INSP - Final | 6/18/1999 | 6/21/1999 | 6/21/1999 | A | PASS |
Carl Dependahl
|
|
|
06/21/99 340 - 859+2755/*/FINAL; ok card to bldr
|
Permanent occupancy | | | 6/21/1999 | | PASS |
|
|
|
Perm. Occ. Cert. #7805 issued 6-21-99 to Fredriksen Storage (addition).
|
INSP-Final Inspection | 6/17/1999 | 6/17/1999 | 6/17/1999 | P | PASS |
Joe Tawney
|
|
|
06/17/99 406 - REINSP OK FOR PERM OCC
|
Permanent Occupancy | | 6/17/1999 | 6/17/1999 | | DONE |
|
|
|
|
Code Occupancy Approval | | | 6/16/1999 | | |
|
|
|
Final Occupancy requested by Shawn 859 2755
|
INSP - Final | 6/2/1999 | 6/2/1999 | 6/2/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC KNOX BOX, NFPA 72
|
INSP-Final Inspection | 6/1/1999 | 6/1/1999 | 6/1/1999 | P | NR |
Joe Tawney
|
|
|
06/01/99 406 - FINAL NOT READY RESCHED FOR 6/2/99 1:00 PM
|
Fee Review-notes | 10/27/1998 | | 4/23/1999 | | PASS |
|
|
|
needs ele.
|
INSP - Framing/Rough-in | 4/21/1999 | 4/22/1999 | 4/22/1999 | A | PART |
Carl Dependahl
|
|
|
04/22/99 340 - CONFERENCE Shawn ###-####, need all sigs for final
|
INSP - Final | 4/20/1999 | 4/21/1999 | 4/21/1999 | A | NR |
Carl Dependahl
|
|
|
04/21/99 340 - ###-#### SHAWN//CONFERENCE
|
INSP-Final Inspection | 4/16/1999 | 4/16/1999 | 4/16/1999 | P | FAIL |
Joe Tawney
|
|
|
04/16/99 406 - REINSP FAIL SUITE NMBRS, SEAL ONE HOUR WALLS
|
INSP-Sprinkler Rough-in/Hydro | 3/11/1999 | 3/11/1999 | 3/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ABOVE GROUND HYDRO TEST
|
INSP-Sprinkler Rough-in/Hydro | 3/11/1999 | 3/11/1999 | 3/11/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON ABOVE GROUND HYDRO TEST
|
INSP-Final Inspection | 3/8/1999 | 3/9/1999 | 3/9/1999 | A | FAIL |
Joe Tawney
|
|
|
03/09/99 406 - FINAL FAIL SPKLR SYSTEM, FIRE EXT, DOOR LANDINGS
|
INSP - Framing/Rough-in | 2/12/1999 | 2/12/1999 | 2/12/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - verbal c/n: nail off all shear panels at blocks and edges pe when ready
|
INSP - Framing/Rough-in | 12/22/1998 | 12/23/1998 | 12/23/1998 | A | PART |
|
|
|
12/23/98 338 - made ok to cover interior walls
|
INSP - Framing/Rough-in | 11/25/1998 | 11/30/1998 | 11/30/1998 | A | PART |
|
|
|
11/30/98 338 - made ok to cover roof .
|
INSP - Foundation | 9/28/1998 | 9/28/1998 | 9/28/1998 | P | PART |
|
|
|
09/28/98 338 - MADE OK TO POUR THE INTERIOR FOOTINGS WITH THE SLAB
|
INSP - Conference | 9/22/1998 | 9/22/1998 | 9/22/1998 | | PART |
|
|
|
/ / 338 - MADE OK Q'S ON PLACCEMENT OF THE ANCHOR BOLTS IN THE INTERIO
|
INSP - Foundation | 9/18/1998 | 9/21/1998 | 9/21/1998 | A | PART |
|
|
|
09/21/98 338 - MADE OK TO POUR THE FOUND WALLS FORMS ANND R-BAR PLACED.
|
INSP - Foundation | 9/17/1998 | 9/18/1998 | 9/18/1998 | A | PASS |
|
|
|
09/17/98 338 - MADED OK WITH SP INSP APPROVAL ON THE EPOXY BAR
|
INSP - Foundation | 9/9/1998 | 9/10/1998 | 9/10/1998 | A | PASS |
|
|
|
09/10/98 338 - conf ok to proceed eed eng for fill ok
|
Issue PAID IN FULL permit | | | 9/1/1998 | | |
|
|
|
|
Telephone call | | | 8/25/1998 | | |
|
|
|
CALLED JOHN AT ###-#### PERMIT READY
|
Inspection Record Card- Bld | | | 8/24/1998 | | |
|
|
|
|
Print Occupancy Form | | | 8/24/1998 | | |
|
|
|
|
Plan Reviewer's activity | | | 8/21/1998 | | PASS |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/1998 | | PASS |
|
|
|
|
Print Pending Permit.LaserJet4 | | | 8/21/1998 | | PASS |
|
|
|
|
Plan assigned to (M_P) | 7/13/1998 | | 8/21/1998 | | PASS |
Mike Phillips
|
|
|
08/21/98 15:09:32 M_P - this action updated by action script from <<>> in Case No. BLD98-2048
|
Plan Review Completed(1st rev) | | | 8/6/1998 | | FAIL |
|
|
|
UBC issues not resolved
|
Routing - FIRE | 8/6/1998 | | 8/6/1998 | | PASS |
|
|
|
Requirements for fire sprinkler system noted on attached comments. without a fully complying system to current codes it can not be used to increase area, reduce fire resistive rating of the building or reduce fire flow. all three were used by the architect.
|
Routing - PUBLIC WORKS | 7/22/1998 | | 7/23/1998 | | PASS |
|
|
|
|
Routing - PLANNING | 7/16/1998 | | 7/21/1998 | | PASS |
|
|
|
approved per DRH98-0073. Note: trees along Bond Street shall be a Class I variety and spaced at 20-30 ft.
|
Routing - PUBLIC WORKS | 7/14/1998 | | 7/15/1998 | | FAIL |
|
|
|
REQUIRES DRAINAGE PLAN REVISION.
|
Plans ACCEPTED BY PLAN CHECK | | | 7/14/1998 | | PASS |
|
|
|
|
Plan routing begun/NEW & ADDTN | | | 7/14/1998 | | |
|
|
|
|
Plans ACCEPTED BY PLAN CHECK | | | 7/13/1998 | | PEND |
|
|
|
REQUIRES 1. STRUCT. CALCS. 2. GRADING AND DRAINAGE PLANS WITH CALCS 3. STRUCT. DETAIL SHEETS NEED TO BE STAMPED AND SIGNED BY ENGINEER. CONTACTED JOHN COOK OF THESE NEEDS. 7-14-98 RECEIVED 1. STRUCT. CALCS. 2. SIX GRADING AND DRAINAGE PLANS WITH CALCS. 3. TWO COPIES OF STAMPED AND SIGNED STRUCT. DETAIL SHEETS READY TO ROUTE.
|
Routing Off Site - STRUCTURAL | 7/13/1998 | | 7/13/1998 | | |
|
|
|
PER MIKE P. WE WILL DO ENG. IN HOUSE.
|
Received Certificate of Value | | | 7/13/1998 | | PASS |
|
|
|
|
Application received | | | 7/10/1998 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/10/1998 | | PEND |
|
|
|
|