INSP - Final | 3/3/1999 | 3/3/1999 | 3/3/1999 | | PASS |
Russ Owen
|
|
|
03/03/99 407 - ron ###-####
|
INSP - Final | 3/3/1999 | 3/3/1999 | 3/3/1999 | P | PASS |
Russ Owen
|
|
|
ron ###-####
|
INSP - Final | 2/24/1999 | 3/1/1999 | 3/1/1999 | A | FAIL |
Russ Owen
|
|
|
03/01/99 407 - window temp glass at master,caulk out lets etc energy cod
|
INSP - Framing/Rough-in | 12/4/1998 | 12/7/1998 | 12/7/1998 | A | PASS |
Wes Worcester
|
|
|
12/07/98 342 - RON ###-#### REINSPECT
|
INSP - Framing/Rough-in | 12/3/1998 | 12/4/1998 | 12/4/1998 | A | FAIL |
Wes Worcester
|
|
|
12/04/98 342 - RON ###-#### RE-FR INSP all items still not done
|
INSP - Framing/Rough-in | 12/2/1998 | 12/3/1998 | 12/3/1998 | A | PART |
Wes Worcester
|
|
|
12/03/98 342 - OK TO INSULATE.....C/N STILL NOT COMPLETED
|
INSP - Energy code compliance | 12/2/1998 | 12/2/1998 | 12/3/1998 | | FAIL |
Wes Worcester
|
|
|
12/03/98 342 - NOT ALL PENETRATIONS DONE
|
INSP - Framing/Rough-in | 11/30/1998 | 12/1/1998 | 12/1/1998 | P | FAIL |
Wes Worcester
|
|
|
12/01/98 342 - truss engineering, hangers, bcec infiltration package, et
|
INSP - Foundation | 10/9/1998 | 10/12/1998 | 10/12/1998 | A | PASS |
Wes Worcester
|
|
|
10/12/98 342 - jake- ###-#### for ft insp-ext 17145
|
INSP - Framing/Rough-in | 10/9/1998 | 10/9/1998 | 10/9/1998 | A | PART |
Wes Worcester
|
|
|
10/09/98 342 - JAKE ###-#### EXT. 17145 9:00 AM
|
INSP - Foundation | 10/7/1998 | 10/8/1998 | 10/8/1998 | P | FAIL |
Wes Worcester
|
|
|
10/08/98 342 - footing dave ###-#### poured without inspection, rebar in covered with concrete, soils report not on site
|
INSP - Foundation | 9/17/1998 | 9/17/1998 | 9/17/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - met bldr, developer, canal co on site. will have soils teste and utilties as necessary
|
Issue PAID IN FULL permit | | | 8/25/1998 | | |
|
|
|
|
Plan assigned to (ADS) | 8/21/1998 | | 8/24/1998 | | PASS |
|
|
|
|
Telephone call | | | 8/24/1998 | | MESS |
|
|
|
left mess at ###-#### that plans are ready
|
Print Pending Permit.LaserJet4 | | | 8/24/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/24/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 8/24/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 8/17/1998 | | 8/24/1998 | | PASS |
|
|
|
|
Plan assigned to (DJO) | 6/15/1998 | | 8/21/1998 | | PEND |
Dan Overy
|
|
|
|
Routing - PLANNING | 8/13/1998 | | 8/17/1998 | | PASS |
|
|
|
per revised site plan
|
Office Staff conference/action | | | 6/23/1998 | | FAIL |
|
|
|
failed by p & z angie/ in rejected drawer
|
Routing - PLANNING | 6/16/1998 | | 6/23/1998 | | FAIL |
|
|
|
this is a flag lot. requires 20 foot setback. does not have side entry garage. verified with scott. called joe lamarch on 6-16, he has not came in to redline plans and bring 3rd site plan.
|
Routing - PUBLIC WORKS | 6/15/1998 | | 6/16/1998 | | PASS |
|
|
|
|
Application received | | | 6/15/1998 | | |
|
|
|
|