | | PASS |
|
|
|
drh98-0046
|
Routing Off Site - STRUCTURAL | 8/7/1998 | | 8/12/1998 | | |
|
|
|
SENT RESUBMITTALS TO ATWOOD, HINZMAN, JONES
|
Plan resubmittals received | | | 8/4/1998 | | |
|
|
|
RECEIVED REVISED CIVIL SHEETS 1 THRU 5.
|
Routing - PLUMBING | 7/30/1998 | | 8/4/1998 | | FAIL |
|
|
|
|
Plan resubmittals received | | | 7/29/1998 | | |
|
|
|
RECEIVED 2 COPIES OF CIVIL SHEETS 1 THRU 5. ROUTED TO JOHN M.
|
Routing - FIRE | 7/20/1998 | | 7/22/1998 | | PASS |
|
|
|
|
Plan Review Completed(1st rev) | | | 7/22/1998 | | FAIL |
|
|
|
plumbing, PW, and structural issues
|
Routing - PLUMBING | 7/8/1998 | | 7/13/1998 | | FAIL |
|
|
|
|
Routing - PUBLIC WORKS | 6/30/1998 | | 7/8/1998 | | PASS |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/6/1998 | | PASS |
|
|
|
SEE ACTION 007 PEND
|
Routing Off Site - STRUCTURAL | 6/17/1998 | | 7/1/1998 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO ATWOOD HINZMAN AND JONES 7-1-98 RECEIVED STRUCTURAL PLAN CHECK REVIEW COMMENTS AND ROUTED TO JOHN M.
|
Routing - PLANNING | 6/29/1998 | | 6/30/1998 | | FAIL |
|
|
|
Applicant needs to submit revised plans and information to comply with DRH98-0046 conditions.
|
Plan routing begun/NEW & ADDTN | | | 6/29/1998 | | PEND |
|
|
|
SEE ACTION A007 PEND
|
Received Certificate of Value | 6/12/1998 | | 6/12/1998 | | |
|
|
|
|
Plan assigned to (MYS) | 6/9/1998 | | 6/11/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 6/11/1998 | | PEND |
|
|
|
CONTACTED DAVID KADANKO TO LET HIM KNOW THAT 1. ARCH. SHEETS NEED TO BE SIGNED 2. 2 COPIES OF LANDSCAPE SHEETS ARE REQUIRED. 3. ONE OUTSIDE ENG. PACK. IS REQUIRES WITH SOILS REPORT. 4. THREE ADD. GRADING AND DRAINAGE PLANS ARE REQUIRED. ROUTING CANNOT PROCEED UNTIL THESE ITEMS ARE RECEIVED. KMM 6-17-98 1. GORDON CAME AND SIGNED ARCH. SHEETS. 2. RECEIVED 2 COPIES OF LANDSCAPE SHEETS. 3. EXCHANGED ONE SET FROM PACKAGE #1 FOR ENG. GORDON WILL BRING IN ANOTHER FULL COPY OF PLANS FOR PACKAGE #1. HE WAS TOLD NO INHOUSE ROUTING CAN BEGIN UNTIL I RECEIVE THIS COPY. 4. CONTACTED BRIAN ABOUT CIVIL. HE SAID HE HAD WHAT HE NEEDED. 5. RECEIVED SOILS REPORT AND PUT WITH OUTSIDE ENG. 6-19-98 1. RECEIVED FULL ADDITIONAL COPY OF PLANS, HOWEVER CIVIL SHEETS WERE NOT STAMPED OR SIGNED. CALLED DAVE KADANKO TO GET SHEETS STAMPED AND SIGNED. 6-29-98 TALKED WITH DAVE TO REMIND HIM TO GET CIVIL SHEETS SIGNED. WILL ROUTE TO P & Z WHILE I WAIT. 6-30-98 TALKED WITH KEITH JACOBS ABOUT CIVIL SHEETS. HE WILL BRING 2 COPIES IN TO ME. HE STATED HE ALREADY SUBMITTED TO BRIAN AND JOHN JOHNSON. 7-2-98 RECEIVED STAMPED AND SIGNED CIVIL SHEETS (4 COPIES) TOOK TO PW TO PUT WITH PLANS
|
Recd Pcfee & Taken To Pln CK | | | 6/9/1998 | | PEND |
|
|
|
|
Application received | | | 6/9/1998 | | |
|
|
|
|
Case Summary (BLD) | | | | | |
|
|
|
|
Routing - PLAN CHECK | 7/13/1998 | | | | |
|
|
|
|
Routing - PLAN CHECK | 7/23/1998 | | | | |
|
|
|
|