Permit Information
Permit NumberBLD98-01951
StatusFinaled
Name EMPIRE GROUP
Site Address 211 W GROVEVIEW LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a 2359 sq. ft. two story single family dwelling with a 872 sq. ft. attached three car garage and 372 sq. ft. of concrete patios per approved plans and attached requirement lists. (1st floor 1675 sq. ft.) (2nd floor 684 sq. ft.) This lot is within a hillside area and is subject to the Hillside Oridinance. Class "A" roof system required. ACHD #98-1929 CU #139-78 PC #573 DJO
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final1/21/19991/22/19991/22/1999PPASS
DetailsWes Worcester
01/22/99 342 - TIM DIGITAL ###-#### RE-INSP FIN
INSP - Final1/20/19991/21/19991/21/1999AFAIL
DetailsWes Worcester
01/21/99 342 - tim digital ###-#### fn-call 1/2 hr before insp handrail,
INSP - Grading Inspection1/21/1999 1/21/1999 BOND
DetailsRita DeYoung
Grading approved but revegetation is not complete. Slopes above and below house are not revegetated yet. Recommend $500.00 bond to cover cost of revegetation. Upon receipt of bond the grading is approved.
INSP - Wall cover11/6/199811/6/199811/6/1998PPASS
DetailsWes Worcester
11/06/98 342 - SHEER WALL--TIM ###-####
INSP - Energy code compliance11/3/199811/3/199811/3/1998PPASS
DetailsWes Worcester
TIM ###-#### REINSPECT
INSP - Energy code compliance11/3/199811/3/199811/3/1998 PASS
DetailsWes Worcester
/ / 342 -
INSP - Energy code compliance11/2/199811/2/199811/2/1998PFAIL
DetailsWes Worcester
11/02/98 342 - TIM ###-#### PAGER REINSPECT
INSP - Energy code compliance10/30/199810/30/199810/30/1998PFAIL
DetailsCarl Dependahl
TIM DOLAN- ###-#### ENERGY CODE...still need seal soffit penetrations...keep c/n on frame. 342 area
INSP - Framing/Rough-in10/30/199810/30/199810/30/1998PFAIL
DetailsCarl Dependahl
TIM DOLAN ###-#### FR/INSP...complete fastening truss hangers, complete air seal, some missed.
INSP - Framing/Rough-in10/29/199810/29/199810/29/1998PFAIL
DetailsCarl Dependahl
TIM ###-#### PLEASE CALL WOULD LIKE TO MEET YOU THERE per 325 c/n, fireblocks, truss hangers, add brace panels plate-to-plate at upper floor as needed (gyp ok)...etc, ok to insul.
INSP - Framing/Rough-in10/21/199810/21/199810/22/1998PPART
DetailsWes Worcester
10/21/98 342 - tim- ###-#### digital -preliminary fr-shear wall insp
INSP - Framing/Rough-in10/19/199810/20/199810/20/1998ANR
DetailsWes Worcester
10/20/98 342 - SHEAR WALL /###-####
SUPER- Supervisor's review9/29/19989/29/19989/29/1998 PEND
Review of soil classification. MTI engineer to review.
INSP - Foundation9/1/19989/1/19989/1/1998 PART
DetailsWes Worcester
/ / 342 -
INSP - Framing/Rough-in9/1/19989/1/19989/1/1998 PART
DetailsWes Worcester
09/01/98 342 - rebar john ###-####
INSP - Framing/Rough-in9/1/19989/1/19989/1/1998PFAIL
DetailsWes Worcester
09/01/98 342 - landscaping/retaining wall over 4', retaining earth and w slope > than 2:1 needs design engineering
INSP - Foundation8/27/19988/28/19988/28/1998ANR
DetailsWes Worcester
08/28/98 342 - rebar/steel footing john ###-####
INSP - Foundation8/28/19988/28/19988/28/1998 PASS
DetailsWes Worcester
/ / 342 -
(F) Reprint permit  8/17/1998
Issue PAID IN FULL permit  8/10/1998
Telephone call  8/7/1998
CALLED EMPIRE PERMIT READY
Inspection Record Card- Bld  8/7/1998
Print Occupancy Form  8/7/1998
Plan assigned to (DJO)7/15/1998 8/6/1998 PASS
DetailsDan Overy
08/06/98 16:40:17 DJO - this action updated by action script from <<>> in Case No. BLD98-1951
Print Pending Permit.LaserJet4  8/6/1998 PASS
PLANS/APPL TAKEN TO FRONT DESK  8/6/1998 PASS
Plan Reviewer's activity  8/6/1998 PASS
ISSUES RESOLVED.
Plan Reviewer's activity  7/29/1998 PEND
CALLED. DESIGNER IN MEETING. NOTHING RESOLVED.
Plan Reviewer's activity  7/28/1998 PEND
CALLED EMPIRE GROUP. WALL BRACING ENGINEERING REQUIRED. PLANS INCOMPLETE. FOUNDATION/FLOOR FRAMING NEEDED.
Plans ACCEPTED BY PLAN CHECK  7/28/1998 PEND
Routing - PLANNING7/15/1998 7/15/1998 PASS
Routing - PUBLIC WORKS GRADING7/14/1998 7/14/1998 PASS
DetailsRita DeYoung
Approved as category 3.
Application received  7/1/1998
Routing - PLAN CHECK7/15/1998   PEND