DOC - Permit Finaled | 2/26/2001 | 2/26/2001 | 2/26/2001 | P | PASS |
Tony Young
|
|
|
Added by Inspector: 415 On 2/26/2001 2:54:46 PM
|
DOC - L/C Approved | 6/22/1999 | 6/22/1999 | 6/22/1999 | | PASS |
Russ Owen
|
|
|
/ / 407 - 16811.
|
INSP - Final | 6/21/1999 | 6/22/1999 | 6/22/1999 | A | PASS |
Russ Owen
|
|
|
06/22/99 407 - This is the one we talked about - Bob Stewart
|
INSP - Grading Inspection | 5/25/1999 | | 5/25/1999 | | PASS |
Rita DeYoung
|
|
|
Grading appears to be per plan. I spoke with Bob Stewart, the homeowner, about maintaining the roof drainage dispersal system tht was installed and that if there are any problems with it or if it eroded the slope he would be responsible for correcting the problem.
|
INSP - Final | 5/21/1999 | 5/24/1999 | 5/24/1999 | A | PART |
Russ Owen
|
|
|
05/24/99 407 - need sign off from drainage .
|
INSP - Framing/Rough-in | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PASS |
Wes Worcester
|
|
|
10/27/98 342 - JAN ###-#### -SHEAR PANEL & INS EARLY AM IF POSSIBLE
|
INSP - Framing/Rough-in | 10/22/1998 | 10/22/1998 | 10/22/1998 | P | PASS |
Wes Worcester
|
|
|
10/22/98 342 - JAN CELL # ###-#### 2-3pm apt
|
INSP - Framing/Rough-in | 10/2/1998 | 10/2/1998 | 10/2/1998 | | PART |
Wes Worcester
|
|
|
10/02/98 342 - sheer nailing
|
INSP - Framing/Rough-in | 9/23/1998 | 9/24/1998 | 9/24/1998 | A | FAIL |
Wes Worcester
|
|
|
09/24/98 342 - shear nailing incorrect, double studs missing at front of
|
INSP - Framing/Rough-in | 8/13/1998 | 8/14/1998 | 8/14/1998 | A | PASS |
Wes Worcester
|
|
|
08/13/98 342 - RE-BAR JON ###-#### EXT 19181
|
INSP - Framing/Rough-in | 8/13/1998 | 8/13/1998 | 8/13/1998 | P | PART |
Wes Worcester
|
|
|
08/13/98 342 - re-bar jon ###-#### beep 19181
|
INSP - Foundation | 8/7/1998 | 8/10/1998 | 8/10/1998 | A | PASS |
Wes Worcester
|
|
|
08/10/98 342 - footing ###-#### 19181
|
INSP - Foundation | 8/6/1998 | 8/7/1998 | 8/7/1998 | P | PART |
Wes Worcester
|
|
|
08/07/98 342 - JOHN ###-#### BEEP 19181 4-4:30 apt
|
INSP - Foundation | 8/7/1998 | 8/7/1998 | 8/7/1998 | | NR |
Wes Worcester
|
|
|
/ / 342 - 4-4:30 apt not ready til Mon am
|
Plan assigned to (DJO) | 6/24/1998 | | 7/31/1998 | | PASS |
Dan Overy
|
|
|
07/31/98 08:35:05 DJO - this action updated by action script from <<>> in Case No. BLD98-1856
|
Issue PAID IN FULL permit | | | 7/31/1998 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/31/1998 | | |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/31/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 7/31/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/31/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 7/31/1998 | | PASS |
|
|
|
ENGINEER HAS SUBMITTED WALL BRACE ENGINEERING. COPY ON FILE.
|
Plans ACCEPTED BY PLAN CHECK | | | 7/28/1998 | | PEND |
|
|
|
|
Plan Reviewer's activity | | | 7/28/1998 | | PEND |
|
|
|
WALL BRACE ENGINEERING REQUIRED.
|
Routing - PLANNING | 7/9/1998 | | 7/10/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 6/24/1998 | | 7/9/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/8/1998 | | 7/8/1998 | | PASS |
Rita DeYoung
|
|
|
Approved as category 3.
|
Application received | | | 6/24/1998 | | |
|
|
|
|
Routing - PLAN CHECK | 7/10/1998 | | | | PEND |
|
|
|
|