Case Summary (BLD) | | | 11/4/2003 | | |
|
|
|
|
Permanent occupancy | | | 5/26/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7774 issued 5-26-99 to 3d Imax Theater.
|
INSP - Final | 5/24/1999 | 5/25/1999 | 5/25/1999 | A | PASS |
Carl Dependahl
|
|
|
05/25/99 340 - ken ###-####, ok for c.o
|
INSP - Final | 5/24/1999 | 5/24/1999 | 5/24/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
Permanent Occupancy | | 5/23/1999 | 5/23/1999 | | DONE |
|
|
|
|
INSP-Final Inspection | 5/20/1999 | 5/20/1999 | 5/20/1999 | | FAIL |
Joe Tawney
|
|
|
05/20/99 406 - ###-#### KEN//FIRE & LIFE SAFETY REINSP FAIL KNOX BOX, FAX OF SIGNALS
|
INSP - Final | 5/19/1999 | 5/20/1999 | 5/20/1999 | A | FAIL |
Carl Dependahl
|
|
|
05/20/99 340 - ###-#### KEN//FINAL; need fire ok, has t/o
|
INSP - Final | 5/17/1999 | 5/18/1999 | 5/18/1999 | A | FAIL |
Carl Dependahl
|
|
|
05/18/99 340 - ###-#### KEN//FINAL; need fire, recall
|
INSP-Final Inspection | 5/17/1999 | 5/18/1999 | 5/18/1999 | A | CANC |
Joe Tawney
|
|
|
05/18/99 406 - REINSP CANCEL RESCHED TO 5/20/99 AT 8:30 AM
|
INSP - Framing/Rough-in | 5/17/1999 | 5/17/1999 | 5/17/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF W/ PROJ MGR.
|
INSP - Framing/Rough-in | 5/14/1999 | 5/14/1999 | 5/14/1999 | P | PART |
Carl Dependahl
|
|
|
05/14/99 340 - ken ###-####; ok to use UBC 1016.5 EXC. for rest room doo
|
INSP - Framing/Rough-in | 5/12/1999 | 5/13/1999 | 5/13/1999 | A | NR |
Carl Dependahl
|
|
|
05/13/99 340 - ken ###-#### left msg, not at office
|
INSP - Framing/Rough-in | 5/12/1999 | 5/12/1999 | 5/12/1999 | P | PART |
Carl Dependahl
|
|
|
05/12/99 340 - conf only w/ proj mgr; need arch's letter re smoke dampers, door hdwe; keep c/n.
|
INSP - Framing/Rough-in | 5/11/1999 | 5/11/1999 | 5/11/1999 | P | FAIL |
Carl Dependahl
|
|
|
ken ###-#### call first to meet; keep c/n, need arch's letter re doors & smoke dampers
|
INSP - Final | 4/30/1999 | 4/30/1999 | 4/30/1999 | P | FAIL |
Carl Dependahl
|
|
|
conf w/ proj mgr re corrections, keep c/n.
|
INSP-Final Inspection | 4/29/1999 | 4/30/1999 | 4/29/1999 | A | |
Joe Tawney
|
|
|
Theresa ###-####
|
(F) Reprint permit | | | 4/29/1999 | | |
|
|
|
|
INSP - Final | 4/27/1999 | 4/27/1999 | 4/27/1999 | | NR |
Carl Dependahl
|
|
|
/ / 340 - CONF W/ BLDR
|
INSP-Final Inspection | 4/26/1999 | 4/26/1999 | 4/26/1999 | P | PART |
Joe Tawney
|
|
|
FINAL OK FOR TEMP OCC NEED TO RESOLVE S/F DAMPER ISSUE
|
INSP - Final | 4/26/1999 | 4/26/1999 | 4/26/1999 | P | FAIL |
Carl Dependahl
|
|
|
04/26/99 340 - ###-####//TEMP OCCUPY, c/n ok for t/o; card to cont.
|
Code Occupancy Approval | | | 4/26/1999 | | PASS |
|
|
|
Inspection for Final - complies w/DRH-98-0068 - PASS
|
INSP - Final | 4/22/1999 | 4/23/1999 | 4/23/1999 | A | FAIL |
Carl Dependahl
|
|
|
04/23/99 340 - Theresa ###-####; need eng's letter, other sigs, LITES IN
|
Fee Review-notes | 1/15/1999 | | 4/23/1999 | | |
|
|
|
gc faxed final cert value went up. lh
|
INSP-Conference | 4/14/1999 | 4/14/1999 | 4/14/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF ON LOCATION OF FIRE EXT
|
INSP-Supply line flush | 2/22/1999 | 2/23/1999 | 2/22/1999 | A | |
Russ Owen
|
|
|
###-#### Mike
|
INSP-Conference | 2/10/1999 | 2/10/1999 | 2/10/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - conf with ken harder & jerry with ESI regarding fire/life sa
|
INSP-Conference | 2/10/1999 | 2/10/1999 | 2/10/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - conf with ken harder & jerry with ESI regarding fire/life sa
|
INSP - Conference | 2/5/1999 | 2/5/1999 | 2/5/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - conf w/ joe tawney re sprinklers; bldr unaware of req's for etc. keep c/n
|
INSP - Framing/Rough-in | 2/3/1999 | 2/4/1999 | 2/4/1999 | A | CANC |
Russ Owen
|
|
|
02/04/99 407 - trans to 340.
|
INSP - Conference | 2/4/1999 | 2/4/1999 | 2/4/1999 | | PASS |
Carl Dependahl
|
|
|
/ / 340 - chk'd previous insp's re frame request 2-4-99
|
INSP - Framing/Rough-in | 2/4/1999 | 2/4/1999 | 2/4/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - c/n, need fire r/i, resolve plan review issues, firestop rat
|
INSP - Framing/Rough-in | 1/19/1999 | 1/19/1999 | 1/19/1999 | | PART |
Tom Arcoraci
|
|
|
/ / 408 - bath rooms ok to cover
|
INSP - Framing/Rough-in | 1/19/1999 | 1/19/1999 | 1/19/1999 | | PART |
Tom Arcoraci
|
|
|
/ / 408 - bath rooms ok to cover
|
INSP - Framing/Rough-in | 1/15/1999 | 1/19/1999 | 1/19/1999 | A | PART |
Tom Arcoraci
|
|
|
01/19/99 408 - ###-#### CEILING GRID
|
INSP - Framing/Rough-in | 1/13/1999 | 1/13/1999 | 1/15/1999 | P | PART |
|
|
|
01/13/99 338 - will finish 01/19/99
|
INSP - Framing/Rough-in | 12/28/1998 | 12/28/1998 | 12/28/1998 | P | PART |
|
|
|
12/28/98 338 - made ok to cover with ele insp approval
|
INSP - Foundation | 12/9/1998 | 12/10/1998 | 12/11/1998 | A | PART |
|
|
|
12/11/98 338 - made ok with sp insp approval
|
Plan resubmittals received | | | 12/10/1998 | | |
|
|
|
RECEIVED DRAWINGS WITH CENTRAL DIST. HEALTH COMMENTS. ROUTED TO PERRY P. KMM
|
INSP - Foundation | 12/7/1998 | 12/7/1998 | 12/7/1998 | P | PART |
|
|
|
12/07/98 333 - ok pend spec insp rep
|
INSP - Foundation | 12/4/1998 | 12/4/1998 | 12/4/1998 | P | PART |
|
|
|
12/04/98 338 - MADE OK TO POUR WITH SP INSP APPROVAL
|
INSP - Foundation | 11/23/1998 | 11/23/1998 | 11/23/1998 | P | PART |
|
|
|
11/23/98 338 - made ok with sp insp approval.
|
INSP - Foundation | 11/20/1998 | 11/20/1998 | 11/20/1998 | P | PART |
|
|
|
11/20/98 338 - madeookwith sp insp approval
|
INSP - Foundation | 11/19/1998 | 11/19/1998 | 11/19/1998 | P | |
|
|
|
Scheduled by Hello!. Contact phone is [6584471].
|
INSP - Foundation | 11/18/1998 | 11/18/1998 | 11/19/1998 | P | PART |
|
|
|
11/19/98 338 - madeok with sp insp approval
|
INSP - Foundation | 11/16/1998 | 11/17/1998 | 11/17/1998 | P | PART |
|
|
|
11/17/98 338 - made ok with sp insp approval
|
INSP - Foundation | 11/13/1998 | 11/16/1998 | 11/16/1998 | P | PART |
|
|
|
11/14/98 338 - made ok with sp insp approval
|
INSP - Foundation | 11/13/1998 | 11/16/1998 | 11/16/1998 | P | PART |
|
|
|
11/14/98 338 - made ok with sp insp approval
|
INSP - Foundation | 11/11/1998 | 11/12/1998 | 11/13/1998 | A | PART |
|
|
|
11/12/98 338 - made ok with sp insp approval
|
INSP - Foundation | 11/11/1998 | 11/12/1998 | 11/12/1998 | P | PART |
|
|
|
11/12/98 338 - made ok with sp insp approval next to top and top bond be
|
INSP - Foundation | 11/9/1998 | 11/10/1998 | 11/10/1998 | P | PART |
|
|
|
11/10/98 338 - made ok for pour with sp insp approval
|
INSP - Foundation | 11/6/1998 | 11/9/1998 | 11/9/1998 | A | PART |
|
|
|
11/09/98 338 - made ok for pour with sp insp approvel r-bar placed for g
|
INSP - Foundation | 11/5/1998 | 11/5/1998 | 11/5/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [6584471]. pending spec insp report; 338 area.
|
INSP - Foundation | 11/4/1998 | 11/4/1998 | 11/4/1998 | P | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [6584471]. 338 area, pending spec insp report.
|
INSP - Foundation | 11/3/1998 | 11/3/1998 | 11/3/1998 | A | PART |
Carl Dependahl
|
|
|
Scheduled by Hello!. Contact phone is [6584471]. pending spec insp. report...338 area.
|
INSP - Foundation | 10/30/1998 | 11/2/1998 | 11/2/1998 | A | FAIL |
|
|
|
11/02/98 333 - no one there
|
INSP - Foundation | 10/29/1998 | 10/30/1998 | 10/30/1998 | A | PART |
|
|
|
10/30/98 338 - made ok with sp insp approval
|
INSP - Foundation | 10/28/1998 | 10/28/1998 | 10/28/1998 | | PART |
|
|
|
10/28/98 338 - made ok to pour bond beam with sp insp approval
|
INSP - Foundation | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
|
|
|
10/27/98 338 - made ok for bond beam pour with sp insp approval
|
INSP - Framing/Rough-in | 10/23/1998 | 10/26/1998 | 10/26/1998 | A | PART |
|
|
|
10/26/98 338 - MADE OK WITH SP INSP APPROVAL
|
INSP - Foundation | 10/23/1998 | 10/23/1998 | 10/23/1998 | P | PART |
|
|
|
10/23/98 338 - made ok with sp insp approval
|
INSP - Foundation | 10/20/1998 | 10/21/1998 | 10/21/1998 | P | PART |
|
|
|
10/21/98 338 - made o k to pour with sp insp approval
|
INSP - Foundation | 10/19/1998 | 10/19/1998 | 10/19/1998 | P | PART |
|
|
|
10/19/98 338 - made ok with sp insp approval
|
INSP - Framing/Rough-in | 10/14/1998 | 10/15/1998 | 10/15/1998 | A | PART |
|
|
|
10/15/98 338 - MADE OK TO COVER WITH SP INSP APPROVAL
|
INSP - Foundation | 10/12/1998 | 10/12/1998 | 10/14/1998 | P | PART |
|
|
|
10/15/98 338 - made ok with sp insp approval
|
INSP - Foundation | 10/8/1998 | 10/9/1998 | 10/9/1998 | P | PART |
|
|
|
10/09/98 338 - made ok with sp insp blessing
|
INSP - Foundation | 10/6/1998 | 10/7/1998 | 10/7/1998 | A | PART |
|
|
|
10/07/98 338 - MADE OK TO POUR THE BLACK FLOOR AT THE FRONT STAGE AREA
|
INSP - Foundation | 9/29/1998 | 10/1/1998 | 10/1/1998 | P | PART |
Tom Arcoraci
|
|
|
10/01/98 408 - Scheduled by Hello!. Contact phone is [6584471]. spec insp on site
|
INSP - Foundation | 9/24/1998 | 9/25/1998 | 9/25/1998 | P | PART |
|
|
|
09/25/98 338 - MADE OK WITH SP INSP Approval
|
INSP - Foundation | 9/21/1998 | 9/22/1998 | 9/22/1998 | A | PART |
|
|
|
09/22/98 338 - made3 ok with sp insp approval recieved the sp insp lette
|
INSP - Foundation | 9/18/1998 | 9/21/1998 | 9/21/1998 | P | NR |
|
|
|
09/21/98 338 - NOT READY TO POUR SP INSP LETTER NOT ON SITE NO FORMS OR
|
(F) Reprint permit | | | 9/4/1998 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/3/1998 | | PASS |
|
|
|
|
Inspection Record Card- Bld | | | 9/3/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 9/3/1998 | | PASS |
|
|
|
|
Print Occupancy Form | | | 9/3/1998 | | PASS |
|
|
|
|
Telephone call | | | 9/3/1998 | | PASS |
|
|
|
called steve ###-#### says he will be down
|
Plan resubmittals received | | | 9/3/1998 | | PEND |
|
|
|
RECEIVED PLAN RESUBMITTALS, FORWARDED SAME TO
|
Issue PAID IN FULL permit | | | 9/3/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 9/2/1998 | | PASS |
|
|
|
AFTER SPEAKING WITH RON BERNHARDT OF PERKOWITZ & RUTH ARCHITECTS, HE INDICATED THAT THE OWNERS INTEND TO SPRINKLE THE BUILDING AND THAT HE WILL ISSUE NEW PLANS SHOWING THE ENTRY CANOPY SET BACK AS REQUIRED AT THE NORTH PROPERTY LINE; WITH THIS INFORMATION I AM ABLE TO APPROVE THIS PERMIT FOR CONSTRUCTION. JCM
|
Plan assigned to (JCM) | 7/10/1998 | | 9/2/1998 | | PASS |
John Menard
|
|
|
|
Routing - PLAN CHECK | 8/17/1998 | | 9/2/1998 | | PASS |
|
|
|
|
Plan Reviewer's activity | | | 9/1/1998 | | PEND |
|
|
|
FAXED RON BERNHARDT A LETTER REQUESTING CLARIFICATION ON HIS RESUBMITTAL LETTER.
|
Plan resubmittals received | | | 8/24/1998 | | PEND |
|
|
|
RECEIVED RESUBMITTALS FROM PERKOWITZ AND RUTH, FORWARDED SAME TO JOHN MENARD. DAR
|
Routing Off Site - STRUCTURAL | 8/3/1998 | | 8/19/1998 | | |
|
|
|
RESUBSUBS FROM ATWOOD HINSMAN JONES 1ST RESUB.
|
Routing - PLUMBING | 8/14/1998 | | 8/17/1998 | | PASS |
|
|
|
|
Routing - FIRE | 8/7/1998 | | 8/13/1998 | | PASS |
|
|
|
|
Plan resubmittals received | | | 8/10/1998 | | |
|
|
|
RECEIVED TWO COPIES OF REVISED PLUMBING SHEETS (P-1, P-2, P-3, M-1, M-2, M-3, & M-4). ROUTED TO JOHN M.
|
Plan resubmittals requested | | | 8/7/1998 | | PEND |
|
|
|
MAILED A COPY OF THE CORRECTION LIST REQUESTING REVISIONS TO PERKOWITZ & RUTH ARCHITECTS.
|
Plan resubmittals received | | | 8/3/1998 | | |
|
|
|
RECEIVED 2 COPIES OF RESPONSE TO PLAN REVIEW COMMENTS, AND 2 COPIES OF REVISED SHEETS S2.3 AND S4.2 CHANGEDS ARE CLOUDED, LABELED 1 AND DATED 7-31-98. 2 COPIES OF SUPPLEMENTAL STRUCT. CALCS. ROUTED TO JOHN M.
|
Plan resubmittals requested | | | 7/27/1998 | | PEND |
|
|
|
FAXED STEVE HILL AT ESI A COPY OF THE COMMENT LIST FROM CH2MHILL AND REQUESTED THAT IT BE FORWARDED TO THE ENGINEER OF RECORD FOR A RESPONSE.
|
Routing Off Site - STRUCTURAL | 7/3/1998 | | 7/24/1998 | | |
|
|
|
CONTACTED PDQ TO TAKE PLANS OUT TO CH2MHILL NEED SOILS REPORT BEFORE I ROUTE TO CH2MHILL 7-13-98 RECEIVED SOILS REPORT. 7-24-98 RECEIVED 1. STRUCTURAL REVIEW FROM CH2MHILL. ROUTED TO JOHN M.
|
Routing - PLUMBING | 7/22/1998 | | 7/23/1998 | | FAIL |
|
|
|
|
Routing - PLANNING | 7/15/1998 | | 7/22/1998 | | PASS |
|
|
|
CUP98-0048 approved by TAC DRH98-0068 approved by MGS
|
Routing - PUBLIC WORKS | 7/13/1998 | | 7/15/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/13/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/13/1998 | | PASS |
|
|
|
|
Plan assigned to (MYS) | 7/9/1998 | | 7/10/1998 | | |
Marlene Southard
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/10/1998 | | PEND |
|
|
|
CONTACTED STEVE HILL TO LET HIM KNOW THAT A SOILS REPORT IS NEEDED BEFORE I CAN ROUTE TO OUTSIDE ENG. 7-13-98 RECEIVED 3 COPIES OF SOILS REPORT. GAVE ONE TO DAVE FOR GRADING AND DRAINAGE, PUT TWO WITH OUTSIDE ENG.
|
Recd Pcfee & Taken To Pln CK | | | 7/9/1998 | | |
|
|
|
|
Application received | | | 7/9/1998 | | |
|
|
|
|
Received Certificate of Value | | | 7/9/1998 | | PASS |
|
|
|
|