INSP - Grading Inspection | 8/19/1999 | | 8/19/1999 | | PASS |
Rita DeYoung
|
|
|
Revegetation complete. $750.00 surety can be released.
|
INSP - Final | 3/10/1999 | 3/10/1999 | 3/10/1999 | P | PASS |
Wes Worcester
|
|
|
03/10/99 342 - c/c issued
|
INSP - Grading Inspection | 3/8/1999 | | 3/8/1999 | | BOND |
Rita DeYoung
|
|
|
Rough grading is complete but fine grading and revegetation is not. Also there is some disturbance on the lot to the northeast that must be restored. The engineer has recommended a surety of $750.00 to ensure the satisfactory completion of the grading and revegetation, including restoration of the lot next door.
|
INSP - Final | 3/2/1999 | 3/3/1999 | 3/3/1999 | A | FAIL |
Wes Worcester
|
|
|
03/03/99 342 - ###-#### John not quite done
|
INSP - Framing/Rough-in | 11/4/1998 | 11/4/1998 | 11/4/1998 | | PART |
Wes Worcester
|
|
|
/ / 342 - placing addl truss bracing
|
INSP - Energy code compliance | 11/3/1998 | 11/4/1998 | 11/4/1998 | A | PART |
Wes Worcester
|
|
|
11/04/98 342 - JOHN ###-#### ì
|
INSP - Framing/Rough-in | 10/29/1998 | 10/30/1998 | 10/30/1998 | A | PASS |
Alan Hauser
|
|
|
10/30/98 350 - nailing as per plans
|
INSP - Framing/Rough-in | 10/28/1998 | 10/28/1998 | 10/28/1998 | P | PART |
Wes Worcester
|
|
|
10/28/98 342 - JOHN RYAN ###-####
|
INSP - Foundation | 8/27/1998 | 8/27/1998 | 8/27/1998 | P | PASS |
Wes Worcester
|
|
|
08/27/98 342 - mark ###-#### ì
|
INSP - Foundation | 8/18/1998 | 8/19/1998 | 8/19/1998 | A | PASS |
Wes Worcester
|
|
|
08/19/98 342 - footing steve ###-#### faxed eng letter and was recalled
|
INSP - Foundation | 8/18/1998 | 8/18/1998 | 8/18/1998 | | NR |
Wes Worcester
|
|
|
/ / 342 - 11am apt need eng letter
|
INSP - Foundation | 8/18/1998 | 8/18/1998 | 8/18/1998 | P | NR |
Wes Worcester
|
|
|
08/18/98 342 - steve ###-#### footing not ready til am 8/19
|
Routing - PLAN CHECK | 7/21/1998 | | 8/4/1998 | | PASS |
|
|
|
|
Issue PAID IN FULL permit | | | 8/4/1998 | | |
|
|
|
|
Telephone call | | | 8/4/1998 | | PASS |
|
|
|
called gave dollar amount to monica ryan
|
Routing - PLAN CHECK | 7/22/1998 | | 7/30/1998 | | PASS |
|
|
|
|
Telephone call | | | 7/30/1998 | | FAIL |
|
|
|
NO ANSWER AT ###-####
|
Print Occupancy Form | | | 7/30/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/30/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 7/30/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 7/30/1998 | | |
|
|
|
|
Routing - PLANNING | 7/21/1998 | | 7/22/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 7/1/1998 | | 7/21/1998 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS GRADING | 7/20/1998 | | 7/20/1998 | | PASS |
Rita DeYoung
|
|
|
Received letter from soils engineer approving foundation setbacks from slope. Approved as category 3.
|
Application received | | | 7/1/1998 | | |
|
|
|
|