Permit Information
Permit NumberBLD98-02110
StatusFinaled
Name VIEW POINTE INVESTORS, LLC
Site Address 1501 S FEDERAL WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
("VIEW POINTE" - EXTERIOR FACADE & ENTRANCE CANOPIES) This building is not fire sprinkled. To modify the exterior facade of an existing building. Work is to include an approved EIFS on the outside of all exterior walls, an entrance canopy on the North, and an entrance canopy on the West. An existing wall is being upgraded to comply as a 4-hr area separation wall to separate different types of construction. All work shall comply with the approved drawings and plan review conditions on file. Interior work will be covered under a future permit. This permit is not intended to establish a Certificate of Occupancy. DRH-98-0094 PC-473-98 **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Expired/Cancelled  8/18/2003 DONE
BLD-Final4/4/20014/4/20014/4/2001PPASS
DetailsJim Storey
tammy ###-####
INSP - Final2/16/19992/16/19992/18/1999PFAIL
DetailsJim Storey
02/16/99 301 - PENDING SPECIAL INSP. REPORT FINAL.
INSP - Final2/16/19992/16/19992/16/1999 NR
DetailsJim Storey
02/16/99 301 - front landing ok ada at curb cut ok ceilling at entry ok
INSP - Framing/Rough-in10/29/199810/29/199810/29/1998 PASS
DetailsJim Storey
10/28/98 301 - south wall framing ok
INSP - Framing/Rough-in10/27/199810/27/199810/27/1998PPART
DetailsJim Storey
10/27/98 301 - steve ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Foundation10/27/199810/27/199810/27/1998PPART
DetailsJim Storey
10/27/98 301 - steve ###-#### footing FTG -OK FOOTING
INSP - Framing/Rough-in10/7/199810/7/199810/7/1998 PASS
DetailsJim Storey
/ / 301 - recieved resubmittal of briggs engineering of weld connectio screws. archived to approved plan.
INSP - Wall cover10/2/199810/2/199810/2/1998 FAIL
DetailsJim Storey
/ / 301 - CORR-CORREC-CALL FOR REINSP WHEN COMPLETED
INSP - Framing/Rough-in10/2/199810/2/199810/2/1998 FAIL
DetailsJim Storey
/ / 301 - STEVE ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED NL -OK FINAL
INSP - Framing/Rough-in9/30/199810/1/199810/1/1998APART
DetailsJim Storey
10/01/98 301 - STEVE ###-#### CORR-CORREC-CALL FOR REINSP WHEN COMPLETED ok to start cover need clearifacation form engineer and engineers report of field review.
Plan Reviewer's activity  9/10/1998 PASS
Drawings approved with conditions as noted and attached to the approved drawings.
Issue PAID IN FULL permit  9/10/1998
testing condition printout  9/10/1998
PLANS/APPL TAKEN TO FRONT DESK  9/10/1998 PASS
Telephone call  9/10/1998
said they would be in
Print permit w/o conditions  9/10/1998
Inspection Record Card- Bld  9/10/1998
Plan assigned to (CJW)7/20/1998 9/10/1998 PASS
DetailsCarl Westfall
09/10/98 10:06:47 CJW - this action updated by action script from <<>> in Case No. BLD98-2110
Routing - PLAN CHECK7/27/1998 9/10/1998
Plan resubmittals received  9/3/1998
RECEIVED TWO COPIES OF REVISED SHEETS A2-1, A3-1, A4-1, A4-2, A4-3, A4-4, A5-2, A7-1, A7-2, A7-4, A7-5, A8-1, A8-2, A8-3,. ONE COPY OF ATTACHED TECHNICAL DATA AND ONE COPY OF ENG. FROM BRIGGS ENG. ROUTED TO CARL W.
Meeting  8/6/1998
Meet with the Architect (Jerry Teal) and went through the plan review report. Gave him a copy at this meeting.
Plan Reviewer's activity  7/29/1998
UBC plan review started July 29, 1998 and finished August 5, 1998. A response from the Architect is required. See conditions list.
Routing - PLANNING7/21/1998 7/27/1998 PASS
approved per DRH98-0094.
Plan assigned to (MYS)7/15/1998 7/20/1998
DetailsMarlene Southard
Plan routing begun/TENANTS  7/20/1998
Route to PLANNING and PLAN CHECK.
Application received  7/15/1998
Recd Pcfee & Taken To Pln CK  7/15/1998
INSP - Framing/Rough-in11/30/199812/1/199812/19/1980APASS
DetailsJim Storey
12/01/98 301 - both entrys ok for cover.