Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD98-01788
StatusFinaled
Name HYDE PARK RETAIL-AKBAR'S TEAS
Site Address 1607 N 13TH ST
Project Name 
Customer Number 
ePlanReviewNo
Description
(HYDE PARK RETAIL) This building is not fire sprinkled. To convert a 1,198 square foot two story dwelling into a retail sales occupancy on the first floor (656 square feet) and offices on the second floor (542 square feet). Work is to include a restroom, a ramp, and a parking space accessible to the disabled. Some structural changes are being done to the building. The garage in the back yard will be used to meet parking requirements. All work shall be done per the approved drawings and the plan review conditions on file. PC-399-98 DRH-98-0079 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Case Summary (BLD)  2/27/2009 DONE
Letter of compliance  1/5/2000 DONE
Letter of Compliance #18222 issued 1-5-00.
INSP-Final Inspection12/3/199812/4/199812/4/1998APASS
DetailsRick Jackson
GREG ###-#### occ approved
INSP - Final12/3/199812/3/199812/3/1998PPASS
Details
12/03/98 333 - OTH-OTHER AGENCIES NOT APPROVED
INSP - Final11/25/199811/30/199811/30/1998PFAIL
Details
11/30/98 333 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in9/25/19989/25/19989/25/1998PPASS
Details
09/25/98 333 - FRAM-OK FRAMING
Inspection Record Card- Bld  8/5/1998
Issue PAID IN FULL permit  8/5/1998
PLANS/APPL TAKEN TO FRONT DESK  8/5/1998 PASS
Print Occupancy Form  8/5/1998
Telephone call  8/5/1998 MESS
left message for Greg ###-####
Plan assigned to (CJW)6/26/1998 8/4/1998 PASS
DetailsCarl Westfall
08/04/98 16:26:09 CJW - this action updated by action script from <<>> in Case No. BLD98-1788
Routing - PLAN CHECK7/22/1998 8/4/1998
testing condition printout  8/4/1998
Plan Reviewer's activity  8/4/1998 PASS
Drawings approved, with conditions, after resubmittal review.
Print permit w/o conditions  8/4/1998
Plan resubmittals received  7/28/1998
RECEIVED 2 COPIES OF SHEETS A1, AND A2. ROUTED TO CARL W.
Routing - FIRE7/21/1998 7/22/1998 PASS
Plan Reviewer's activity  7/17/1998
UBC plan review started July 17, 1998 and finished July 21, 1998. A response from the Architect is required. See conditions list.
Routing - PUBLIC WORKS7/8/1998 7/10/1998 PASS
Routing - PLANNING6/26/1998 7/7/1998 PASS
NEED TO EXTEND PAVING TO PROPERY LINE/ALLEY.
Plan Reviewer's activity  6/26/1998
I spoke to Gary Inselman (ACHD) and he said they could drain into the alley from new parking slab, therefore no drainage calcs for parking are required by Brian Murphy (Public Works). I then called Bradley Marczuk (architect) and told him they needed to contact ACHD for approval prior to permit issuance.
Plan routing begun/TENANTS  6/26/1998
Route to PLANNING, PUBLIC WORKS, PLAN CHECK and FIRE.
Plan assigned to (MYS)6/18/1998 6/26/1998
DetailsMarlene Southard
See note under Plan Reviewer's activity.
Recd Pcfee & Taken To Pln CK  6/18/1998 PEND
Application received  6/18/1998