Information based on query as of Sunday, August 18, 2024.
Permit Information
Permit NumberBLD98-02108
StatusFinaled
Name ST LUKES RMC OFFICES
Site Address 373 W FORT ST
Project NameST LUKES-OFFICES
Customer Number 
ePlanReviewNo
Description
To remodel a 11,000 sq.ft. two story building for offices and construct two (2) new exterior stairways per approved plans on file. New exterior stairways will include an area of refuge on each landing at both levels. Work to include demolition of interior as indicated on plans. To construct new interior nonbearing walls to create office areas, a new stairway and elevator lift for accessibility to both levels within an existing building per Appendix Ch. 11, 1994 UBC. Notes & attachments to plans from plan review staff are considered a part of the approved plans and required compliance for final approval and occupancy. All per approved plans. (P.C.#475-98)/drs
Contact Information
See Activities list for contact information
Color Key
Current location of plans being reviewed:  
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Fee Review-notes10/6/1998 4/20/1999
Permanent Occupancy 3/31/19993/31/1999 DONE
Details
Permanent occupancy  3/31/1999 PASS
Perm. Occ. Cert. #7713 issued 3-31-99 to St. Luke's RMC.
INSP - Final3/29/19993/30/19993/30/1999APASS
Details
03/30/99 338 - Scheduled by Hello!. Contact phone is [3812023].
Code Occupancy Approval  3/24/1999 PASS
Checked site and found handicap areas marked , landscape ok and concret ramp added for handicap access. Signed permanent.
Code Occupancy Approval  3/22/1999
Final Occupancy requested by Dan Wilson @ ###-####.
INSP - Final3/18/19993/19/19993/19/1999AFAIL
Details
03/19/99 338 - need the diffusers attached properly and zoning signoff
INSP-Final Inspection3/17/19993/18/19993/18/1999APASS
DetailsRick Jackson
Scheduled by Hello!. Contact phone is [3812023]. occ approved
INSP - Framing/Rough-in1/11/19991/12/19991/12/1999AFAIL
DetailsJim Storey
01/12/99 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED only two areas
INSP - Framing/Rough-in12/28/199812/28/199812/28/1998PPASS
Details
12/28/98 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in12/17/199812/17/199812/17/1998PPASS
Details
12/17/98 333 - FIRST FLOOR CEILINGS OK
INSP - Framing/Rough-in12/7/199812/8/199812/8/1998APASS
Details
12/08/98 333 - FRAM-OK FRAMING
INSP - Framing/Rough-in11/23/199811/23/199811/23/1998PPART
Details
11/23/98 333 - FRAM-OK FRAMING
INSP - Foundation10/16/199810/19/199810/19/1998PPASS
Details
10/19/98 333 - Scheduled by Hello!. Contact phone is [3447337]. FDN -OK FOUNDATION
INSP - Foundation10/12/199810/13/199810/13/1998APASS
Details
10/13/98 333 - DAN ###-#### ###-#### CELL FDN -OK FOUNDATION
INSP - Foundation10/9/199810/12/199810/12/1998APASS
Details
10/13/98 333 - Scheduled by Hello!. Contact phone is [3812023]. FDN -OK FOUNDATION
Issue PAID IN FULL permit  10/2/1998
Print Occupancy Form  9/30/1998
Inspection Record Card- Bld  9/30/1998
Meeting  9/29/1998
Meeting with Julia Davis, ZGA Architects to review stairs and process plans for permit issuance.
PLANS/APPL TAKEN TO FRONT DESK  9/29/1998 PASS
Plan resubmittals received  9/29/1998 PASS
Received stair details for bolt placement.
Plan assigned to (DRS)7/21/1998 9/29/1998 PASS
DetailsDan Stuart
09/29/98 15:06:29 DAR - this action updated by action script from <<>> in Case No. BLD98-2108
Plan resubmittals received  9/28/1998 PEND
RECEIVED NEW SUBMITTALS FOR PROJECT. pARTS OF CORRECTION NUMBER FIVE WAS NOTE ANSWERED. NOTIFIED ARCHITECT OF PROBLEM. ASSEMBLED NEW SHEETS WITH ORIGINALS.
Telephone call  9/28/1998
CALLED ART ALBANESE TO REVIEW THE PORTION OF PLAN REVIEW COMMENTS THAT WERE NOT ANSWERED BY THE RE-SUBMITTALS OF 9/25/98
Plan resubmittals received  9/25/1998
RECEIVED 2 COPIES OF REVISED SHEETS A1.0, A2.1, A2.2, A2.3, AND A3.0. ONE COPY OF COMMENT RESPONSE LETTER, AND ONE COPY OF ACCESS INDUSTRIES, IN. SHOP DRAWING. ROUTED TO DAN S.
Plan resubmittals requested  9/16/1998 HOLD
Required new submittals & or clarrifications list faxed and mailed to architect, Art Albanese.
Routing - PLAN CHECK9/14/1998 9/16/1998 HOLD
Plans forwarded to Fire Dept. for review while waiting for architects response to Bulding Dept. Plan Review.
Plan Review Completed(1st rev)  9/16/1998 FAIL
UBC
Print Pending Permit.LaserJet4  9/16/1998
Routing - FIRE9/16/1998 9/16/1998 PASS
Routing - PLAN CHECK7/30/1998 9/14/1998
Picked up plan to start review.
Routing - PUBLIC WORKS7/28/1998 7/30/1998 PASS
Routing - PLANNING7/28/1998 7/28/1998 PASS
Plan routing begun/TENANTS  7/21/1998
Route to PLANNING, PUBLIC WORKS, PLAN CHECK and FIRE.
Routing - PLANNING7/21/1998 7/21/1998 PEND
Design Review approved per DRH97-0187.
Plan assigned to (MYS)7/15/1998 7/21/1998
DetailsMarlene Southard
Recd Pcfee & Taken To Pln CK  7/15/1998 PASS
Application received  7/15/1998
Routing - PLAN CHECK9/16/1998